Anthropic / Lambda compute deal, November 2026

Announced Nov 2, 2026 · Undisclosed · $41.3B · Terms extend into 2034

Anthropic's November 2, 2026 Form S-1/A discloses agreements with Lambda entered in May, June, and August 2026, with aggregate spend of approximately $41.3B over terms extending into 2034. Fees accrue only as capacity is delivered and accepted. The August agreement represents about $34.9B and can be terminated by either party if Lambda does not secure the facility lease on time. Other commitments are generally non-cancelable subject to stated exceptions, including delivery milestones. The filing does not disclose capacity in MW, sites, or a first-delivery date. The agreement-level spend is counted once; the separate Anthropic portfolio commitment disclosure is not additive.

First-capacity target: not disclosed

Assess the delivery assumptions

Check the site, power connection, permits, and delivery milestones behind this agreement with GreenCIO.