Research / Infrastructure

AI compute deals. When will the power arrive?

Who is buying capacity, who is building it, and when it is expected. Agreements and projects across AI labs, cloud providers, and neoclouds.

Dataset updated Oct 28, 2026 · Latest announcement Oct 27, 2026

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases8.21 GW10.5 GW300 MW
IT power leases3.273 GW—200 MW
Campus projects4.851 GW685 MW—

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

USD compute agreements

$466.1B

Stated contract values over their full terms

Additional upper-limit values

Up to $210.5B

Additional minimum values

Over $401.2B

29 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.

Compare buyers · 49 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
CoreWeave7———4 of 7
Meta5———1 of 5
SpaceX1———0 of 1
Crusoe7———4 of 7
Nebius3———1 of 3
General Compute2———2 of 2
Aolani1———1 of 1
doubleAI1———0 of 1
Microsoft12———9 of 12
Moore Threads1———0 of 1
Oracle1———0 of 1
Genesis Mission Consortium1———0 of 1
Applied Digital1———1 of 1
Google4———1 of 4
atNorth1———0 of 1
Qai1———0 of 1
RHAELM1———1 of 1
Undisclosed buyer20———7 of 20
Gimlet Labs1———1 of 1
Anthropic105.46 GW6 GW300 MW5 of 10
Alibaba Cloud2———0 of 2
Thinking Machines Lab1———0 of 1
Perplexity1———0 of 1
JD Cloud1———0 of 1
OpenAI102.75 GW4.5 GW—1 of 10
Palantir1———0 of 1
Figure1———1 of 1
Runpod1———1 of 1
SK Horizon1———0 of 1
Hudson River Trading1———0 of 1
QumulusAI1———1 of 1
Axe Compute1———0 of 1
Mistral AI2———1 of 2
Together AI1———1 of 1
IMC1———0 of 1
Flow Traders1———0 of 1
Nscale8———4 of 8
SK Hyper2———2 of 2
Huawei1———0 of 1
NVIDIA3———0 of 3
Firmus4———0 of 4
Yotta1———0 of 1
Jane Street1———0 of 1
Fluidstack1———1 of 1
Amazon Web Services1———1 of 1
xAI1———0 of 1
Cohere1———0 of 1
Sarvam AI1———0 of 1
Tencent1———1 of 1

Time to Power

When is capacity expected?

53 dated targets · 81 without a first-capacity window

Assess a site →

2 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

Reported delivery

atNorth / CoreWeave · MW undisclosed · majority of planned it capacity online

CoreWeave did not state the exact live MW quantity, initial online date, or metered energized power.

Company update · 2026-10-27 ↗

Polar Data Centers / Crusoe · 12 MW dra01 is live and powering crusoe cloud

Polar and Crusoe state that DRA01 provides 12 MW of IT capacity and is live. The announcement does not give a utility energization date.

Company update · 2026-10-21 ↗

Moore Threads / Moore Threads · MW undisclosed · phase one reported at full load

Moore Threads reports full-load operation but gives no MW, GPU count, or utility-metered power.

Company update · 2026-10-16 ↗

QumulusAI / Runpod · MW undisclosed · all 616 gpus active; deployment completed in august ahead of the september 1 target

QumulusAI reports all 77 nodes active across two one- and two-year reserved-capacity agreements. It does not disclose MW or where within its US data-center footprint the GPUs are hosted.

Company update · 2026-09-03 ↗

QumulusAI / Undisclosed buyer · MW undisclosed · final b300 handoff completed october 1; all gpus under the agreement in production and billing

QumulusAI says B200 handoff occurred September 8 and final B300 handoff at its Kansas City site occurred October 1. It does not state agreement-specific MW. The release separately reports portfolio totals of 7 MW active, 1 MW energized but awaiting customer handoff, and 3.75 MW at Atlanta targeted for early 2027; these values are not allocated to this customer.

Company update · 2026-10-15 ↗

QumulusAI / Undisclosed buyer · MW undisclosed · full customer handoff in philadelphia; agreement live and in production

QumulusAI reports full handoff on September 1 at its Philadelphia colocation site. The GPU count, site MW, IT load, and utility energization date are undisclosed.

Company update · 2026-09-10 ↗

China Telecom / Huawei · MW undisclosed · 11,520-card ascend cluster reported launched

The government report says the 11,520-card cluster launched on July 9. China Telecom reports 30 supernodes and 9,000 PFLOPS FP16. Neither figure is MW, IT load, or an energization measurement.

Company update · 2026-07-10 ↗

Sharon AI / Undisclosed buyer · MW undisclosed · initial ai cloud deployment delivered and accepted by customer

Sharon AI says the customer accepted an initial deployment under the five-year agreement. The release does not identify the specific site, GPU count, customer MW, or utility energization date.

Company update · 2026-08-20 ↗

SpaceX / Anthropic · MW undisclosed · compute capacity ramped during may and june

SpaceX's prospectus describes Anthropic service agreements across Colossus 1 and 2, with approximately 325,000 GPUs and fees ramping during May and June. It does not allocate delivered capacity to Colossus 1, state delivered MW, or give an energization date. This is partial ramp evidence, not confirmation that all Colossus 1 capacity was delivered.

Company update · 2026-06-05 ↗

China Telecom / Alibaba Cloud · MW undisclosed · ten-thousand-card-class cluster reported online

The official report says the cluster went online on April 3 and served government, health, and industry workloads. It does not give an exact accelerator count, MW, critical IT load, or utility energization date.

Company update · 2026-04-04 ↗

Verne / Nscale · 7.5 MW first phase complete; 7.5 mw of gpu capacity deployed

Verne says 7.5 MW was deployed in the first phase, with 128 racks including 64 liquid-cooled NVIDIA GB300 racks. This is a first phase of the 15 MW agreement, not full delivery of the contracted amount.

Company update · 2026-04-23 ↗

IREN / Microsoft · 50 MW horizon 1 delivered

First 50 MW IT deployment delivered to Microsoft in August 2026; part of the 200 MW contract. Exact energization date undisclosed. Horizon 2 was commissioning; Horizon 3–4 targeted Q4 2026 delivery.

Company update · 2026-08-27 ↗

Firmus / Firmus · MW undisclosed · firmus and cdc said they had mutually agreed not to proceed with the proposed development partnership

DCD reported approximately 42 MW deployed at CDC's Melbourne facility and said the site would not reach the prior 150 MW plan. The report does not state the MW basis or deployment date. CDC said it continues to provide infrastructure to Firmus. No dated energization milestone was verified.

Company update · 2026-10-06 ↗

Nscale / Microsoft · MW undisclosed · nscale filing states more than 12,600 gpus deployed for microsoft

Nscale's September 18 Form S-1 says more than 12,600 Grace Blackwell Ultra GPUs were deployed at the first SINES building for Microsoft. It does not give a customer service start date, Microsoft IT-load allocation, or utility energization date.

Company update · 2026-09-18 ↗

Ionic Digital / Nscale · 234 MW ionic reports operating leased capacity; monthly rent began

Ionic states the Ward County campus is energized and operating and reports rent commencement for the 234 MW Nscale lease in August 2026. This verifies facility capacity under lease, not Microsoft GPU service delivery.

Company update · 2026-08-19 ↗

Nebius / Microsoft · MW undisclosed · all contracted tranches delivered

Nebius reports delivery of all Microsoft contract tranches, including two in the preceding month. Customer MW and exact energization dates are undisclosed.

Company update · 2026-08-12 ↗

TeraWulf / Fluidstack · MW undisclosed · partial lease commencement

One Fluidstack lease had partially commenced by June 30. Customer-specific delivered MW are undisclosed; the original approximately 40 MW tranche is not confirmed in full.

Company update · 2026-08-05 ↗

MEEZA / Undisclosed buyer · 4 MW ready-for-service certificate signed; facility handed over on june 21, 2026

MEEZA confirms delivery of the 4 MW expansion to the unnamed hyperscaler. This is project capacity; IT-load versus facility-power basis remains undisclosed.

Company update · 2026-07-01 ↗

Applied Digital / CoreWeave · 250 MW ready for service

Polaris Forge 1 campus; 250 MW of critical IT load live as of October 1, 2026, out of 400 MW contracted. Ready for service is a company-reported operational milestone; it does not establish the date of utility energization.

Company update · 2026-10-07 ↗

2025

Original target passed

Nscale / InfraPartners

Glomfjord, Norway · Expanded facility targeted to go live in Q2 2025

First power · A first phase may cover only part of the agreement.

Assess delivery →

2025

Delivery reported

Microsoft / Nebius

Vineland, New Jersey, US · Late 2025 (announced target)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2025

Delivery reported

CoreWeave / Applied Digital

Ellendale, North Dakota, US · First 100 MW targeted for Q4 2025

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Delivery reported

Microsoft / Nscale / Start Campus

Sines, Portugal · Deployment targeted from Q1 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Delivery reported

Anthropic / SpaceX

Site not disclosed · Initial capacity ramped in May–June 2026; all contracted capacity was expected by December 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Delivery reported

Fluidstack / TeraWulf

Lake Mariner, New York, US · First approximately 40 MW targeted for first half of 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Delivery reported

Runpod / Runpod

Site not disclosed · All nodes active in August 2026; QumulusAI reports completion ahead of the September 1 target

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Delivery reported

Undisclosed buyer / Undisclosed AI inference platform

Site not disclosed · Q3 2026 target; B200 handoff September 8 and final B300 handoff October 1

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Original target passed

Microsoft / Nscale

Ward County, Texas, US · Phased delivery of AI infrastructure services targeted from Q3 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–2 months away

Undisclosed buyer / Undisclosed California neocloud provider

Michigan, United States · November 2026 target in September 17 update; not yet confirmed operational

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

1–3 months away

Undisclosed buyer / Undisclosed generative-AI inference platform

Site not disclosed · Capacity turnover expected in December 2026; no dated delivery or energization evidence

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–3 months away

Gimlet Labs / Cerebras

Site not disclosed · First Cerebras-powered Gimlet Cloud datacenter expected later in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–3 months away

QumulusAI / QumulusAI

Metropolitan Atlanta, Georgia, United States · Ready-for-service target Q4 2026, conditional on the current occupant transition; no completion evidence found

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–3 months away

Nebius / Nebius

Site not disclosed · First 328 MW fuel-cell project expected to be operational in 2026

First power · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–3 months away

Anthropic / CoreWeave

Site not disclosed · Later in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Delivery reported

Nscale / Verne

Iceland · Deployment planned in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–3 months away

OpenAI / Nscale / Aker

Kvandal, Narvik, Norway · 100,000 NVIDIA GPUs targeted by end of 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–3 months away

Tencent / Tencent Greater Bay Area Computing Center

Shaoguan, Guangdong, China · Shaoguan municipal government targeted project production by year-end 2026; no dated commissioning evidence found

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–6 months away

General Compute / Positron AI

Site not disclosed · Atlas systems expected to be available to General Compute customers beginning Q1 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–6 months away

General Compute / Cerebras

Site not disclosed · Customer availability targeted for Q1 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–6 months away

Microsoft / ChronoScale

North America; site undisclosed · Q1 2027 projected deployment completion

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–6 months away

Together AI / IBM Cloud

Site not disclosed · Expected availability Q1 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–9 months away

Crusoe / Energy Vault

Snyder, Texas, US · 1H 2027 (August target; July release said Q1 2027)

First power · A first phase may cover only part of the agreement.

Assess delivery →

2027

7–11 months away

Crusoe / Araico

Adjacent to the Itaipu substation, Paraguay · Initial deployment planned for mid-2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

11–15 months away

Crusoe / Polar Data Centers

Tørdal, Norway · Expected live in late 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

8–15 months away

Aolani / Aolani / undisclosed Malaysia data-center partners

Multiple sites, Malaysia · Second half of 2027 target under non-binding letters of intent

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Undisclosed buyer / Undisclosed AI inference platform

Metro Atlanta, Georgia, United States · Capacity turnover targeted for early 2027; no dated delivery or energization evidence

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

11–15 months away

Anthropic / Nscale

Mason County, West Virginia, US · Late 2027 reported target; not verified delivery or energization

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Google / Google / Blackstone

United States · site allocations undisclosed · Crux AI plans to bring its first 500 MW of TPU capacity online in 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

8–15 months away

Figure / Nscale

Barstow, Texas, United States · Initial GPU deployment targeted for H2 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Crusoe / Aalo Atomics

Idaho National Laboratory, Idaho, US · Crusoe Spark proof of concept targeted for 2027

First power · A first phase may cover only part of the agreement.

Assess delivery →

2027

8–15 months away

Nscale / Ionic Digital

Ward County, Texas, US · Ionic expects the additional power to be energized in the second half of 2027, subject to approval

First power · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Undisclosed buyer / Applied Digital

Boyce, Louisiana, US · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Undisclosed buyer / Applied Digital

United States; state not identified in cited release · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

8–15 months away

Anthropic / TeraWulf

Hawesville, Kentucky, US · Initial phases expected in the second half of 2027; full 401 MW expected in early 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

SK Hyper / SK Telecom / NVIDIA

South Korea; site allocation undisclosed · First AI factory planned to come online in 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

11–15 months away

Microsoft / Nscale / Start Campus

Sines, Portugal · Late 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Microsoft / Nscale

Narvik, Norway · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Anthropic / Google / Broadcom

Primarily United States · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Microsoft / Crusoe

Abilene, Texas, US · First building: mid-2027

First power · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Meta / Nebius

Multiple locations · not named · Early 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Microsoft / Nscale

Mason County, West Virginia, US · Late 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Mistral AI / EcoDataCenter

Borlänge, Sweden · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

CoreWeave / Applied Digital

Ellendale, North Dakota, US · 2027 (planned ready for service)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Amazon Web Services / SK Group

Ulsan, South Korea · Operations expected by 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

14–21 months away

Undisclosed buyer / Applied Digital

Southern United States; state undisclosed · First half of 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

14–21 months away

Nscale / Nscale

Mason County, West Virginia, US · 1H 2028

First power · A first phase may cover only part of the agreement.

Assess delivery →

2028

19–23 months away

CoreWeave / CoreWeave / AdaniConneX

Navi Mumbai, India · Mid-2028 (first phase expected to be available)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

14–27 months away

Microsoft / NiSource / NIPSCO

Northwest Indiana · campus location undisclosed · NiSource expects Microsoft to begin taking electric service in 2028 under a 20-year term

First power · A first phase may cover only part of the agreement.

Assess delivery →

2028

14–27 months away

Applied Digital / Applied Digital

Finland · Initial power availability anticipated beginning in 2028

First power · A first phase may cover only part of the agreement.

Assess delivery →

2028

14–27 months away

RHAELM / JERA / Dell Technologies

Chiba Thermal Power Station, Chiba, Japan · Operations targeted around 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

14–27 months away

CoreWeave / Local facility partners

Indonesia · three facilities · 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2029

26–39 months away

SK Hyper / SK Telecom / SK Hyper

South Korea; regional projects include Ulsan, Chungcheong, and Honam · First phase targets 5 GW of phased openings in 2029; long-term plan targets 15 GW total by 2035, subject to market demand

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 70 announcements disclose no MW allocation. 29 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

134 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Oct 27, 2026

CoreWeave

CoreWeave / atNorth

Campus build

Undisclosed

22.5 MW

Planned IT capacity at DEN01; CoreWeave says the majority is online, but does not quantify the live portion or report utility-metered power

Copenhagen, Denmark

The majority of planned IT capacity was online by October 27, 2026; the initial online date is not stated

In use at announcement
Deal details

CoreWeave says most of the planned 22.5 MW of IT capacity at atNorth DEN01 was online on October 27, 2026. The exact online quantity and initial service date are not disclosed. This is a named IT-capacity project, not a utility measurement of energized power. CoreWeave's 1.5 GW active-power and 4.2 GW contracted-power figures are company-wide snapshots from June and August, respectively, and are not added to this site record.

Hardware: NVIDIA Blackwell systems

CoreWeave Denmark deployment announcement ↗Assess this deal
Source ↗
Oct 26, 2026

Meta

Meta Platforms

Infrastructure financing

US$35B of launched public offerings; separate potential Class C share program of up to US$60B is not yet established

Undisclosed

Corporate equity financing; no project, site, or power quantity disclosed

Location undisclosed

No delivery date disclosed

Financing announced
Deal details

Meta launched approximately US$35B in public offerings: US$22.5B of Class A common stock under forward sale agreements and US$12.5B of mandatory convertible preferred shares. Meta also plans a separate at-the-market Class C offering of up to US$60B after the class begins trading; the program is not yet established. Meta says the offerings support continued investment in AI infrastructure, but proceeds are for general corporate purposes. Nvidia, AMD, and Broadcom expressed non-binding interest in buying up to US$5B of Class A shares; this is not a committed purchase and is not added. These financing amounts are not project capex, a compute agreement, or MW capacity, and are excluded from financial totals.

Meta investor release on public offerings, October 26, 2026 ↗Assess this deal
Source ↗
Oct 26, 2026

SpaceX

SpaceX / Apollo-managed lessor

Infrastructure financing

Approximately US$40B aggregate scheduled principal payments under contemplated lease schedules; excludes interest and other costs

Undisclosed

GPU pods and related equipment for data centers selected by SpaceX; quantity, sites, and power basis undisclosed

Location undisclosed

GPU deliveries and lease schedules expected to start in the first half of 2027; not a site energization date

Financing announced
Deal details

SpaceX entered a binding commitment letter on October 24, 2026 for a master finance lease with an Apollo-managed entity. The lessor would acquire and lease GPU pods and related equipment to SpaceX. SpaceX expects approximately US$40B in aggregate principal payments over the lease schedules. The master lease remains subject to closing conditions and definitive documentation; SpaceX expects closing before year-end 2026. No GPU count, equipment price, MW quantity, named data-center site, or energization evidence is disclosed. Principal payments are financing obligations, not project capex or compute-contract value, and are excluded from financial totals.

Hardware: GPU pods and related equipment; manufacturer and quantity not stated in the filing

SpaceX Form 8-K, October 26, 2026 ↗Assess this deal
Source ↗
Oct 22, 2026

Crusoe

Araico

Strategic partnership

Undisclosed

106 MW

Path to scale to 106 MW of IT capacity; not the initial deployment capacity. Further expansion to approximately 280 MW total is an option and its measurement basis is unspecified.

Adjacent to the Itaipu substation, Paraguay

Initial deployment planned for mid-2027

7–11 months to target

Agreement signed
Deal details

Crusoe and Araico announced a strategic partnership on October 22, 2026, for AI Cloud infrastructure adjacent to the Itaipu substation. The first deployment is planned for mid-2027. Crusoe describes a path to 106 MW of IT capacity and long-term options to expand to approximately 280 MW total, but it does not state when the 106 MW scale-up will be reached. The 106 MW is not initial capacity; the optional 280 MW is not additive and its basis is not specified. No investment amount or compute contract value is disclosed. This is not Araico's separately announced Iguazu AI Campus, and its campus estimates are not assigned here.

Crusoe-Araico Paraguay AI Cloud partnership announcement ↗U.S. Department of State Paraguay fact sheet ↗Assess this deal
Source ↗
Oct 21, 2026

Crusoe

Polar Data Centers

Campus build

Undisclosed

12 MW

IT capacity

Tørdal, Norway

No delivery date disclosed

In use at announcement
Deal details

Polar and Crusoe report DRA01 as live, with 12 MW of IT capacity powering Crusoe Cloud. The stated capacity is IT load, not campus or utility power. The October 21 report date does not establish the energization date.

Polar and Crusoe partnership expansion ↗Assess this deal
Source ↗
Oct 21, 2026

Crusoe

Polar Data Centers

Campus build

Undisclosed

40 MW

Additional critical liquid-cooled IT capacity

Tørdal, Norway

Expected live in late 2027

11–15 months to target

Build announced
Deal details

Crusoe and Polar plan DRA02 as a separate phase with an additional 40 MW of critical liquid-cooled IT capacity, expected to go live in late 2027. This is a target, not delivery evidence. It is separate from the 12 MW live at DRA01.

Polar and Crusoe partnership expansion ↗Assess this deal
Source ↗
Oct 21, 2026

Nebius

Nebius AI Builder Program participants

Strategic partnership

$10 million in additional compute grants

Undisclosed

Grant program; recipient allocation, GPU quantity, IT load, and facility power are undisclosed

Location undisclosed

No delivery date disclosed

Compute credits pledged
Deal details

Nebius announced an additional $10 million in compute grants for its AI Builder Program across Europe. The announcement also describes public GPU spot pricing; pricing availability is not a signed customer agreement. Grant value is a program commitment, not a customer contract or infrastructure investment. Recipient allocations and MW are not disclosed.

Nebius expands AI Builder Program with compute grants ↗Assess this deal
Source ↗
Oct 20, 2026

General Compute

Positron AI

Strategic partnership

Undisclosed

Undisclosed

Customer availability target; system count, site and power allocation undisclosed

Location undisclosed

Atlas systems expected to be available to General Compute customers beginning Q1 2027

2–6 months to target

Agreement signed
Deal details

Positron says General Compute will purchase Atlas systems and has committed to purchasing next-generation Titan systems. Positron states that Atlas will expand customer availability beginning in Q1 2027. System quantities, purchase value, site, MW, and the Titan delivery schedule are undisclosed. Positron's separate $875 million Series C is not this agreement's value or site investment. The Q1 target is customer availability, not dated delivery or proof of energized power.

Hardware: Positron Atlas inference systems; commitment to next-generation Titan systems

Positron, General Compute Atlas purchase and Titan commitment ↗Assess this deal
Source ↗
Oct 19, 2026

Aolani

Aolani / undisclosed Malaysia data-center partners

Campus build

Undisclosed

Up to 500 MW

Up to 500 MW across multiple unnamed Malaysian sites under non-binding letters of intent; IT-load versus facility-power basis is not stated

Multiple sites, Malaysia

Second half of 2027 target under non-binding letters of intent

8–15 months to target

Letter of intent
Deal details

Aolani announced non-binding letters of intent for up to 500 MW of data-center capacity across unnamed Malaysian sites, with capacity targeted to start coming online in the second half of 2027. Definitive agreements remain subject to negotiation and execution. Aolani's separate approximately 80 MW already committed in 2026 and its projected 580 MW 2027 total are portfolio figures and are not added to this project record.

Hardware: AI data centers and GPU deployments; quantities not stated

Aolani letters of intent for Malaysian capacity ↗Assess this deal
Source ↗
Oct 19, 2026

doubleAI

Bynet Data Communications / NVIDIA

Campus build

Undisclosed

Undisclosed

doubleAI describes the cluster as 2 MW of power; the source does not state whether this is IT load or facility power

Israel · site undisclosed

doubleAI says it is building a 1,024-NVIDIA-B300-GPU cluster in 128 DGX servers; no service, delivery, or energization date is stated

Build announced
Deal details

doubleAI says it is building a 1,024-B300 cluster in 128 DGX servers with Bynet Data Communications, MedOne, and NVIDIA. The company describes the system as totaling 2 MW of power but does not define the measurement as IT load or facility power. The company post showed a relative publication age, so the exact post date is not established; the record date is the dated October 19 Wall Street Journal report that identified the chip purchase. The source does not name a site or give a delivery, service, or energization target. Keep the 2 MW out of capacity analytics and do not infer operational capacity. The reported $220 million funding and chip purchase cost are not separated or quantified and are not entered as a contract value or infrastructure investment.

Hardware: 1,024 NVIDIA B300 GPUs in 128 DGX servers

The Wall Street Journal report, October 19, 2026 ↗doubleAI company post on its cluster build (date displayed relatively by LinkedIn) ↗Assess this deal
Source ↗
Oct 16, 2026

Microsoft

NiSource / NIPSCO

Power supply

Undisclosed

About 1.1 GW

Approximate addition to NiSource Generation Company's shared generation-resource pool; not Microsoft's campus load, a data-center allocation, or delivered/energized power

Northwest Indiana · campus location undisclosed

NiSource expects Microsoft to begin taking electric service in 2028 under a 20-year term

14–27 months to target

Agreement signed
Deal details

NiSource announced a long-term electricity agreement for Microsoft's previously announced northwest Indiana campus. Microsoft is expected to begin taking service in 2028 under a 20-year term. NiSource says its GenCo-owned shared resource pool will add approximately 1,100 MW of generation resources, and Microsoft will fund the generation and transmission required for its load. The release does not state Microsoft's load in MW, identify the campus site, or report delivered power. The 1,100 MW describes generation resources in a shared pool, not data-center capacity; it is excluded from compute, IT-load, campus, and energized-power totals. NiSource separately disclosed a 600 MW battery contract for shared pool resources. The release does not establish whether that 600 MW is included in or additional to the approximately 1,100 MW portfolio increase, so the figures are not added together. The 2028 service target is not evidence that the campus or all generation assets will be energized by then.

NiSource announcement, October 16, 2026 ↗Business Wire distribution of NiSource announcement, October 16, 2026 ↗Assess this deal
Source ↗
Oct 16, 2026

Moore Threads

Wuxi (Huishan) Domestic AI Computing Center

Strategic partnership

Undisclosed

Undisclosed

Phase one reported at full load; MW, IT load, GPU count, and metered power are undisclosed

Huishan, Wuxi, Jiangsu, China

No delivery date disclosed

In use at announcement
Deal details

Moore Threads reported that phase one of the Wuxi (Huishan) domestic intelligent-computing center was operating at full load on October 16, 2026. The source identifies Moore Threads full-stack systems and MTT S5000 accelerators, but gives no MW quantity, facility-power basis, total GPU count, or first energization date. The operating statement is delivery evidence; it does not establish metered energized MW.

Hardware: Moore Threads full-stack compute; MTT S5000 GPUs identified in company report

Moore Threads Wuxi phase-one operating update ↗Assess this deal
Source ↗
Oct 15, 2026

Oracle

Project Jupiter onsite fuel-cell microgrid

Power supply

Undisclosed

Up to 2.45 GW

Up to 2.45 GW of planned installed fuel-cell generation capacity; not IT load, campus load, or energized power

Doña Ana County, New Mexico, US

No delivery date disclosed

Build announced
Deal details

Oracle and Yucca Growth Infrastructure proposed a refinement to Project Jupiter's Bloom Energy fuel-cell microgrid on October 15. Oracle said planned data-center IT capacity remained unchanged. Its October 22 power-plan article states up to 2.45 GW of installed fuel-cell generation capacity. The plan remains subject to state permit review. The 2.45 GW is generation equipment rating, not customer IT load or measured energized power; no commissioning date or delivered MW is stated. Do not add this figure to the separate 4.5 GW compute-capacity amount in the OpenAI/Oracle Stargate record.

Oracle and Yucca Growth Infrastructure Project Jupiter permit refinement ↗Oracle Project Jupiter self-supplied power plan, October 22, 2026 ↗Oracle Project Jupiter scope update, October 13, 2026 ↗Assess this deal
Source ↗
Oct 8, 2026

Genesis Mission Consortium

Crusoe Cloud

Strategic partnership

$50 million in AI compute credits over three years

Undisclosed

Compute credit commitment; GPU count, MW, and recipient allocation are undisclosed

United States

No delivery date disclosed

Compute credits pledged
Deal details

Crusoe pledged $50 million in high-performance AI compute credits over three years to the Genesis Mission Consortium. Credits will support workloads and technical assistance for researchers across more than 15 federal agencies. This is an in-kind compute pledge, not a cash contract, infrastructure investment, or disclosed GPU/MW allocation.

Crusoe compute-credit pledge for the Genesis Mission ↗Assess this deal
Source ↗
Oct 6, 2026

Applied Digital

Applied Digital

Campus build

Undisclosed

Up to 1 GW

Potential power capacity access for a planned campus; site details and customer allocations are not disclosed

Finland

Initial power availability anticipated beginning in 2028

14–27 months to target

Build announced
Deal details

Applied Digital says an agreement provides access to up to 1 GW of potential power capacity and that it plans an AI Factory campus of that scale. Initial power availability is anticipated beginning in 2028. The company is marketing the site and discussing potential customers; this is not a customer lease, contracted IT load, or delivered capacity. The target is a company forecast, not energization evidence.

Applied Digital Finland development announcement ↗Assess this deal
Source ↗
Oct 6, 2026

CoreWeave

CoreWeave / AdaniConneX

Campus build

Undisclosed

240 MW

Three 80 MW data-center buildings; IT-load versus facility-power basis is not stated

Navi Mumbai, India

Mid-2028 (first phase expected to be available)

19–23 months to target

Build announced
Deal details

CoreWeave plans 240 MW of data-center capacity across three 80 MW buildings at AdaniConneX's Taloja campus. CoreWeave is the sole tenant and plans to deploy Vera Rubin systems. The source does not define the MW basis. The first phase is expected to be available in mid-2028; this is a planned availability target, not delivery or energization evidence. A further 240 MW is an expansion opportunity and is not included.

Hardware: NVIDIA Vera Rubin platform planned

CoreWeave and AdaniConneX India campus announcement ↗Related: CoreWeave / CoreWeave / atNorth · 2026-10-27Assess this deal
Source ↗
Oct 6, 2026

Google

Constellation Energy

Strategic partnership

Undisclosed

890 MW

New nuclear generation capacity delivered to the PJM grid; not a data-center allocation

PJM Interconnection, United States

No delivery date disclosed

Agreement signed
Deal details

The 20-year agreement covers 890 MW of new nuclear capacity from uprates at 11 Constellation units, with the first uprate expected in 2028. A separate 15-year agreement supports 2,700 MW from existing generation on the PJM grid. Neither amount is a Google data-center allocation or evidence of energized data-center power. Constellation's stated $4.3B investment is not Google's contract value and is excluded.

Google and Constellation, PJM power agreement ↗Assess this deal
Source ↗
Oct 5, 2026

atNorth

atNorth

Campus build

Approximately €2 billion for the Salo site; excludes customer-owned servers and installation

Up to 230 MW

Path to power for the wider development; the first phase is planned at 75 MW with power secured; source does not state critical IT load

Salo, Finland

No delivery date disclosed

Build announced
Deal details

atNorth announced a new 28.6-hectare site. The first 75 MW phase has secured power; the wider development has a path to power of up to 230 MW. The source does not give a first-capacity date. The approximately €2B site investment excludes customer servers and installation; the separate estimate of up to €10B for customer equipment is not included. No USD investment total is inferred.

atNorth FIN05 announcement ↗Assess this deal
Source ↗
Oct 4, 2026

Qai

MEEZA

Cloud compute

Undisclosed

Undisclosed

GPU infrastructure hosted in one MEEZA data centre in Qatar; GPU quantity, IT load, and facility MW are undisclosed

Qatar

No delivery date disclosed

Agreement signed
Deal details

Qai will deploy GPU infrastructure in one of MEEZA's Qatar data centres. MEEZA will provide hosting, high-density power, and managed services. The parties did not disclose GPU count, MW, contract value, or a date for first service. This is separate from MEEZA's 4 MW hyperscaler expansion; no site link was stated.

Hardware: Advanced GPU infrastructure; generation and quantity undisclosed

Qai and MEEZA AI infrastructure agreement ↗Qatar News Agency, October 4, 2026 ↗Assess this deal
Source ↗
Oct 1, 2026

RHAELM

JERA / Dell Technologies

Campus build

>US$15B total project capital deployment across all phases; not a customer contract

Up to 400 MW

Supported site power capacity; not stated critical IT load or energized compute

Chiba Thermal Power Station, Chiba, Japan

Operations targeted around 2028

14–27 months to target

Build announced
Deal details

RHAELM and JERA are developing the Chiba project; Dell contributes a standardized AI infrastructure model. The 400 MW figure is power capacity supporting the project, with no critical IT allocation or energized quantity disclosed. More than US$15B covers land, power infrastructure, facility construction and AI compute across all phases; it is project capital, not contract value. Apollo is a planned financing partner. The separate national framework and possible 2030s sites are not additional projects.

RHAELM, JERA and Dell October 1 project announcement ↗RHAELM Japanese-language project announcement, October 1, 2026 ↗JERA October 1 announcement ↗Assess this deal
Source ↗
Sep 29, 2026

Meta

Firmus AI Factories

Cloud compute

Undisclosed

Undisclosed

GPU compute agreements; site capacity, contracted quantity, and expansion-option quantity are undisclosed

Southeast Asia

No delivery date disclosed

Agreement signed
Deal details

Firmus and Meta announced contracted GPU capacity and additional expansion options at Southeast Asian sites. The announcement does not give site names, MW, GPU count, value, or first-capacity timing. Firmus also says Meta already uses its Melbourne AI factory; the source does not tie that existing Australian use to the Southeast Asian agreements or assign it capacity.

Firmus and Meta strategic infrastructure agreements ↗Assess this deal
Source ↗
Sep 29, 2026

General Compute

Cerebras

Strategic partnership

Undisclosed

Undisclosed

Location undisclosed

Customer availability targeted for Q1 2027

2–6 months to target

Agreement signed
Deal details

General Compute will finance and buy Cerebras systems to offer dedicated inference, initially for agentic coding. Agreement value, site, system count and MW are undisclosed. The separate $400M debt facility is not the purchase price. Q1 2027 is a service target, not dated delivery or energization evidence.

Hardware: Cerebras wafer-scale inference systems

Cerebras September 29 General Compute agreement ↗General Compute September 29 deployment announcement ↗Assess this deal
Source ↗
Sep 29, 2026

Undisclosed buyer

Undisclosed AI inference platform

Cloud compute

$211.9M · Three-year take-or-pay agreement; two one-year extensions are optional and excluded from the stated value

Undisclosed

More than 2,000 B300 GPUs across both September 29 agreements; per-customer GPU quantity and IT-load allocation are undisclosed. The 3.75 MW Atlanta site capacity is not assigned as customer IT load.

Metro Atlanta, Georgia, United States

Capacity turnover targeted for early 2027; no dated delivery or energization evidence

2–15 months to target

Agreement signed
Deal details

QumulusAI reports a three-year take-or-pay agreement worth US$211.9 million with a returning AI inference platform customer. It says the deal follows that customer's separate US$71.9 million agreement and targets capacity turnover in early 2027. The source combines GPU counts across this and another contract and does not disclose this customer's count. Two optional one-year extensions worth US$70.6 million each are excluded. The associated Atlanta site's up-to 3.75 MW is data-center capacity, not a disclosed customer IT allocation, and its MW basis is unknown.

Hardware: NVIDIA Blackwell B300 GPUs; exact customer allocation undisclosed

QumulusAI, US$240.9 million in two new customer contracts ↗Related: Undisclosed buyer / Undisclosed AI inference platform · 2026-07-28Related: QumulusAI / QumulusAI · 2026-08-20Assess this deal
Source ↗
Sep 29, 2026

Undisclosed buyer

Undisclosed generative-AI inference platform

Cloud compute

$29.1M · Three-year agreement; a two-year extension option worth US$19.4 million is excluded from the stated value

Undisclosed

More than 2,000 B300 GPUs across both September 29 agreements; per-customer GPU quantity and MW allocation undisclosed

Location undisclosed

Capacity turnover expected in December 2026; no dated delivery or energization evidence

1–3 months to target

Agreement signed
Deal details

QumulusAI reports a three-year agreement worth US$29.1 million with a returning generative-AI inference platform customer. It says the deal follows a separate two-year agreement worth more than US$32 million. Customer GPU quantity and MW are undisclosed; the September announcement gives more than 2,000 B300 GPUs combined across this and another new agreement. A two-year extension option worth US$19.4 million is excluded. December 2026 turnover is a target, not delivery evidence.

Hardware: NVIDIA Blackwell B300 GPUs; exact customer allocation undisclosed

QumulusAI, US$240.9 million in two new customer contracts ↗Related: Undisclosed buyer / Undisclosed generative-AI inference platform · 2026-07-23Assess this deal
Source ↗
Sep 28, 2026

Gimlet Labs

Cerebras

Strategic partnership

Undisclosed

100 MW

Planned inference deployment; facility versus critical IT basis unspecified

Location undisclosed

First Cerebras-powered Gimlet Cloud datacenter expected later in 2026

0–3 months to target

Build announced
Deal details

Planned 100 MW deployment across the partnership, not a disclosed customer purchase or energized power measurement. Site, contract value and first-phase MW are undisclosed. Existing private inference traffic does not establish delivery of the planned cloud datacenter. The initial 2026 datacenter target is distinct from 2027 CS-4 access.

Hardware: Cerebras wafer-scale systems with GPUs; CS-4 access expected in 2027

Gimlet September 28 Cerebras deployment announcement ↗Cerebras September 28 partnership release ↗Assess this deal
Source ↗
Sep 28, 2026

Google

Crusoe

Campus build

Undisclosed

Undisclosed

Armstrong County, Texas, United States

No delivery date disclosed

Build announced
Deal details

Google campus under construction since June 2025. Connected to Goodnight 1 wind farm (265.5 MW, operational) and Goodnight 2 (265.5 MW, under construction). Wind generation ratings are not campus load or energized IT capacity. Campus MW, agreement value and first-capacity date are undisclosed. Separate from Crusoe’s Abilene campuses.

Crusoe September 28 Google campus announcement ↗Assess this deal
Source ↗
Sep 24, 2026

Anthropic

Akamai

Cloud compute

$11.6B · Seven years from each project plan’s service start

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Project Plans 2 and 3 signed September 18 under the May 5 master agreement. Approximately $11.6B is subject to delivery, availability and termination provisions. Potential additional $9B, equity warrants and supplier capital spending are excluded. Site, MW and dated first service are undisclosed.

Hardware: CPU cloud infrastructure

Akamai September 24 Anthropic expansion ↗Akamai September 24 Form 8-K ↗Assess this deal
Source ↗
Sep 23, 2026

Alibaba Cloud

Alibaba Cloud

Campus build

Undisclosed

Undisclosed

Cloud-region expansion; no site, facility capacity, power allocation, or capital budget disclosed

Finland

Cloud region planned within 12 months of September 23, 2026; no facility power date stated

Build announced
Deal details

Alibaba Cloud plans to establish its first Finnish cloud region within 12 months. The company did not name a site, data-center partner, MW quantity, or investment amount. A cloud-region target is not a facility power or energization date.

Alibaba Cloud global infrastructure expansion ↗Assess this deal
Source ↗
Sep 23, 2026

Thinking Machines Lab

Crusoe

Cloud compute

$65 million annually; agreement term not disclosed

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

The $65M figure is an annual inference agreement; the term and MW allocation are not disclosed. Do not treat the annual amount as a full-term contract value or compute it as annual capital expenditure. Crusoe said total Managed Inference contracted annual revenue exceeded $100M; that portfolio figure overlaps this agreement and other customers.

Hardware: Dedicated NVIDIA HGX B200 systems with Quantum-2 InfiniBand

Crusoe and Thinking Machines Lab announce inference agreement ↗Assess this deal
Source ↗
Sep 18, 2026

Anthropic

Nscale

Cloud compute

Up to $44.6B · up to six years

About 460 MW

Reported compute capacity allocation; source does not specify IT-load versus facility-power basis and does not confirm energization

Mason County, West Virginia, US

Late 2027 reported target; not verified delivery or energization

11–15 months to target

Agreement signed
Deal details

Nscale's September 18 Form S-1 says four Anthropic Services Agreements signed August 25, 2026 provide for aggregate payments of up to approximately US$44.6 billion. CNBC reported that the six-year agreements cover about 460 MW of compute capacity at Monarch and that the campus was expected to come online at the end of 2027. The 460 MW and timing are reported terms, not utility measurements; the filing does not specify whether the MW figure is IT load or total facility power. Do not treat the capacity as energized or delivered. The agreement value is full-term service spend, not annual revenue or infrastructure capital expenditure.

Hardware: NVIDIA Vera Rubin

Nscale September 18, 2026 Form S-1 ↗CNBC report on Anthropic compute capacity, August 26, 2026 ↗Assess this deal
Source ↗
Sep 16, 2026

Anthropic

Zerra DC / Australian Data Centres / Macquarie Capital

Campus build

Undisclosed

Undisclosed

Western Downs, Queensland, Australia

No delivery date disclosed

Agreement signed
Deal details

The consortium signed lease documentation with an Australian Anthropic subsidiary for the first stage of Western Downs Digital Park, subject to customary approvals. The disclosure does not specify leased MW, contract value or delivery date. Consortium funding obligations also remain subject to approvals. Campus estimates are not an Anthropic allocation.

Dexus September 16 regulatory disclosure via EQS ↗Assess this deal
Source ↗
Sep 15, 2026

Perplexity

Crusoe

Cloud compute

Undisclosed

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Perplexity contracted Crusoe Cloud for model training and managed inference. Contract value, GPU count, MW allocation, sites and first-service date are undisclosed. Crusoe also plans to adopt Perplexity software for its employees; that reciprocal software purchase is not additional compute capacity.

Hardware: NVIDIA GB300 NVL72 clusters / InfiniBand

Crusoe September 15 partnership announcement ↗Assess this deal
Source ↗
Sep 9, 2026

Google

Google / Blackstone

Strategic partnership

$5 billion equity commitment; not a customer contract or construction spend

500 MW

Crux AI's planned first-phase TPU capacity; critical IT-load versus facility-power basis and site allocations are undisclosed

United States · site allocations undisclosed

Crux AI plans to bring its first 500 MW of TPU capacity online in 2027

2–15 months to target

Build announced
Deal details

Crux AI launched as the U.S.-based compute-as-a-service company formed through the Blackstone and Google TPU cloud venture. Crux says Blackstone funds committed $5 billion in equity and Google will provide TPUs, software, and services. Crux plans to bring its first 500 MW of TPU capacity online in 2027 as the initial phase of a multi-gigawatt roadmap. The 500 MW is provider-level planned compute capacity, not a customer allocation; the source does not define critical IT load versus facility power or disclose site allocations. Bloomberg reported delays at proposed sites, including Google's scrapped plan for Crusoe to build in Cheyenne, but did not quantify the affected share or report a revised Crux-wide target. Keep the 2027 target as announced; no dated operating or energization evidence is established. The $5 billion is an equity commitment to the platform, not customer contract value or disclosed construction spend, and is excluded from financial totals.

Hardware: Google Tensor Processing Units (TPUs)

Crux AI launch announcement, September 9, 2026 ↗Blackstone and Google TPU cloud joint venture announcement, May 18, 2026 ↗Google Cloud announcement, May 19, 2026 ↗Bloomberg report on Crux AI site delays, September 9, 2026 ↗Assess this deal
Source ↗
Sep 9, 2026

Google

Google Finland digital infrastructure program

Campus build

€13 billion Finland digital infrastructure, clean energy, and partnership investment program over two years

Undisclosed

Program covers multiple data centers, clean energy, and partnerships; no site-level capacity disclosed

Hamina, Kajaani, Muhos, and Vaala, Finland

No delivery date disclosed

Build announced
Deal details

Google announced a €13B two-year Finland program covering digital infrastructure, clean energy, and partnerships. This is not a site cost or contract value. Google named activity in Hamina, Kajaani, Muhos, and Vaala, but disclosed no site-level MW or first-capacity dates. On October 6, 2026, the Finnish Licensing and Supervision Agency asked Tuike Finland Oy to suspend work that significantly changes the environment at the planned Muhos and Kajaani sites by October 23, until the environmental impact assessments are complete. The notice does not cover planning, measurements, soil studies, or other low-impact and readily reversible work. It is a permitting and delivery risk, not evidence of energization or a revised delivery date.

Google Finland infrastructure announcement ↗Google Finland clean energy and infrastructure plan ↗Finnish Licensing and Supervision Agency notice, October 6, 2026 ↗Google Muhos location page, checked October 7, 2026 ↗Assess this deal
Source ↗
Sep 9, 2026

JD Cloud

JD Cloud / Moore Threads

Strategic partnership

Undisclosed

Undisclosed

Planned 100,000-GPU cluster; GPU count does not disclose MW, IT load, or facility power

Location undisclosed

No delivery date disclosed

Build announced
Deal details

Moore Threads announced a deep partnership with JD Cloud to plan a 100,000-card domestic intelligent-computing cluster on September 9, 2026. The announcement does not identify the site, GPU model, power quantity, IT load, value, or first-service date. The GPU target is not converted to MW or treated as a delivered fleet.

Hardware: 100,000 domestic GPUs; model and site allocation not disclosed

Moore Threads, JD Cloud cluster announcement ↗Assess this deal
Source ↗
Sep 8, 2026

OpenAI

Firmus AI Factories

Cloud compute

Undisclosed

Undisclosed

Dedicated compute agreement; site capacity and OpenAI allocation are undisclosed

Malaysia

No delivery date disclosed

Agreement signed
Deal details

Firmus and OpenAI announced a multi-year agreement for dedicated compute capacity at two Malaysian sites. They did not disclose the OpenAI MW allocation, contract value, or first-capacity date. Firmus's more-than-900 MW company-wide contracted-capacity figure includes multiple customers and is not assigned to this agreement.

Firmus and OpenAI Malaysia compute partnership ↗Assess this deal
Source ↗
Sep 8, 2026

Palantir

Nebius

Strategic partnership

Undisclosed

Undisclosed

Preferred sovereign AI infrastructure partnership; no customer allocation or MW quantity disclosed

Nebius infrastructure; customer locations not disclosed

No delivery date disclosed

Agreement signed
Deal details

Palantir named Nebius its preferred sovereign AI infrastructure partner. Following an integration period, Palantir customers can access Nebius compute and inference. The companies also plan to accelerate capacity deployments, including modular data centers at sites with available power. The announcement gives no contract value, customer allocation, MW quantity, or first-service date.

Company announcement ↗Assess this deal
Source ↗
Sep 7, 2026

Undisclosed buyer

MEEZA

Cloud compute

More than QAR 1 billion; contract term not disclosed

8 MW

Operational data centre services capacity at a planned campus; source does not define IT-load versus facility-power basis

Qatar; campus name not disclosed

No delivery date disclosed

Agreement signed
Deal details

MEEZA announced a long-term lease with an unnamed global hyperscaler for 8 MW of data centre services at an upcoming campus. MEEZA valued the agreement at more than QAR 1 billion. The customer, contract term, site name, delivery date, and IT-load versus facility-power basis are not disclosed. Keep its capacity and native-currency value out of aggregates. This is a separate announced contract, but the unnamed customer prevents overlap checks against the other MEEZA hyperscaler records.

MEEZA hyperscaler agreement for 8 MW ↗Data Center Dynamics reports MEEZA's 8 MW lease ↗MEEZA announcement reproduced by Mubasher ↗Assess this deal
Source ↗
Sep 3, 2026

Figure

Nscale

Cloud compute

$3.5B · Multi-year; exact term undisclosed

Undisclosed

Barstow, Texas, United States

Initial GPU deployment targeted for H2 2027

8–15 months to target

Agreement signed
Deal details

Initial compute commitment for Figure’s Helix models. Intent to expand above $6B is not an additional signed commitment. Nscale’s separate equity investment is undisclosed and excluded. GPU count is a potential upper limit; customer MW and energization date are undisclosed. Deployment target does not establish operational delivery.

Hardware: Potential deployment of up to 100,000 NVIDIA Vera Rubin GPUs

Nscale September 3 Figure agreement ↗Assess this deal
Source ↗
Sep 3, 2026

Runpod

Runpod

Cloud compute

Undisclosed

Undisclosed

616 NVIDIA RTX PRO 6000 Blackwell GPUs across two reserved-capacity agreements; MW and customer contract value undisclosed

Location undisclosed

All nodes active in August 2026; QumulusAI reports completion ahead of the September 1 target

Delivery reported

In use at announcement
Deal details

QumulusAI reports full deployment of 616 GPUs for Runpod in August 2026, ahead of the September 1 target. The agreements have different one- and two-year terms, but value and MW are not disclosed. QumulusAI says the GPUs are served from its existing US data-center footprint; no specific site or utility energization date is given.

Hardware: 616 NVIDIA RTX PRO 6000 Blackwell GPUs in 77 nodes

QumulusAI reports Runpod deployment completion ↗Assess this deal
Source ↗
Sep 1, 2026

Undisclosed buyer

Green Mountain

Campus build

Undisclosed

14 MW

Data centre capacity; IT versus facility power not specified

LON-East, Romford, London, UK

Capacity described as recently delivered; customer occupancy date undisclosed

Agreement signed
Deal details

An unnamed neocloud operator contracted 14 MW within the 37 MW LON-East campus. Company-reported facility delivery does not establish customer occupancy or a utility energization date. Price and term are undisclosed. The campus total is not the customer allocation.

Green Mountain September 1 company announcement ↗Assess this deal
Source ↗
Aug 31, 2026

Undisclosed buyer

E2E Networks

Cloud compute

Approx. INR 1,000 crore (excluding taxes)

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Binding term sheet with an unnamed sovereign AI company based in India for Blackwell cloud GPUs and allied services. Customer identity is undisclosed; do not attribute the order to Sarvam. Site, MW, GPU count and first-service date are undisclosed. Original INR value is retained without currency conversion.

Hardware: NVIDIA Blackwell cloud GPUs; count undisclosed

E2E Networks August 31 binding term sheet filing ↗Assess this deal
Source ↗
Aug 27, 2026

Microsoft

ChronoScale

Cloud compute

Undisclosed

50 MW

Approximate planned AI compute deployment; IT versus facility-power basis not disclosed

North America; site undisclosed

Q1 2027 projected deployment completion

2–6 months to target

Agreement signed
Deal details

ChronoScale announced plans for an approximately 50 MW Microsoft deployment on August 27. A ChronoScale filing says the parties entered a two-year strategic partnership on August 6, then extended the service term to three years on August 24. The filing targets projected completion in Q1 2027 and says delivery depends on financing and customary development, construction, and operational conditions. The North American site, contract value, and IT-load versus facility-power basis are not disclosed. This record tracks the planned customer deployment; it does not establish delivered or energized capacity.

Hardware: NVIDIA GB300 NVL72 systems with liquid cooling

ChronoScale announcement ↗ChronoScale Form 10-K, Microsoft partnership terms and conditions ↗Assess this deal
Source ↗
Aug 27, 2026

SK Horizon

SK Telecom / KKR / IMM Investment-Stonebridge

Campus build

KRW 3.08 trillion combined equity investment under a definitive agreement

318 MW

Portfolio figure covering eight operating data centers and new sites under construction; IT-load versus facility-power basis is not stated

South Korea; portfolio includes Ulsan and Guro developments

No delivery date disclosed

Build announced
Deal details

SK Telecom plans to spin off its wholly owned SK Broadband data-center business into SK Horizon. A definitive agreement provides for KRW 3.08 trillion in combined equity investment from KKR-managed funds and the IMM Investment-Stonebridge consortium. SKT says SK Horizon's 318 MW portfolio figure includes eight operating data centers and new AIDCs under construction, including Ulsan and Guro. The source gives no site allocation or IT-load versus facility-power basis. The portfolio figure is not incremental capacity and may overlap group-level SK Hyper plans; it is excluded from capacity totals. The equity is financing, not project construction spend, and remains in native currency.

SK Telecom launches SK Horizon and announces investor agreement ↗Related: SK Hyper / SK Telecom / SK Hyper · 2026-07-23Assess this deal
Source ↗
Aug 24, 2026

Undisclosed buyer

Undisclosed U.S. cloud customer

Cloud compute

$13.7B · Six-year commercial agreement; approximately US$13.7 billion for three initial GPU-service tranches; later expansion agreements are unpriced

Undisclosed

Customer GPU-services allocation and site MW undisclosed

Maysville, Georgia, United States

Maysville site is under development; no first-delivery date stated. The customer must approve the proposed delivery date for the third tranche.

Agreement signed
Deal details

RUM Group's August 24 SEC filing confirms a six-year GPU-services agreement with an unnamed US cloud customer at its Maysville site, then under development. The three initial tranches have an approximately US$13.7 billion total order value, spread evenly across the tranches. The customer must review and accept RUM's proposed delivery date for the third tranche before obligations for that tranche apply. The filing does not name the customer; The Information reports Anthropic, but that attribution is not confirmed by the filing or a company announcement. It states no MW, GPU count, first-delivery date, or utility energization date. RUM said it did not yet have financing for the required development and equipment when it filed; no financing condition applies to its agreement. Expansion agreements are possible but unpriced and are not included.

Hardware: GPU access and GPU services; model and quantity undisclosed

RUM Group Form 8-K, August 23 GPU-services agreement ↗The Information reports that Anthropic is the customer; the SEC filing does not identify it ↗Assess this deal
Source ↗
Aug 20, 2026

Hudson River Trading

Hudson River Trading

Cloud compute

Multi-billion-dollar agreement per CoreWeave; exact value undisclosed

Undisclosed

AI research and model training workloads; no MW allocation stated

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

CoreWeave announced a multi-year agreement with Hudson River Trading for AI research and model development. Its release describes the deal as multi-billion-dollar but gives no exact value, term length, MW allocation, GPU quantity, site, or start date. The multi-billion description is retained as source text and excluded from numeric contract totals.

Hardware: NVIDIA Vera Rubin NVL72 and HGX B200 systems

CoreWeave and Hudson River Trading agreement ↗Assess this deal
Source ↗
Aug 20, 2026

QumulusAI

QumulusAI

Campus build

Undisclosed

Up to 3.75 MW

Up to 3.75 MW of data-center capacity under a seven-year colocation agreement; IT-load versus facility-power basis is not stated

Metropolitan Atlanta, Georgia, United States

Ready-for-service target Q4 2026, conditional on the current occupant transition; no completion evidence found

0–3 months to target

Agreement signed
Deal details

QumulusAI signed a seven-year colocation agreement for up to 3.75 MW in metropolitan Atlanta, conditional on the current occupant leaving. QumulusAI states a Q4 2026 ready-for-service target and says the site could support up to 2,048 B300-class GPUs. A right of first offer for up to 7 MW is not contracted capacity and is not included. The source does not say whether 3.75 MW is critical IT load or facility power. The later US$211.9 million customer agreement uses this site, but the MW basis remains unclear and the planned site amount is not a delivered customer allocation.

Hardware: Site expected to support up to 2,048 NVIDIA Blackwell B300-class GPUs

QumulusAI Atlanta colocation agreement ↗Related: Undisclosed buyer / Undisclosed AI inference platform · 2026-09-29Assess this deal
Source ↗
Aug 17, 2026

Axe Compute

Duos Technologies

Cloud compute

Over $500 million in aggregate contractual base payments over five years; excludes electricity and usage-based charges

Up to 55 MW

Aggregate total AI facility capacity reserved across multiple sites; not disclosed as critical IT load or energized power

Multiple U.S. sites

Initial project readiness targeted from late 2026 through early 2027; testing and written acceptance are required

Agreement signed
Deal details

Duos signed service orders reserving up to 55 MW of total facility capacity for Axe Compute across multiple U.S. sites. Duos supplies the facilities, power, and colocation services; Axe brings and operates the compute equipment. Initial project readiness was targeted to begin in late 2026 and continue into early 2027, subject to construction, commissioning, testing, and Axe's written acceptance. The agreements are separate from the earlier 10 MW Georgia deployment. The reported hosting payments are retained as source text and excluded from compute-purchase and infrastructure-investment totals.

Axe Compute announcement of 55 MW Duos agreements ↗Duos Technologies agreement terms and capacity basis ↗Duos update on the Axe Compute relationship, October 5, 2026 ↗Assess this deal
Source ↗
Aug 11, 2026

Mistral AI

European enterprise coalition

Campus build

Undisclosed

Up to 1 GW

Program ambition · possible project overlap

Europe · sites not allocated

Program target: 2030

Build announced
Deal details

Program ambition for up to 1 GW by 2030, supported by enterprise compute commitments. Individual sites and incremental capacity beyond earlier Mistral projects are not allocated in this announcement. Excluded from physical capacity totals.

Company announcement ↗Related: Mistral AI / EcoDataCenter · 2026-02-11Assess this deal
Source ↗
Aug 11, 2026

Together AI

IBM Cloud

Cloud compute

$240M · Multi-year; exact term undisclosed

Undisclosed

Location undisclosed

Expected availability Q1 2027

2–6 months to target

Agreement signed
Deal details

Dedicated IBM Cloud cluster for Together AI open-source inference. Site, MW and GPU count are undisclosed. Expected availability is a target, not delivery evidence. Together AI’s separate financing is excluded.

Hardware: NVIDIA HGX B300 / Spectrum-X

IBM August 11 Together AI agreement ↗Assess this deal
Source ↗
Aug 6, 2026

IMC

IMC

Cloud compute

Undisclosed

Undisclosed

Expanded AI cloud use; no incremental MW or GPU quantity stated

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

IMC said it would significantly scale its use of CoreWeave, where it had operated several production clusters since 2025. CoreWeave describes additional capacity as immediately available but gives no quantity, value, site, or service-start date. The prior production relationship means this expansion is not a new deployment start.

CoreWeave and IMC research expansion ↗Assess this deal
Source ↗
Aug 4, 2026

CoreWeave

Local facility partners

Campus build

Undisclosed

360 MW

Contracted IT power · three facilities

Indonesia · three facilities

2028

14–27 months to target

Build announced
Deal details

Three Indonesian facilities with 360 MW of contracted IT power, expected online in 2028. This is the regional deployment allocation, not CoreWeave’s global contracted-power total.

Company announcement ↗Assess this deal
Source ↗
Aug 4, 2026

Undisclosed buyer

Undisclosed global AI platform

Cloud compute

$373M · Cloud computing services over five years

Undisclosed

Initial 2,048 B300 GPUs; customer MW allocation undisclosed. Sharon AI's 132 MW company-wide capacity and 120 MW contracted across customers are not allocated to this agreement.

Australia

Revenue expected to commence in Q1 2027; source does not give a distinct first-compute or energization date

Agreement signed
Deal details

Sharon AI reports a five-year cloud service agreement with an unnamed global AI platform. The initial deployment is expected to use 2,048 NVIDIA B300 GPUs, with revenue expected from Q1 2027. Sharon AI's 132 MW AI Factory capacity and 120 MW contracted across end customers are not allocated to this agreement. Revenue timing does not establish a first-compute or energization date.

Hardware: Initial deployment of 2,048 NVIDIA Blackwell Ultra B300 GPUs

Sharon AI Form 8-K exhibit, US$373 million customer agreement ↗Assess this deal
Source ↗
Jul 30, 2026

Crusoe

Aalo Atomics

Strategic partnership

Undisclosed

Undisclosed

Idaho National Laboratory, Idaho, US

Crusoe Spark proof of concept targeted for 2027

2–15 months to target

Build announced
Deal details

The companies plan to run a Crusoe Spark modular data center on Aalo power in 2027 as a proof of concept. They also describe future Aalo Pods and 50 MWe reactor plants, but do not state a data-center power allocation. Aalo's 10 MWe reactor rating is not entered as delivered campus power. No MW, contract value or energization evidence is disclosed for the data center.

Crusoe and Aalo Atomics announce nuclear-powered AI factory partnership ↗Assess this deal
Source ↗
Jul 28, 2026

Flow Traders

Flow Traders

Cloud compute

Undisclosed

Undisclosed

Dedicated compute for foundation-model training; no MW allocation stated

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Flow Traders selected CoreWeave as its primary cloud platform for AI model training and secured dedicated compute capacity. The announcement gives no contract value, GPU count, MW allocation, term, site, or dated service start. Flow Traders' plan to launch an AI division is not a compute-delivery date.

CoreWeave and Flow Traders AI training agreement ↗Assess this deal
Source ↗
Jul 28, 2026

Nscale

Ionic Digital

Campus build

Undisclosed

89 MW

Incremental site power under lease amendment; conditional on availability and regulatory approval, not IT load

Ward County, Texas, US

Ionic expects the additional power to be energized in the second half of 2027, subject to approval

8–15 months to target

Agreement signed
Deal details

The filing reports that a February 2026 lease amendment obligates Nscale to lease an additional 89 MW when available. Ionic expects to energize the increment in the second half of 2027, but the capacity is subject to regulatory approval and is not yet operating. This is incremental to the original 234 MW lease.

Ionic Digital SEC registration statement ↗Related: Nscale / Ionic Digital · 2025-10-14Assess this deal
Source ↗
Jul 28, 2026

Undisclosed buyer

Undisclosed AI inference platform

Cloud compute

$71.9M · Three-year agreement with renewal options

Undisclosed

B200 and B300 capacity; GPU quantity and customer MW allocation undisclosed

Location undisclosed

Q3 2026 target; B200 handoff September 8 and final B300 handoff October 1

Delivery reported

In use at announcement
Deal details

QumulusAI first expected capacity for customer use in Q3 2026. It later reported B200 handoff on September 8 and B300 handoff at its Kansas City site on October 1; on October 15 it said all GPUs under the agreement were in production and billing. The agreement reached service after its Q3 target. Customer MW and utility energization are undisclosed. QumulusAI's separate portfolio MW figures are not assigned to this customer.

Hardware: NVIDIA Blackwell B200 and B300 GPUs

QumulusAI three-year AI inference agreement ↗QumulusAI reports full B200 handoff ↗QumulusAI reports final B300 handoff and production billing ↗Related: Undisclosed buyer / Undisclosed AI inference platform · 2026-09-29Assess this deal
Source ↗
Jul 27, 2026

Crusoe

Energy Vault

Campus build

Undisclosed

8 MW

Contracted powered-shell capacity · Phase 1

Snyder, Texas, US

1H 2027 (August target; July release said Q1 2027)

2–9 months to target

Build announced
Deal details

Energy Vault began construction on a powered-shell campus for Crusoe Cloud. Phase 1 is contracted for 8 MW and includes ten Crusoe Spark modular data centers. Energy Vault's August 11 filing reports a 1H 2027 commercial-operation target; the July 27 release gave Q1 2027. The release describes expansion potential to 25 MW in Phase 2 and planned site capacity up to 500 MW. Those are not contracted Phase 1 capacity and are excluded from totals. Construction is not energization; no delivered or energized MW is confirmed.

Energy Vault, Snyder AI campus groundbreaking ↗Energy Vault Q2 2026 results, SEC Exhibit 99.1 ↗Assess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

300 MW

Critical IT load

Boyce, Louisiana, US

2027

2–15 months to target

Agreement signed
Deal details

Delta Forge 1: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 results ↗Assess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

210 MW

Critical IT load

Southern United States; state undisclosed

First half of 2028

14–21 months to target

Agreement signed
Deal details

Delta Forge 2: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 results ↗Assess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

300 MW

Critical IT load

United States; state not identified in cited release

2027

2–15 months to target

Agreement signed
Deal details

Polaris Forge 3: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 results ↗Assess this deal
Source ↗
Jul 23, 2026

Undisclosed buyer

Undisclosed generative-AI inference platform

Cloud compute

$32M+ · Two-year agreement with renewal options

Undisclosed

Dedicated B300 GPU clusters; GPU quantity and customer MW allocation undisclosed

Location undisclosed

Capacity expected in fall 2026; no dated delivery evidence found

Agreement signed
Deal details

QumulusAI reports a two-year agreement worth more than US$32 million for dedicated Blackwell B300 clusters serving a generative-AI inference platform. The September 29 US$29.1 million agreement is a separate second commitment by the same customer. The original fall 2026 target remains unverified; the later agreement's December target does not prove delivery of this tranche.

Hardware: NVIDIA Blackwell B300 GPU clusters

QumulusAI generative-AI inference agreement ↗Related: Undisclosed buyer / Undisclosed generative-AI inference platform · 2026-09-29Assess this deal
Source ↗
Jul 23, 2026

SK Hyper

SK Telecom / SK Hyper

Campus build

KRW 750 billion investment through 2030 to establish sites and substations

15 GW

Planned nationwide AI data-center capacity; SKT does not state whether the figure is IT load or total facility power

South Korea; regional projects include Ulsan, Chungcheong, and Honam

First phase targets 5 GW of phased openings in 2029; long-term plan targets 15 GW total by 2035, subject to market demand

26–39 months to target

Build announced
Deal details

SK Telecom established SK Hyper as a wholly owned AI data-center development company. It approved KRW 750 billion through 2030 for foundational development, including sites and substations. The company targets phased opening of 5 GW in 2029 and expansion toward 15 GW total by 2035, subject to market demand. The capacity basis is not stated. In an October 22 Bloomberg interview, SK Hyper's CEO said the first 5 GW phase would require $350 billion including equipment and that the company was discussing financing with potential partners. This is an estimated phase cost, not committed financing, project spend, or contract value. It is excluded from financial totals. The 5 GW is part of the 15 GW plan and is not additive.

SK Telecom establishes SK Hyper for 15 GW AI data-center plan ↗Bloomberg interview with SK Hyper CEO, October 22, 2026 ↗Assess this deal
Source ↗
Jul 22, 2026

Undisclosed buyer

Undisclosed GPU cloud marketplace

Cloud compute

$18M+ · Two-year take-or-pay agreement

Undisclosed

NVIDIA B300 GPU capacity; quantity and customer MW allocation undisclosed

Philadelphia, Pennsylvania, United States

Customer handoff completed September 1, 2026

In use at announcement
Deal details

QumulusAI reports a two-year take-or-pay agreement worth more than US$18 million with an unnamed GPU marketplace. Its September 10 release says the full Blackwell B300 deployment was handed to the customer on September 1 at the Philadelphia colocation site. GPU count and MW are not disclosed; operational handoff does not give a utility energization measurement.

Hardware: NVIDIA Blackwell B300 nodes

QumulusAI marketplace agreement announcement ↗QumulusAI confirms full handoff in Philadelphia ↗Assess this deal
Source ↗
Jul 16, 2026

Undisclosed buyer

Undisclosed global AI lab

Cloud compute

$1.3B · Cloud computing services over five years

Undisclosed

Customer-specific MW and GPU allocation undisclosed; reported 116 MW of company-wide contracted capacity is not allocated to this agreement

New Zealand

Cloud deployments planned in New Zealand; revenue expected across Q1 and Q2 2027, with no distinct first-compute date stated

Agreement signed
Deal details

Sharon AI reports a five-year cloud computing agreement with an unnamed global AI lab. It plans deployments across data center infrastructure in New Zealand and expects revenue to begin in Q1–Q2 2027. That revenue window is not reported as a first compute or power date. Sharon AI's 132 MW AI Factory capacity and 116 MW contracted to customers are company-wide amounts, not this customer's allocation.

Sharon AI Form 8-K exhibit, US$1.32 billion customer agreement ↗Assess this deal
Source ↗
Jul 15, 2026

Crusoe

Lancium

Campus build

Undisclosed

1 GW

Planned campus capacity

Childress, Texas, US

No delivery date disclosed

Build announced
Deal details

Crusoe and Lancium announced a 1 GW campus for an unnamed hyperscale customer. Construction is expected to start in Q3 2026. This is a separate project from IREN’s Childress campus.

Crusoe announcement ↗Assess this deal
Source ↗
Jul 10, 2026

Huawei

China Telecom / Huawei

Strategic partnership

Approximately RMB 5.5 billion total project investment

Undisclosed

11,520 Ascend accelerators in 30 supernodes; source also reports 9,000 PFLOPS FP16, not MW or IT load

Shaoguan, Guangdong, China

Cluster launched July 9, 2026

In use at announcement
Deal details

China Telecom and Huawei launched an Ascend 910C cluster on July 9, 2026. Shaoguan government reports 11,520 accelerators; China Telecom reports 30 supernodes, 9,000 PFLOPS FP16, and approximately RMB 5.5 billion total project investment. The investment is kept in native currency and excluded from USD contract totals. Accelerator count and compute throughput are not MW, critical IT load, or utility power. The launch establishes operational compute, not a measured power-delivery date.

Hardware: Huawei Ascend 910C accelerators in 30 supernodes; 11,520 cards reported by Shaoguan government

China Telecom, Ascend cluster launch and investment disclosure ↗Shaoguan government report on the 11,520-card cluster launch ↗Assess this deal
Source ↗
Jul 6, 2026

Anthropic

TeraWulf

Cloud compute

Undisclosed

401 MW

Approximately 401 MW of critical IT load under a 20-year lease

Hawesville, Kentucky, US

Initial phases expected in the second half of 2027; full 401 MW expected in early 2028

8–15 months to target

Agreement signed
Deal details

TeraWulf's subsidiary entered a 20-year lease with Anthropic for approximately 401 MW of critical IT load at the Justified Data Campus. Initial leased premises are expected in phases during the second half of 2027; full delivery is expected in early 2028. The lease has two five-year renewal options. TeraWulf states approximately $19 billion of contracted lease revenue over the initial term. That service revenue is not a compute-purchase value or infrastructure investment and is excluded from contract-value analytics. The August 5 filing says the lease had not commenced as of the filing date. This is a customer IT-load allocation, not the campus's gross power availability or proof of energized capacity.

TeraWulf July 6 lease announcement ↗TeraWulf SEC Form 8-K, July 6, 2026 ↗TeraWulf SEC Form 10-Q, filed August 5, 2026 ↗Assess this deal
Source ↗
Jul 6, 2026

Nscale

Nordkraft

Strategic partnership

Undisclosed

Undisclosed

Narvik, Norway

No delivery date disclosed

Agreement signed
Deal details

Joint operations company for the existing Narvik development. Its planned 2026 start refers to the operations company, not energized customer capacity. No incremental power allocation or contract value is disclosed.

Nscale July 6 announcement ↗Related: Microsoft / Nscale · 2026-04-14Assess this deal
Source ↗
Jun 24, 2026

CoreWeave

Conapto

Campus build

Undisclosed

Undisclosed

Stockholm, Sweden

Initial capacity online at announcement

Build announced
Deal details

Colocation agreement across two campuses. CoreWeave stated that initial capacity at Stockholm 4 South was already online. No deal-specific power allocation or contract value is disclosed. The company-wide active and contracted power figures are not assigned to these campuses.

CoreWeave investor announcement ↗Assess this deal
Source ↗
Jun 24, 2026

Undisclosed buyer

Undisclosed California neocloud provider

Cloud compute

More than $1.2 billion in expected revenue over the maximum 20-year term; more than $3.0 billion only if the customer exercises expansion to 52 MW and both extension options

20 MW

Initial critical AI compute capacity under the MSA; not campus power or confirmed energized capacity

Michigan, United States

November 2026 target in September 17 update; not yet confirmed operational

0–2 months to target

Agreement signed
Deal details

The June 24 MSA covers an initial 20 MW of critical AI compute capacity and gives the customer an option to expand to 52 MW. The September 17 update says operations are targeted to begin in November 2026 and that more than $70 million had been invested as of September 15; neither statement confirms delivery. The approximately 340 MW figure is total potential campus capacity, subject to power, infrastructure, financing, and regulatory approvals, and is not included here. Contract revenue is conditional on the maximum term and is not recorded as compute-purchase value or capital expenditure.

Hyperscale Data MSA for Michigan AI compute capacity ↗Hyperscale Data September 17 delivery and investment update ↗Assess this deal
Source ↗
Jun 12, 2026

NVIDIA

NVIDIA / Sharon AI

Strategic partnership

Up to $4.9B · Six-year strategic compute collaboration; maximum value under a revenue-sharing and credit-support model

72 MW

New Australian data-center capacity; source does not say whether 72 MW is critical IT load or facility power and it may support customer contracts recorded separately

Australia

No dated first-compute or utility energization target stated

Agreement signed
Deal details

Sharon AI reports a six-year agreement with NVIDIA worth up to US$4.88 billion and enabling 72 MW of new Australian data-center capacity and up to 40,000 GB300 GPUs. The parties use a revenue-sharing and credit-support model. The 72 MW basis is unspecified and may support customer capacity represented in separate Sharon AI agreements. Keep the 72 MW out of IT-load, campus, or energized-power totals, and exclude the maximum collaboration value from contract totals because it may overlap revenue from customer agreements.

Hardware: Up to 40,000 NVIDIA Grace Blackwell GB300 GPUs

Sharon AI Form 8-K, NVIDIA collaboration ↗Assess this deal
Source ↗
Jun 11, 2026

Undisclosed buyer

Hyperbolic and one unnamed AI inference platform

Cloud compute

$124M+ · Two customer agreements with three-year terms; the announcement reports their combined value

Undisclosed

1,280 NVIDIA Blackwell GPUs across two customer agreements; per-customer GPU counts and MW are undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

QumulusAI reports more than US$124 million in two three-year customer agreements, one with Hyperbolic and one unnamed AI inference platform. The source states that the agreements support 1,280 Blackwell GPUs and include nearly US$21.9 million in combined upfront commitments. It does not allocate contract value or GPUs by customer, so this combined announcement is one record. The figure is counted once; later customer-specific agreements are separate commitments.

Hardware: 1,280 NVIDIA Blackwell GPUs across both agreements

QumulusAI, two AI inference infrastructure agreements ↗Assess this deal
Source ↗
Jun 8, 2026

Nebius

Nebius UK infrastructure deployments

Campus build

Approximately £1.7 billion investment across four UK capacity sites

65 MW

Combined capacity of three new NVIDIA infrastructure deployments at full ramp; source does not specify IT load versus facility power

United Kingdom

Three new deployments reach full ramp in 2027; first-capacity date not stated

Build announced
Deal details

Nebius states approximately £1.7B of investment for UK capacity buildout and three new deployments with 65 MW combined capacity at full ramp in 2027. The source does not define the MW basis or identify individual site allocations. The investment is in pounds and is not a compute contract value. A separate first UK deployment was already operating from November 2025 and is not included as a fourth deployment in the 65 MW figure.

Hardware: NVIDIA infrastructure; model and quantity not stated

Nebius UK expansion announcement ↗Assess this deal
Source ↗
Jun 8, 2026

SK Hyper

SK Telecom / NVIDIA

Strategic partnership

Undisclosed

About 1 GW

Gigawatt-scale AI Cloud plan; exact quantity and IT-load versus facility-power basis are not stated

South Korea; site allocation undisclosed

First AI factory planned to come online in 2027

2–15 months to target

Build announced
Deal details

SK Telecom plans a gigawatt-scale AI Cloud built on NVIDIA DSX, with the first AI factory planned for 2027. The source does not state an exact MW quantity or IT-load versus facility-power basis. This SKT and NVIDIA plan may overlap SK Hyper's wider 15 GW program and the Ulsan-AWS development; its capacity is excluded from totals pending site and scope reconciliation.

SK Telecom and NVIDIA build AI infrastructure for Korea ↗Related: SK Hyper / SK Telecom / SK Hyper · 2026-07-23Related: Amazon Web Services / SK Group · 2025-06-22Assess this deal
Source ↗
Jun 2026

Firmus

Firmus / Gunvor

Strategic partnership

Undisclosed

600 MW

Firm 12-year wholesale electricity supply; not customer IT load, campus capacity, or energized data-centre power

South Australia

No delivery date disclosed

Agreement signed
Deal details

Firmus announced a 12-year wholesale supply agreement for 600 MW of firm electricity. Gunvor will support 1.2 GW of new renewable generation and 1.5 GWh of battery storage by 2032. The agreement supports two planned South Australian campuses; it does not establish campus capacity, IT load, or a first-power date.

Firmus and Gunvor 600 MW electricity agreement ↗Related: Firmus / Firmus · 2026-06Assess this deal
Source ↗
Jun 2026

Firmus

Firmus / NVIDIA

Campus build

Undisclosed

360 MW

Dedicated planned campus capacity; source does not define IT-load versus facility-power basis

Batam, Indonesia

No delivery date disclosed

Build announced
Deal details

Firmus announced a dedicated 360 MW campus with NVIDIA and DayOne. The source says the agreement covers up to 170,000 accelerators through 2027 and 2028 but gives no first-service date. Firmus expects US$25–30 billion in customer offtake receipts over the first six years; that is a company estimate across customer offtake, not a Firmus–NVIDIA purchase value or realized revenue.

Hardware: Up to 170,000 NVIDIA accelerators across Grace-Blackwell, Vera-Rubin, and Vera platforms through 2027 and 2028

Firmus and NVIDIA AI Factory campus announcement ↗Assess this deal
Source ↗
Jun 2026

Firmus

Firmus

Campus build

Undisclosed

2.7 GW

Combined planned campus capacity; source does not define IT-load versus facility-power basis

South Australia

No delivery date disclosed

Build announced
Deal details

Firmus describes 2.7 GW as the planned capacity of the first phase of two campuses. It does not state whether this is IT load or facility power, give a site-level split, or provide a first-capacity date. The announcement places the sites under Firmus's wider Southgate strategy. Their relationship to the earlier 1.6 GW CDC rollout is not clear, so this figure is kept out of capacity subtotals.

Firmus South Australia campus and energy announcement ↗Related: Firmus / Firmus / Gunvor · 2026-06Related: Firmus / Firmus / CDC / NVIDIA · 2025-10-16Assess this deal
Source ↗
May 20, 2026

Nebius

Nebius

Strategic partnership

Undisclosed

328 MW

Installed behind-the-meter fuel-cell generation capacity for an unnamed first US project; not compute, IT load, or confirmed energized power

Location undisclosed

First 328 MW fuel-cell project expected to be operational in 2026

0–3 months to target

Build announced
Deal details

The partners describe 328 MW of installed fuel-cell generation capacity for the first US project, expected to be operational in 2026. The release does not name the site or report commissioning, energization, or delivered compute. Keep the generation rating separate from data-center load and actual energized power.

Nebius and Bloom May 20 project announcement ↗Assess this deal
Source ↗
May 14, 2026

Undisclosed buyer

Undisclosed global technology company

Cloud compute

$950M · Initial contract value over five years; take-or-pay

Undisclosed

Customer-specific MW and GPU allocation undisclosed; Sharon AI's company-wide secured and contracted capacity is not allocated to this agreement

Multiple data centers in Australia

Initial deployment accepted August 20, 2026; additional clusters expected over the following months

Agreement signed
Deal details

Sharon AI reports an approximately US$950 million five-year take-or-pay cloud infrastructure agreement with an unnamed global technology company. Its August 20 release confirms that the customer accepted an initial deployment, with more NVIDIA GPU clusters expected in the following months. Sharon AI's reported company-wide secured and contracted MW are not allocated to this customer. Customer MW, GPU count, exact site, and utility energization date are unknown.

Hardware: NVIDIA GPU clusters; model and quantity undisclosed

Sharon AI Form 8-K exhibit, five-year customer agreement ↗Sharon AI reports initial deployment accepted ↗Assess this deal
Source ↗
May 6, 2026

Anthropic

SpaceX

Cloud compute

Up to $120.5B · Through 2029 (cancellable after initial terms)

300+ MW

Colossus 1 compute

Location undisclosed

Initial capacity ramped in May–June 2026; all contracted capacity was expected by December 2026

Delivery reported

Agreement signed
Deal details

The May 6 announcement covers more than 300 MW at Colossus 1. SpaceX’s June 5 prospectus describes Anthropic service agreements across Colossus 1 and 2, approximately 325,000 GPUs, and a $1.25B monthly fee at that time. Anthropic’s October 26 Form S-1 reports that agreements entered into or amended between May and October provide for up to $120.5B through 2029, with fees of about $3.1B per month after all capacity is delivered, which Anthropic expected in December 2026. The separate agreements have initial non-cancelable periods ending in January and March 2027, after which either party may cancel with 90 days’ notice. The upper-limit spend is not a guaranteed contract value. The filing does not add a new MW allocation or give an energization date. Orbital compute remains an expression of interest.

Hardware: 220,000+ NVIDIA GPUs

Anthropic, SpaceX compute deal ↗SpaceX June 5, 2026 prospectus, section 4.3.4.5 ↗Anthropic Form S-1 filed October 26, 2026 ↗Assess this deal
Source ↗
May 5, 2026

Microsoft

Nscale / Start Campus

Cloud compute

Undisclosed

Undisclosed

66,000+ NVIDIA Rubin GPUs; 200 MW describes the second campus building, not Microsoft's compute allocation

Sines, Portugal

Late 2027

11–15 months to target

Agreement signed
Deal details

Nscale announced an agreement with Microsoft and Start Campus for 66,000+ Rubin GPUs starting in late 2027. The 200 MW figure is for a second campus building; the full campus is permitted for 1.2 GW. Neither site figure is an allocation to this Microsoft deployment. Nscale separately reported more than 12,600 Blackwell Ultra GPUs at the first building; those GPUs are not added to this expansion.

Hardware: 66,000+ NVIDIA Rubin GPUs

Nscale, SINES deployment announcement ↗Assess this deal
Source ↗
May 5, 2026

Nscale

Start Campus

Cloud compute

€465 million for the second building; €230 million for shared infrastructure

200 MW

Second campus building; facility capacity, not a customer compute allocation

Sines, Portugal

No delivery date disclosed

Build announced
Deal details

Nscale states a second 200 MW building and €465M investment in that building, plus €230M for shared infrastructure. The figures describe campus build and investment, not Microsoft's compute allocation or contract value. The campus is permitted for 1.2 GW; the full-campus figure is not added to this building. No energization date is stated for the building.

Nscale, SINES deployment announcement ↗Related: Microsoft / Nscale / Start Campus · 2026-05-05Assess this deal
Source ↗
Apr 30, 2026

Yotta

Gorilla Technology

Strategic partnership

Approx. $2.5B project value (July update)

Undisclosed

New Delhi, India (July 21 update)

Original deployment completion target: September 30, 2026; first service date undisclosed

Agreement signed
Deal details

Expansion separate from the earlier 5,120-GPU programme. April disclosure valued this project at approximately $2.8B; July 21 described Yotta 2 at approximately $2.5B without reconciling the difference. September 8 reports equipment deliveries across the wider Yotta programme, not operational acceptance of this tranche. Project value remains outside compute-purchase totals. No MW conversion is inferred from GPU count.

Hardware: 20,736 NVIDIA B300 GPUs

Yotta April 30 expansion announcement ↗Gorilla July 21 project value and location update ↗Gorilla September 8 equipment delivery update ↗Related: NVIDIA / Yotta · 2026-02-18Assess this deal
Source ↗
Apr 29, 2026

Undisclosed buyer

E2E Networks

Cloud compute

$7.7M · Six months

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Executed agreement with an unnamed US AI service provider specialising in large-scale model training. Committed value covers GPU cloud computing and allied services for six months. Customer identity, site, GPU count, MW and service commencement are undisclosed.

E2E Networks April 29 exchange filing ↗Assess this deal
Source ↗
Apr 20, 2026

Anthropic

Amazon Web Services

Cloud compute

$100B+ · 10 years

Up to 5 GW

Trainium and related compute

Location undisclosed

Nearly 1 GW by end of 2026

Agreement signed
Deal details

Anthropic committed more than $100B over ten years to AWS technologies for up to 5 GW of new Trainium and related capacity. Nearly 1 GW is expected before the end of 2026. Amazon also announced a $5B equity investment, with up to $20B more later; those equity figures are omitted from the dollar column.

Hardware: Trainium2–4

Anthropic, Amazon compute collaboration ↗Assess this deal
Source ↗
Apr 15, 2026

Jane Street

Jane Street

Cloud compute

$6B

Undisclosed

Next-generation AI cloud capacity across multiple facilities; no MW allocation stated

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Jane Street committed approximately US$6B to use CoreWeave's AI cloud platform across multiple facilities. The agreement expands an existing relationship and includes access to next-generation compute, including NVIDIA Vera Rubin technology. The announcement does not state the term, MW allocation, sites, or first-service date. Jane Street separately invested US$1B in CoreWeave equity; that financing is excluded from the compute purchase amount and financial totals.

Hardware: NVIDIA Vera Rubin technology included; quantity not stated

CoreWeave and Jane Street agreement announcement ↗Assess this deal
Source ↗
Apr 14, 2026

Microsoft

Nscale

Cloud compute

Undisclosed

Undisclosed

Narvik, Norway

2027

2–15 months to target

Agreement signed
Deal details

Expanded Microsoft agreement adds more than 30,000 Rubin GPUs at Narvik in 2027. The 230 MW figure describes the campus, not the power allocated to this expansion.

Hardware: 30,000+ NVIDIA Rubin GPUs

Nscale announcement ↗Assess this deal
Source ↗
Apr 10, 2026

Anthropic

CoreWeave

Cloud compute

Undisclosed

Undisclosed

Location undisclosed

Later in 2026

0–3 months to target

Agreement signed
Deal details

Multi-year agreement to support Claude development and deployment, with capacity starting later in 2026. No exact dollar or megawatt figure is disclosed.

Company announcement ↗Assess this deal
Source ↗
Apr 9, 2026

Meta

CoreWeave

Cloud compute

$21B · Approx. · through Dec 2032

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Expanded agreement for approximately $21B through December 2032. Includes new capacity and exercise of an option under a previous order. Read with the earlier agreement rather than treating both as independent projects.

CoreWeave announcement ↗Related: Meta / CoreWeave · 2025-09-30Assess this deal
Source ↗
Apr 6, 2026

Anthropic

Google / Broadcom

Cloud compute

Undisclosed

5 GW

TPU compute · May 6 disclosure

Primarily United States

2027

2–15 months to target

Agreement signed
Deal details

The April 6 announcement is for multiple gigawatts of next-generation TPU capacity starting in 2027. Anthropic’s May 6 recap states a 5 GW agreement with Google and Broadcom. No public dollar figure appears on either Anthropic page. Builds on a prior October 2025 TPU-capacity increase.

Hardware: Google TPUs

Anthropic, Google and Broadcom compute partnership ↗Anthropic, May 6 capacity update ↗Assess this deal
Source ↗
Apr 4, 2026

Alibaba Cloud

China Telecom / Alibaba Cloud

Strategic partnership

Undisclosed

Undisclosed

Ten-thousand-card-class Zhenwu accelerator cluster; exact card count, IT load, and facility power undisclosed

Shaoguan, Guangdong, China

Cluster launched April 3, 2026

In use at announcement
Deal details

China Telecom and Alibaba Cloud jointly built the first Zhenwu ten-thousand-card-class cluster in the Greater Bay Area. The cluster was reported online on April 3, 2026. The report gives a class-size description, not an exact card count. It reports no MW, site-specific capital amount, or utility energization date. Treat operational compute as evidenced; keep actual energized power unknown.

Hardware: Alibaba Zhenwu AI accelerators; ten-thousand-card-class cluster

Shaoguan government report on the Zhenwu cluster launch ↗Alibaba Cloud report on the Zhenwu cluster entering service ↗Assess this deal
Source ↗
Apr 2, 2026

Nscale

Fortum

Campus build

Undisclosed

Undisclosed

Harjavalta, Finland

No delivery date disclosed

Build announced
Deal details

Site securing and development agreement for the Sievari industrial area. Fortum supports grid design and permitting; preliminary land-sale work is underway. Power capacity remains subject to design and permitting. No first-capacity date or contract value is disclosed.

Nscale announcement ↗Assess this deal
Source ↗
Mar 27, 2026

Microsoft

Crusoe

Campus build

Undisclosed

900 MW

Planned campus capacity

Abilene, Texas, US

First building: mid-2027

2–15 months to target

Build announced
Deal details

New 900 MW campus serving Microsoft, next to the existing Abilene development. Includes two buildings and onsite generation. The combined 2.1 GW Abilene figure includes the existing campus.

Crusoe announcement ↗Assess this deal
Source ↗
Mar 24, 2026

Crusoe

Crusoe Cloud

Strategic partnership

Undisclosed

20 MW

Power infrastructure partnership; the announcement does not reconcile the 20 MW figure with the existing 12 MW microgrid or state an incremental versus total basis

Sparks, Nevada

No delivery date disclosed

Build announced
Deal details

The campus already operates four Crusoe Spark modular data centers on a 12 MW / 63 MWh microgrid. The announced expansion increases the deployment to 24 data centers and describes work with Redwood Energy at 20 MW, but does not state whether 20 MW is incremental or the final power-system total. Do not add this figure to power subtotals until the basis is reconciled. The source reports 99.2% operating availability for the existing system; that is not a new delivery milestone for the expansion.

Crusoe and Redwood March 24 expansion announcement ↗Assess this deal
Source ↗
Mar 16, 2026

Meta

Nebius

Cloud compute

Up to $27B · 5 years

Undisclosed

Multiple locations · not named

Early 2027

2–15 months to target

Agreement signed
Deal details

Includes $12B of dedicated capacity and up to $15B of additional capacity that remains after sales to other customers. The $27B ceiling is not all dedicated capacity.

Hardware: NVIDIA Vera Rubin

Nebius announcement ↗Assess this deal
Source ↗
Mar 16, 2026

Microsoft

Nscale

Cloud compute

Undisclosed

Up to 1.35 GW

Proposed compute capacity

Mason County, West Virginia, US

Late 2027

2–15 months to target

Letter of intent
Deal details

Letter of intent for up to 1.35 GW at Monarch. The campus’s potential power expansion above 8 GW is not the Microsoft allocation. A letter of intent is not a completed supply contract.

Hardware: NVIDIA Vera Rubin NVL72

Nscale announcement ↗Assess this deal
Source ↗
Mar 16, 2026

Nscale

Nscale

Campus build

Undisclosed

2 GW

Initial onsite powered-microgrid capacity

Mason County, West Virginia, US

1H 2028

14–21 months to target

Build announced
Deal details

Nscale announced its agreement to acquire AIPCorp and Monarch Compute Campus. Nscale states initial onsite microgrid power capacity of 2 GW is expected online by 1H 2028, with expansion to approximately 8 GW planned for 2031. The 2 GW is site power capacity, not a customer compute allocation or energized power. Microsoft's separate up-to-1.35 GW letter of intent at Monarch is linked and must not be added to the campus figure.

Nscale, AIPCorp and Monarch campus announcement ↗Related: Microsoft / Nscale · 2026-03-16Assess this deal
Source ↗
Feb 27, 2026

OpenAI

Amazon Web Services

Cloud compute

$100B · 8 years · expansion

2 GW

Approximately · Trainium compute

Location undisclosed

Trainium4 expected in 2027

Agreement signed
Deal details

An additional $100B over eight years expands the earlier $38B AWS agreement. Approximately 2 GW of Trainium capacity is included. Amazon’s equity investment is separate.

Hardware: Trainium3 / Trainium4

OpenAI announcement ↗Assess this deal
Source ↗
Feb 18, 2026

NVIDIA

Yotta

Cloud compute

$1B+ · Four years

Undisclosed

India

Host supercluster target: August 2026; NVIDIA service start unconfirmed

Agreement signed
Deal details

Four-year NVIDIA DGX Cloud engagement within Yotta's Blackwell Ultra supercluster. April says NVIDIA is expected to account for roughly half the tranche offtake. The full 20,736 GPUs, host facility MW and over $2B build budget are not NVIDIA allocations or additional contract value. The April deployment completion target is September 30, 2026. No customer service acceptance was verified.

Yotta February 18 NVIDIA DGX Cloud engagement ↗Yotta April 30 offtake and deployment update ↗Related: Yotta / Gorilla Technology · 2026-04-30Assess this deal
Source ↗
Feb 11, 2026

Mistral AI

EcoDataCenter

Campus build

€1.2B

Undisclosed

Borlänge, Sweden

2027

2–15 months to target

Build announced
Deal details

Long-term €1.2B infrastructure partnership at Borlänge. EcoDataCenter will build and operate the facility. The disclosed euro amount is retained without a dollar conversion.

Hardware: NVIDIA Vera Rubin

EcoDataCenter announcement ↗Assess this deal
Source ↗
Jan 14, 2026

OpenAI

Cerebras

Cloud compute

Undisclosed

750 MW

Inference compute

Location undisclosed

Phased through 2028

Agreement signed
Deal details

OpenAI announced 750 MW of inference compute to be introduced in phases through 2028. The announcement does not disclose a contract price or individual sites.

Hardware: Cerebras wafer-scale systems

OpenAI announcement ↗Assess this deal
Source ↗
Nov 20, 2025

Nscale

Verne

Campus build

Undisclosed

15 MW

Deployment power; IT versus facility basis not specified

Iceland

Deployment planned in 2026

Delivery reported

Agreement signed
Deal details

15 MW deployment at Verne’s Icelandic campus. The power basis is not specified as critical IT load, so this figure remains outside the IT power subtotal. Verne reported that the first 7.5 MW phase was deployed on April 23, 2026; this does not confirm the remaining 7.5 MW.

Hardware: Approximately 4,600 NVIDIA Blackwell Ultra GPUs

Nscale announcement ↗Data Center Dynamics reports the first-phase deployment ↗Assess this deal
Source ↗
Nov 18, 2025

Anthropic

Microsoft Azure / NVIDIA

Cloud compute

$30B

Up to 1 GW

Additional compute capacity

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Anthropic committed to purchase $30B of Azure compute capacity and to contract additional capacity up to 1 GW, initially on NVIDIA Grace Blackwell and Vera Rubin systems. NVIDIA and Microsoft also committed to invest up to $10B and $5B in Anthropic; those equity figures are omitted from the dollar column. Amazon remains Anthropic’s stated primary cloud and training partner.

Hardware: Grace Blackwell / Vera Rubin

Anthropic, Microsoft and NVIDIA partnerships ↗Assess this deal
Source ↗
Nov 12, 2025

Anthropic

Fluidstack

Campus build

$50B

Undisclosed

Texas and New York, US

Sites coming online through 2026

Build announced
Deal details

Anthropic announced a $50B investment in U.S. computing infrastructure, building data centers with Fluidstack in Texas and New York. The announcement says Fluidstack can deliver gigawatts of power but does not state a megawatt figure. This is an infrastructure build, not a cloud offtake.

Anthropic, $50 billion American AI infrastructure ↗Assess this deal
Source ↗
Nov 10, 2025

NVIDIA

CoreWeave

Cloud compute

$6.3B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

The results recap a $6.3B NVIDIA arrangement; the September 9 order gives NVIDIA access to residual unsold capacity. This backstop can overlap capacity sold to other customers and is excluded from aggregate purchase values. The date identifies the cited results disclosure.

CoreWeave third-quarter results ↗CoreWeave registration filing: residual capacity terms ↗Assess this deal
Source ↗
Nov 3, 2025

Microsoft

IREN

Cloud compute

$9.7B · Approx. · 5 years

200 MW

Critical IT load · Horizon 1–4

Childress, Texas, US

Phased through 2026

Agreement signed
Deal details

Approximately $9.7B over five years, with 20% prepayment. Horizon 1–4 support 200 MW of critical IT load within the 750 MW Childress campus; the full campus is not assigned to this contract.

Hardware: NVIDIA GB300

IREN announcement ↗IREN August 27 FY26 results: Horizon 1 delivery ↗Assess this deal
Source ↗
Nov 3, 2025

Microsoft

Lambda

Cloud compute

Undisclosed

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Multibillion-dollar agreement for tens of thousands of NVIDIA GPUs. No exact contract price or megawatt allocation is disclosed in the announcement.

Hardware: NVIDIA GPUs, including GB300 NVL72

Lambda announcement ↗Assess this deal
Source ↗
Oct 28, 2025

OpenAI

Microsoft Azure

Cloud compute

$250B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Microsoft disclosed an incremental $250B Azure services purchase by OpenAI. The equity ownership and prior investment are separate from this services commitment.

Microsoft quarterly filing ↗Assess this deal
Source ↗
Oct 28, 2025

Undisclosed buyer

MEEZA

Cloud compute

More than QAR 750 million; contract term not disclosed

6 MW

Phase-one data centre services capacity; source does not define IT-load versus facility-power basis

Qatar; site name not disclosed

No delivery date disclosed

Agreement signed
Deal details

MEEZA announced a lease with an unnamed global hyperscaler for 6 MW of data centre services as phase one, with capacity intended for cloud and AI workloads. The company stated a value above QAR 750 million. Customer, site, contract term, delivery date, and IT-load versus facility-power basis are not stated. Do not add this capacity or native-currency value to USD totals. The unnamed customer prevents overlap checks against MEEZA's other hyperscaler contracts.

MEEZA global hyperscaler agreement for 6 MW, Qatar Exchange filing ↗Qatar Exchange filing ↗Assess this deal
Source ↗
Oct 22, 2025

OpenAI

OpenAI / Oracle Stargate

Campus build

Vantage stated a $15B+ project investment; retained as a source statement and excluded from contract-value totals

902 MW

Vantage-stated critical IT load across four buildings; campus total, not an OpenAI or Oracle customer allocation

Port Washington, Wisconsin, US

No delivery date disclosed

Build announced
Deal details

Vantage, OpenAI, and Oracle announced this Stargate site on October 22, 2025, with completion scheduled for 2028. Vantage's current campus page states 902 MW of critical IT load across four buildings. This is the full site figure, not an OpenAI or Oracle allocation; utility power requirements use a separate basis. The Wisconsin PSC revoked the first transmission application's completeness determination on September 10, 2026. The replacement application is docket 137-CE-229 and remains under review. Oracle's September 16 statement says its commitment to completion is unchanged but gives no first-service date. Construction completion is not a first-capacity target, and no energized-power evidence is recorded.

OpenAI, Oracle and Vantage announce Stargate site in Wisconsin ↗Vantage current Project Lighthouse campus specifications ↗Oracle statement on the revised transmission application, September 16, 2026 ↗Wisconsin PSC docket 137-CE-229 current application status ↗Related: OpenAI / Stargate (SoftBank, Oracle, MGX) · 2025-01-21Assess this deal
Source ↗
Oct 16, 2025

Firmus

Firmus / CDC / NVIDIA

Campus build

A$4.5 billion initial-stage investment; up to A$73.3 billion program scale-up estimate

Up to 1.6 GW

Original multi-site program target through 2028; not customer IT load or current contracted capacity

Australia

Initial stages targeted for delivery by mid-2026; no dated energization evidence

Agreement ended
Deal details

The October 2025 plan targeted up to 1.6 GW of AI factories through 2028 and cited A$4.5 billion for its initial stage and up to A$73.3 billion at program scale. Firmus later said it and CDC had mutually agreed not to proceed with the proposed development partnership. This ended partnership is not Firmus's current total capacity plan. The reported 42 MW deployment is not assigned to IT load or energized power, and its deployment date is undisclosed. Do not include the original program budget or capacity in current totals.

CDC, Project Southgate announcement ↗Firmus, Southgate program and original capacity target ↗Firmus co-CEO statement on ending the proposed CDC partnership ↗DCD report on the partnership and reported Melbourne deployment ↗Assess this deal
Source ↗
Oct 15, 2025

Microsoft

Nscale / Start Campus

Cloud compute

Undisclosed

Undisclosed

Approximately 12,600 NVIDIA GB300 GPUs; no customer MW allocation stated

Sines, Portugal

Deployment targeted from Q1 2026

Delivery reported

Agreement signed
Deal details

This is the initial Microsoft deployment at the first SINES building. Nscale's September 18, 2026 Form S-1 says more than 12,600 Grace Blackwell Ultra GPUs were deployed there for Microsoft. The filing confirms deployment but does not date the start of customer service or disclose Microsoft MW allocation or utility energization. This is separate from the 66,000+ Rubin expansion announced in May 2026 for late 2027.

Hardware: Approximately 12,600 NVIDIA GB300 GPUs

Nscale Microsoft GB300 deployment announcement ↗Nscale September 18, 2026 Form S-1, first-building deployment disclosure ↗Related: Microsoft / Nscale / Start Campus · 2026-05-05Assess this deal
Source ↗
Oct 15, 2025

Microsoft

Nscale

Cloud compute

Undisclosed

Undisclosed

Approximately 104,000 NVIDIA GB300 GPUs; the roughly 240 MW figure describes the Texas campus, not a disclosed Microsoft IT allocation

Ward County, Texas, US

Phased delivery of AI infrastructure services targeted from Q3 2026

Target elapsed · confirm delivery

Agreement signed
Deal details

This is a site-level deployment under Nscale's approximately 200,000-GPU Microsoft agreement across four countries. The GPUs are not added to a global GPU total. Nscale's October 1, 2026 update says Ward County was live and delivering thousands of GPUs, but it does not identify them as Microsoft capacity. No dated evidence that Microsoft compute service began was verified by October 26, 2026. Ionic Digital's separate 234 MW lease is facility power, not Microsoft's compute allocation.

Hardware: Approximately 104,000 NVIDIA GB300 GPUs

Nscale Microsoft GB300 deployment announcement ↗Related: Nscale / Ionic Digital · 2025-10-14Assess this deal
Source ↗
Oct 14, 2025

Nscale

Ionic Digital

Campus build

Undisclosed

234 MW

Operating facility power capacity leased to Nscale; not critical IT load or a Microsoft compute allocation

Ward County, Texas, US

No delivery date disclosed

Agreement signed
Deal details

Ionic leased its full 234 MW Ward County capacity to Nscale for an AI/HPC campus. Its filing says the powered campus has operated since 2023 and monthly lease payments began in August 2026. Nscale's October 1 update says the Ward site is live and delivering thousands of GPUs, but it does not identify those GPUs as Microsoft capacity. The 234 MW is site power, not customer IT load. The campus announcement's approximately 240 MW figure is not added as a second record.

Ionic Digital lease announcement ↗Ionic Digital Q2 2026 results, filed August 19, 2026 ↗Nscale reports Ward County live and delivering GPUs ↗Related: Microsoft / Nscale · 2025-10-15Related: Nscale / Ionic Digital · 2026-07-28Assess this deal
Source ↗
Sep 30, 2025

Meta

CoreWeave

Cloud compute

Up to $14.2B · Through Dec 2031

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Filed September 30 for a September 25 order. Up to approximately $14.2B through December 2031, subject to delivery and availability terms. An option to expand through 2032 is separate.

CoreWeave SEC filing ↗Related: Meta / CoreWeave · 2026-04-09Assess this deal
Source ↗
Sep 25, 2025

OpenAI

CoreWeave

Cloud compute

Up to $6.5B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

September expansion only. CoreWeave also disclosed a $4B May expansion and approximately $22.4B in cumulative OpenAI contracts. Do not add the cumulative figure again.

CoreWeave announcement ↗Related: OpenAI / CoreWeave · 2025-03-10Assess this deal
Source ↗
Sep 23, 2025

OpenAI

Oracle

Cloud compute

$300B+ · 5 years

Up to 4.5 GW

Planned compute capacity

United States · multiple sites

No delivery date disclosed

Agreement signed
Deal details

September disclosure of the July Oracle agreement: over $300B across five years and up to 4.5 GW of additional Stargate capacity. This is part of the Stargate program, not capacity additional to its headline total. For Project Jupiter, Oracle proposed an Energy Service Agreement with El Paso Electric on October 13 to support late-stage construction, initial commissioning, emergency backup, and worker life safety. On October 15, Oracle said its revised fuel-cell permit reduced permitted emissions by 35%; on October 22, it described the private microgrid plan and stated up to 2.45 GW of installed fuel-cell generation capacity. Oracle's October 13 update says campus scope and planned capacity did not change. The 2.45 GW power-system rating is recorded separately from this compute agreement. These releases do not confirm energization or a revised customer delivery date. Oracle's reported force-majeure notice and debt-market concerns remain unverified in company or regulatory filings; they are not treated as changed contract terms. The proposed utility agreement does not disclose an MW allocation; its expected $10M annual power payment is not compute-contract value or project investment. A separate proposed ratepayer credit is not campus capacity or customer compute.

Oracle announcement ↗Oracle proposed Project Jupiter energy service agreement, October 13, 2026 ↗Oracle Project Jupiter construction-permitting statement, September 14, 2026 ↗Oracle revised Project Jupiter microgrid permit, October 15, 2026 ↗Oracle Project Jupiter self-supplied power plan, October 22, 2026 ↗Oracle Project Jupiter scope update, October 13, 2026 ↗Related: OpenAI / Stargate (SoftBank, Oracle, MGX) · 2025-01-21Assess this deal
Source ↗
Sep 16, 2025

Microsoft

Microsoft Azure

Cloud compute

Undisclosed

50 MW

Announced AI capacity at the Loughton site; source separately says power allocation can scale to 90 MW, but does not define that as delivered IT load

Loughton, Essex, UK

Microsoft withdrew from the customer agreement in October 2026 before first compute; Nscale has not announced a replacement customer or revised site delivery date

Agreement ended
Deal details

Nscale's January 2025 UK investment announcement said the Loughton site was scheduled to be live in Q4 2026. Its September 2025 Microsoft deployment announcement stated 50 MW of AI capacity, scalable to 90 MW, with 23,040 GB300 GPUs targeted from Q1 2027. These were separate site-readiness and customer-service targets. On October 19, 2026, Reuters reported Microsoft's spokesperson confirmed that its decision to terminate the Loughton agreement related to this single site. Nscale said it remains committed to the site and UK expansion, is exploring alternative power sources, and has a strong long-term relationship with Microsoft for other projects. The 50 MW is retained as the historical announced customer allocation, not a current Microsoft commitment. The Microsoft agreement ended before first compute; the 2027 customer target no longer applies. Nscale has not announced a replacement customer or revised site delivery date. Reported grid delays into the 2030s are not a confirmed energization date. The 90 MW figure remains a possible site power scale, not IT load or contracted Microsoft capacity. The separate UK-wide investment plan and Stargate UK framework are not added to this site record.

Hardware: 23,040 NVIDIA GB300 GPUs initially

Nscale UK commitment announcement ↗The Guardian report on Loughton power delay, September 24, 2026 ↗Nscale UK site investment announcement, January 13, 2025 ↗Bloomberg report on the Microsoft withdrawal, October 18, 2026 ↗Reuters report on the Microsoft withdrawal, October 18, 2026 ↗The Register report quoting Nscale on Loughton, October 19, 2026 ↗ITPro report quoting Microsoft and Nscale on Loughton, October 19, 2026 ↗Reuters report quoting Microsoft and Nscale on Loughton, October 19, 2026 ↗Assess this deal
Source ↗
Sep 8, 2025

Microsoft

Nebius

Cloud compute

$17.4B · Approx. · through 2031

Undisclosed

Vineland, New Jersey, US

Late 2025 (announced target)

Delivery reported

Agreement signed
Deal details

Approximately $17.4B for dedicated GPU capacity, subject to deployment and availability. Additional services could increase the value to approximately $19.4B. Microsoft can terminate delayed tranches under the filing’s conditions.

Nebius announcement ↗Nebius September 8 SEC filing ↗Nebius August 12, 2026 shareholder letter, page 5 ↗Assess this deal
Source ↗
Aug 28, 2025

CoreWeave

Applied Digital

Campus build

Undisclosed

150 MW

Incremental critical IT load; Building 4

Ellendale, North Dakota, US

2027 (planned ready for service)

2–15 months to target

Agreement signed
Deal details

Third lease dated August 28 adds 150 MW to the initial 250 MW, bringing CoreWeave’s campus allocation to 400 MW. The record contains only the incremental allocation. Reported campus delivery remains attached to the original record to avoid counting it twice.

Applied Digital quarterly filing ↗Related: CoreWeave / Applied Digital · 2025-06-02Assess this deal
Source ↗
Aug 14, 2025

Fluidstack

TeraWulf

Campus build

Undisclosed

200+ MW

Critical IT load; approximately 250 MW gross facility capacity

Lake Mariner, New York, US

First approximately 40 MW targeted for first half of 2026

Delivery reported

Agreement signed
Deal details

Two ten-year hosting agreements. Approximately $3.7B initial-term revenue; $8.7B includes optional extensions. Google’s $1.8B backstop and warrants are financing support, not another compute purchase. The 160 MW expansion is separate. The August 2026 filing reports partial lease commencement by June 30, with later phases extending into early 2027. Its 102 MW energized figure covers Lake Mariner across customers, not a Fluidstack allocation.

TeraWulf August 14 announcement ↗TeraWulf August 5, 2026 filing, lease commencement ↗Assess this deal
Source ↗
Jul 31, 2025

OpenAI

Nscale / Aker

Campus build

Undisclosed

Undisclosed

Nscale and Aker announced 230 MW initial campus capacity; possible overlap with the separately reported Narvik campus

Kvandal, Narvik, Norway

100,000 NVIDIA GPUs targeted by end of 2026

0–3 months to target

Build announced
Deal details

Nscale and Aker announced a 230 MW initial campus with ambition for another 290 MW. Nscale later disclosed a possible 115 MW Narvik expansion backed by an uncommitted financing feature. OpenAI welcomed the opportunity to be an initial offtaker; the announcement does not state a signed OpenAI capacity allocation. OpenAI's page describes a 500 MW data center. These figures may describe the Narvik development also covered by Microsoft/Nscale announcements, so this record is excluded from capacity totals. Nscale and Aker said they committed about $1B to an initial 20 MW phase; this is project financing/investment, not an OpenAI contract value. The end-2026 target is a GPU deployment target, not proof of first energization.

Hardware: 100,000 NVIDIA GPUs targeted initially

Nscale, Aker and OpenAI announce Stargate Norway ↗OpenAI, Introducing Stargate Norway ↗Nscale, Stargate Norway project background ↗Nscale Norway financing and possible 115 MW expansion ↗Related: Microsoft / Nscale · 2026-04-14Related: Nscale / Nordkraft · 2026-07-06Assess this deal
Source ↗
Jul 15, 2025

CoreWeave

Chirisa Technology Parks / Machine Investment Group

Campus build

Up to $6B

100 MW

Initial data-center capacity; IT versus facility basis unspecified

Lancaster County, Pennsylvania, US

No delivery date disclosed

Letter of intent
Deal details

CoreWeave described its intent to commit up to $6B to equip a new Lancaster data center. The source states an initial 100 MW facility with potential expansion to 300 MW, but does not define the MW basis or give a first-capacity date. The amount is an infrastructure commitment, not a signed compute purchase or annual capital expenditure. The 300 MW expansion is potential and is not added to the stated 100 MW initial capacity.

CoreWeave, Pennsylvania data center announcement ↗CoreWeave, Pennsylvania data center announcement ↗Assess this deal
Source ↗
Jul 1, 2025

Undisclosed buyer

MEEZA

Cloud compute

More than QAR 350 million over a term exceeding 10 years

4 MW

Data centre expansion capacity; source does not identify whether 4 MW is IT load or total facility power

Qatar

No delivery date disclosed

Agreement signed
Deal details

MEEZA announced a long-term agreement with an unnamed global hyperscaler to use a 4 MW data centre expansion. MEEZA valued the contract at more than QAR 350 million over more than ten years. On July 1, 2026, MEEZA said the expansion was handed over on June 21 after signing a ready-for-service certificate. The source does not name the customer or define the MW basis; retain the native currency and exclude 4 MW from power aggregates until the basis is known.

MEEZA global hyperscaler agreement ↗MEEZA confirms handover and ready-for-service milestone ↗Assess this deal
Source ↗
Jun 22, 2025

Amazon Web Services

SK Group

Campus build

Undisclosed

Undisclosed

Data center for AWS AI Zone; project MW and AWS customer allocation are undisclosed

Ulsan, South Korea

Operations expected by 2027

2–15 months to target

Agreement signed
Deal details

SK Group and AWS signed a 15-year strategic partnership to build a data center in Ulsan for a new AWS AI Zone. SK Group leads construction; AWS will establish the AI Zone and provide cloud capabilities. SK Telecom's July 3, 2025 update retains the 2027 initial-operations target and says a combined total above 300 MW by 2030 includes Ulsan and the Guro data center; it does not give Ulsan's site capacity or MW basis. The 300 MW is not assigned to this record. The source gives no contract value or later delivery confirmation. The Ulsan project is related to broader SK data-center plans, so no group-level capacity is assigned to this record.

SK Group and AWS Ulsan AI Zone partnership ↗SK Telecom's Ulsan and Guro development plan ↗Related: SK Hyper / SK Telecom / SK Hyper · 2026-07-23Related: SK Horizon / SK Telecom / KKR / IMM Investment-Stonebridge · 2026-08-27Assess this deal
Source ↗
Jun 2, 2025

CoreWeave

Applied Digital

Campus build

Undisclosed

250 MW

Critical IT load under initial leases

Ellendale, North Dakota, US

First 100 MW targeted for Q4 2025

Delivery reported

Agreement signed
Deal details

Initial leases cover 250 MW for approximately 15 years, with approximately $7B expected revenue. A separate 150 MW option was subsequently exercised, taking the campus to 400 MW under contract. The initial allocation is not the whole campus. Hosting revenue is excluded from compute purchase totals.

Applied Digital June 2 filing ↗Applied Digital fiscal Q4 2026 results ↗Applied Digital fiscal Q1 2027 results, filed October 7, 2026 ↗Assess this deal
Source ↗
Mar 25, 2025

Nscale

InfraPartners

Campus build

Undisclosed

60 MW

Announced site capacity after expansion; source says the existing 30 MW facility would expand to 60 MW

Glomfjord, Norway

Expanded facility targeted to go live in Q2 2025

Target elapsed · confirm delivery

Build announced
Deal details

The 60 MW announcement is the planned total site capacity, not an incremental 60 MW above the existing 30 MW. The Q2 2025 go-live target has elapsed. Nscale's current site page, checked October 25, 2026, states 30 MW operational capacity, expandable to 60 MW; it gives no dated confirmation that the expansion reached 60 MW. Bloomberg reported on October 15, 2026 that construction was six months behind schedule and that 6.4 MW of the planned 30 MW was operating in early October. This reported operating amount conflicts with Nscale's 30 MW operational-capacity statement and has no published utility or company measurement cited here. Keep the source claims separate; do not replace the announced 60 MW site capacity or count either claim as an independently verified energized-power total. Bloomberg also reported delay penalties owed to customers, citing people familiar with the matter, without a public amount or filing that confirms the liability.

Nscale and InfraPartners Glomfjord expansion ↗Nscale Glomfjord site status, checked October 26, 2026 ↗Bloomberg report on Glomfjord construction delays, October 15, 2026 ↗Assess this deal
Source ↗
Mar 10, 2025

OpenAI

CoreWeave

Cloud compute

Up to $11.9B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Initial compute agreement. Later expansions are separate records; the September cumulative figure is not another contract.

CoreWeave announcement ↗Related: OpenAI / CoreWeave · 2025-09-25Assess this deal
Source ↗
Jan 21, 2025

OpenAI

Stargate (SoftBank, Oracle, MGX)

Campus build

$100B · $500B intended over four years

Undisclosed

United States · starts in Texas

Texas buildout underway at announcement

Build announced
Deal details

Stargate is a new company that intends to invest $500B over four years in U.S. AI infrastructure for OpenAI, beginning with $100B. Initial equity funders: SoftBank, OpenAI, Oracle, and MGX. Technology partners: Arm, Microsoft, NVIDIA, Oracle, and OpenAI. This is a project-company build, not a bilateral cloud offtake. The $100B figure is the initial deployment; the $500B figure is the stated intention.

OpenAI, Announcing The Stargate Project ↗Related: OpenAI / Oracle · 2025-09-23Assess this deal
Source ↗
Dec 23, 2024

xAI

NVIDIA

Campus build

Undisclosed

Undisclosed

Location undisclosed

In use by December 2024

In use at announcement
Deal details

xAI reported a 100,000-Hopper-GPU Colossus training system in use. The $6B funding round is not a compute contract price. This record describes a self-build milestone.

Hardware: 100,000 NVIDIA Hopper GPUs

xAI company update ↗Assess this deal
Source ↗
Dec 6, 2024

Cohere

Government of Canada

Campus build

Undisclosed

Undisclosed

Canada · site not named

No delivery date disclosed

Build announced
Deal details

Government announcement of support for a Canadian AI data center serving Cohere. The up-to-C$240M government contribution is not the total project cost or a compute purchase price. Builders are not named in this source.

Government of Canada announcement ↗Assess this deal
Source ↗
Oct 24, 2024

Sarvam AI

Yotta

Cloud compute

Undisclosed

Undisclosed

India

Sarvam 1 training completed on Shakti Cloud at announcement

In use at announcement
Deal details

Yotta reports Sarvam 1 was trained on Shakti Cloud in India. Uses the October 24, 2024 announcement date in the body; the page header says November 24. Price, reserved GPU count and MW are undisclosed. Sarvam released 30B and 105B models on March 6, 2026, trained in India using IndiaAI Mission compute. That later release does not identify Yotta as their provider and is not a new compute contract.

Yotta Sarvam 1 partnership (October 24 body date; November 24 page date) ↗Sarvam March 6, 2026 model release ↗Assess this deal
Source ↗
May 8, 2024

Tencent

Tencent Greater Bay Area Computing Center

Campus build

RMB 5 billion stated project investment

Undisclosed

Approximately 30,000 standard racks and phase-one operating capability for 200,000 servers; MW and power basis undisclosed

Shaoguan, Guangdong, China

Shaoguan municipal government targeted project production by year-end 2026; no dated commissioning evidence found

0–3 months to target

Build announced
Deal details

Shaoguan Daily reported that Tencent and Shaoguan signed an investment agreement on May 8, 2024 for a Greater Bay Area computing center. The municipal source states RMB 5 billion total project investment, about 30,000 standard racks, and phase-one operating capability for 200,000 servers. It gives no MW, rack power, GPU quantity, or energized-power measurement. A July 20, 2026 city update said it would push Tencent and GDS projects into production before year-end; this is a government target, not confirmation that the Tencent site is live. Later Shaoguan cluster totals and the October 25 six-cluster report are not attributed to this site because their project boundaries are unclear.

Hardware: AI, large-model, cloud-computing and IoT workloads; phase-one server capability is not a GPU count

Tencent Shaoguan project investment agreement signing ↗Shaoguan municipal government, 2026 compute-cluster update ↗Shaoguan municipal government, district data-center cluster update ↗Assess this deal
Source ↗

From a delivery target to a power assessment

Use Time to Power to assess site readiness with grid, permitting, and project evidence. Workspace access is required.

Coverage and sources

Selected public compute agreements, infrastructure investments, and self-build milestones. Each record links to a company announcement or regulatory source. Dates and agreement status describe the cited announcement; delivery targets are not confirmation that capacity is available today.

Contract values, project budgets, and campus capacity can overlap. We do not add them into a market total. Missing figures remain undisclosed, and original currencies are retained. Financing rounds and government grants are not compute purchase prices.

Coverage is strongest in North America and Europe. Chinese labs and providers, private agreements, and smaller regional operators are not yet comprehensively covered. An absent company does not mean it has no deals.

Suggest a deal or correction