Research / Infrastructure

AI compute deals. When will the power arrive?

Who is buying capacity, who is building it, and when it is expected. Agreements and projects across AI labs, cloud providers, and neoclouds.

Dataset updated Sep 29, 2026 · Latest announcement Sep 28, 2026

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases7.75 GW10.5 GW300 MW
IT power leases1.77 GW—200 MW
Campus projects1.9 GW——

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

$443.4B

Stated contract values, over their full terms

Additional upper-limit values

Up to $45.4B

Additional minimum values

Over $401B

16 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 21 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Google1———0 of 1
Anthropic85 GW6 GW300 MW3 of 8
Thinking Machines Lab1———0 of 1
Perplexity1———0 of 1
Palantir1———0 of 1
Figure1———1 of 1
Undisclosed buyer6———3 of 6
Mistral AI2———1 of 2
Together AI1———1 of 1
CoreWeave4———3 of 4
Crusoe1———0 of 1
Nscale3———1 of 3
Yotta1———0 of 1
Microsoft6———4 of 6
Meta3———1 of 3
OpenAI72.75 GW4.5 GW—0 of 7
NVIDIA2———0 of 2
Fluidstack1———1 of 1
xAI1———0 of 1
Cohere1———0 of 1
Sarvam AI1———0 of 1

Time to Power

When is capacity expected?

19 dated targets · 34 without a first-capacity window

Assess a site →

1 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

Reported delivery

IREN / Microsoft · 50 MW horizon 1 delivered

First 50 MW IT deployment delivered to Microsoft in August 2026; part of the 200 MW contract. Exact energization date undisclosed. Horizon 2 was commissioning; Horizon 3–4 targeted Q4 2026 delivery.

Company update · 2026-08-27 ↗

Nebius / Microsoft · MW undisclosed · all contracted tranches delivered

Nebius reports delivery of all Microsoft contract tranches, including two in the preceding month. Customer MW and exact energization dates are undisclosed.

Company update · 2026-08-12 ↗

TeraWulf / Fluidstack · MW undisclosed · partial lease commencement

One Fluidstack lease had partially commenced by June 30. Customer-specific delivered MW are undisclosed; the original approximately 40 MW tranche is not confirmed in full.

Company update · 2026-08-05 ↗

Applied Digital / CoreWeave · 175 MW ready for service

Polaris Forge 1 campus; part of 400 MW contracted. Report date, not energization date.

Company update · 2026-07-27 ↗

2025

Delivery reported

Microsoft / Nebius

Vineland, New Jersey, US · Late 2025 (announced target)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2025

Delivery reported

CoreWeave / Applied Digital

Ellendale, North Dakota, US · First 100 MW targeted for Q4 2025

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Original target passed

Anthropic / SpaceX

Site not disclosed · May 2026 (original target; later May–June ramp disclosed)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

Delivery reported

Fluidstack / TeraWulf

Lake Mariner, New York, US · First approximately 40 MW targeted for first half of 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–4 months away

Anthropic / CoreWeave

Site not disclosed · Later in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–4 months away

Nscale / Verne

Iceland · Deployment planned in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–7 months away

Together AI / IBM Cloud

Site not disclosed · Expected availability Q1 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

9–16 months away

Figure / Nscale

Barstow, Texas, United States · Initial GPU deployment targeted for H2 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Undisclosed buyer / Applied Digital

Boyce, Louisiana, US · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Undisclosed buyer / Applied Digital

United States; state not identified in cited release · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Microsoft / Nscale

Narvik, Norway · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Anthropic / Google / Broadcom

Primarily United States · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Microsoft / Crusoe

Abilene, Texas, US · First building: mid-2027

First power · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Meta / Nebius

Multiple locations · not named · Early 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Microsoft / Nscale

Mason County, West Virginia, US · Late 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Mistral AI / EcoDataCenter

Borlänge, Sweden · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

CoreWeave / Applied Digital

Ellendale, North Dakota, US · 2027 (planned ready for service)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

15–22 months away

Undisclosed buyer / Applied Digital

Southern United States; state undisclosed · First half of 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

15–28 months away

CoreWeave / Local facility partners

Indonesia · three facilities · 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 32 announcements disclose no MW allocation. 4 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

53 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Sep 28, 2026

Google

Crusoe

Campus build

Undisclosed

Undisclosed

Armstrong County, Texas, United States

No delivery date disclosed

Build announced
Deal details

Google campus under construction since June 2025. Connected to Goodnight 1 wind farm (265.5 MW, operational) and Goodnight 2 (265.5 MW, under construction). Wind generation ratings are not campus load or energized IT capacity. Campus MW, agreement value and first-capacity date are undisclosed. Separate from Crusoe’s Abilene campuses.

Crusoe September 28 Google campus announcement ↗Assess this deal
Source ↗
Sep 24, 2026

Anthropic

Akamai

Cloud compute

$11.6B · Seven years from each project plan’s service start

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Project Plans 2 and 3 signed September 18 under the May 5 master agreement. Approximately $11.6B is subject to delivery, availability and termination provisions. Potential additional $9B, equity warrants and supplier capital spending are excluded. Site, MW and dated first service are undisclosed.

Hardware: CPU cloud infrastructure

Akamai September 24 Anthropic expansion ↗Akamai September 24 Form 8-K ↗Assess this deal
Source ↗
Sep 23, 2026

Thinking Machines Lab

Crusoe

Cloud compute

$65 million annually

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Dedicated managed inference for Thinking Machines Lab. The disclosed amount is annual pricing, not a lifetime contract value. Site, MW allocation and dated first-service milestone are undisclosed. Customer commentary describes production use but does not establish a delivery or energization date.

Hardware: NVIDIA HGX B200 / Quantum-2 InfiniBand

Crusoe September 23 inference agreement ↗Assess this deal
Source ↗
Sep 16, 2026

Anthropic

Zerra DC / Australian Data Centres / Macquarie Capital

Campus build

Undisclosed

Undisclosed

Western Downs, Queensland, Australia

No delivery date disclosed

Agreement signed
Deal details

The consortium signed lease documentation with an Australian Anthropic subsidiary for the first stage of Western Downs Digital Park, subject to customary approvals. The disclosure does not specify leased MW, contract value or delivery date. Consortium funding obligations also remain subject to approvals. Campus estimates are not an Anthropic allocation.

Dexus September 16 regulatory disclosure via EQS ↗Assess this deal
Source ↗
Sep 15, 2026

Perplexity

Crusoe

Cloud compute

Undisclosed

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Perplexity contracted Crusoe Cloud for model training and managed inference. Contract value, GPU count, MW allocation, sites and first-service date are undisclosed. Crusoe also plans to adopt Perplexity software for its employees; that reciprocal software purchase is not additional compute capacity.

Hardware: NVIDIA GB300 NVL72 clusters / InfiniBand

Crusoe September 15 partnership announcement ↗Assess this deal
Source ↗
Sep 8, 2026

Palantir

Nebius

Strategic partnership

Undisclosed

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Preferred sovereign infrastructure partnership and planned integration for Palantir customers. No dedicated megawatt allocation or compute purchase value is disclosed. Excluded from investment and capacity totals.

Company announcement ↗Assess this deal
Source ↗
Sep 3, 2026

Figure

Nscale

Cloud compute

$3.5B · Multi-year; exact term undisclosed

Undisclosed

Barstow, Texas, United States

Initial GPU deployment targeted for H2 2027

9–16 months to target

Agreement signed
Deal details

Initial compute commitment for Figure’s Helix models. Intent to expand above $6B is not an additional signed commitment. Nscale’s separate equity investment is undisclosed and excluded. GPU count is a potential upper limit; customer MW and energization date are undisclosed. Deployment target does not establish operational delivery.

Hardware: Potential deployment of up to 100,000 NVIDIA Vera Rubin GPUs

Nscale September 3 Figure agreement ↗Assess this deal
Source ↗
Sep 1, 2026

Undisclosed buyer

Green Mountain

Campus build

Undisclosed

14 MW

Data centre capacity; IT versus facility power not specified

LON-East, Romford, London, UK

Capacity described as recently delivered; customer occupancy date undisclosed

Agreement signed
Deal details

An unnamed neocloud operator contracted 14 MW within the 37 MW LON-East campus. Company-reported facility delivery does not establish customer occupancy or a utility energization date. Price and term are undisclosed. The campus total is not the customer allocation.

Green Mountain September 1 company announcement ↗Assess this deal
Source ↗
Aug 31, 2026

Undisclosed buyer

E2E Networks

Cloud compute

Approx. INR 1,000 crore (excluding taxes)

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Binding term sheet with an unnamed sovereign AI company based in India for Blackwell cloud GPUs and allied services. Customer identity is undisclosed; do not attribute the order to Sarvam. Site, MW, GPU count and first-service date are undisclosed. Original INR value is retained without currency conversion.

Hardware: NVIDIA Blackwell cloud GPUs; count undisclosed

E2E Networks August 31 binding term sheet filing ↗Assess this deal
Source ↗
Aug 11, 2026

Mistral AI

European enterprise coalition

Campus build

Undisclosed

Up to 1 GW

Program ambition · possible project overlap

Europe · sites not allocated

Program target: 2030

Build announced
Deal details

Program ambition for up to 1 GW by 2030, supported by enterprise compute commitments. Individual sites and incremental capacity beyond earlier Mistral projects are not allocated in this announcement. Excluded from physical capacity totals.

Company announcement ↗Related: Mistral AI / EcoDataCenter · 2026-02-11Assess this deal
Source ↗
Aug 11, 2026

Together AI

IBM Cloud

Cloud compute

$240M · Multi-year; exact term undisclosed

Undisclosed

Location undisclosed

Expected availability Q1 2027

3–7 months to target

Agreement signed
Deal details

Dedicated IBM Cloud cluster for Together AI open-source inference. Site, MW and GPU count are undisclosed. Expected availability is a target, not delivery evidence. Together AI’s separate financing is excluded.

Hardware: NVIDIA HGX B300 / Spectrum-X

IBM August 11 Together AI agreement ↗Assess this deal
Source ↗
Aug 4, 2026

CoreWeave

Local facility partners

Campus build

Undisclosed

360 MW

Contracted IT power · three facilities

Indonesia · three facilities

2028

15–28 months to target

Build announced
Deal details

Three Indonesian facilities with 360 MW of contracted IT power, expected online in 2028. This is the regional deployment allocation, not CoreWeave’s global contracted-power total.

Company announcement ↗Assess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

300 MW

Critical IT load

Boyce, Louisiana, US

2027

3–16 months to target

Agreement signed
Deal details

Delta Forge 1: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 results ↗Assess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

210 MW

Critical IT load

Southern United States; state undisclosed

First half of 2028

15–22 months to target

Agreement signed
Deal details

Delta Forge 2: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 results ↗Assess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

300 MW

Critical IT load

United States; state not identified in cited release

2027

3–16 months to target

Agreement signed
Deal details

Polaris Forge 3: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 results ↗Assess this deal
Source ↗
Jul 15, 2026

Crusoe

Lancium

Campus build

Undisclosed

1 GW

Planned campus capacity

Childress, Texas, US

No delivery date disclosed

Build announced
Deal details

Crusoe and Lancium announced a 1 GW campus for an unnamed hyperscale customer. Construction is expected to start in Q3 2026. This is a separate project from IREN’s Childress campus.

Crusoe announcement ↗Assess this deal
Source ↗
Jul 6, 2026

Nscale

Nordkraft

Strategic partnership

Undisclosed

Undisclosed

Narvik, Norway

No delivery date disclosed

Agreement signed
Deal details

Joint operations company for the existing Narvik development. Its planned 2026 start refers to the operations company, not energized customer capacity. No incremental power allocation or contract value is disclosed.

Nscale July 6 announcement ↗Related: Microsoft / Nscale · 2026-04-14Assess this deal
Source ↗
Jun 24, 2026

CoreWeave

Conapto

Campus build

Undisclosed

Undisclosed

Stockholm, Sweden

Initial capacity online at announcement

In use at announcement
Deal details

Colocation agreement across two campuses. CoreWeave stated that initial capacity at Stockholm 4 South was already online. No deal-specific power allocation or contract value is disclosed. The company-wide active and contracted power figures are not assigned to these campuses.

CoreWeave investor announcement ↗Assess this deal
Source ↗
May 6, 2026

Anthropic

SpaceX

Cloud compute

$1.25B/month

300+ MW

Colossus 1 compute

Location undisclosed

May 2026 (original target; later May–June ramp disclosed)

Target elapsed · confirm delivery

Agreement signed
Deal details

The May 6 announcement covers more than 300 MW at Colossus 1. SpaceX’s June 5 prospectus describes later agreements across Colossus 1 and 2: approximately 325,000 GPUs and $1.25B per month through May 2029, with reduced fees during the May–June ramp. Either party can terminate on 90 days’ notice after the initial three months. No guaranteed total or incremental MW is inferred. Orbital compute remains an expression of interest.

Hardware: 220,000+ NVIDIA GPUs

Anthropic, SpaceX compute deal ↗SpaceX June 5, 2026 prospectus, section 4.3.4.5 ↗Assess this deal
Source ↗
Apr 30, 2026

Yotta

Gorilla Technology

Strategic partnership

Approx. $2.5B project value (July update)

Undisclosed

New Delhi, India (July 21 update)

Original deployment completion target: September 30, 2026; first service date undisclosed

Agreement signed
Deal details

Expansion separate from the earlier 5,120-GPU programme. April disclosure valued this project at approximately $2.8B; July 21 described Yotta 2 at approximately $2.5B without reconciling the difference. September 8 reports equipment deliveries across the wider Yotta programme, not operational acceptance of this tranche. Project value remains outside compute-purchase totals. No MW conversion is inferred from GPU count.

Hardware: 20,736 NVIDIA B300 GPUs

Yotta April 30 expansion announcement ↗Gorilla July 21 project value and location update ↗Gorilla September 8 equipment delivery update ↗Related: NVIDIA / Yotta · 2026-02-18Assess this deal
Source ↗
Apr 29, 2026

Undisclosed buyer

E2E Networks

Cloud compute

$7.7M · Six months

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Executed agreement with an unnamed US AI service provider specialising in large-scale model training. Committed value covers GPU cloud computing and allied services for six months. Customer identity, site, GPU count, MW and service commencement are undisclosed.

E2E Networks April 29 exchange filing ↗Assess this deal
Source ↗
Apr 20, 2026

Anthropic

Amazon Web Services

Cloud compute

$100B+ · 10 years

Up to 5 GW

Trainium and related compute

Location undisclosed

Nearly 1 GW by end of 2026

Agreement signed
Deal details

Anthropic committed more than $100B over ten years to AWS technologies for up to 5 GW of new Trainium and related capacity. Nearly 1 GW is expected before the end of 2026. Amazon also announced a $5B equity investment, with up to $20B more later; those equity figures are omitted from the dollar column.

Hardware: Trainium2–4

Anthropic, Amazon compute collaboration ↗Assess this deal
Source ↗
Apr 14, 2026

Microsoft

Nscale

Cloud compute

Undisclosed

Undisclosed

Narvik, Norway

2027

3–16 months to target

Agreement signed
Deal details

Expanded Microsoft agreement adds more than 30,000 Rubin GPUs at Narvik in 2027. The 230 MW figure describes the campus, not the power allocated to this expansion.

Hardware: 30,000+ NVIDIA Rubin GPUs

Nscale announcement ↗Assess this deal
Source ↗
Apr 10, 2026

Anthropic

CoreWeave

Cloud compute

Undisclosed

Undisclosed

Location undisclosed

Later in 2026

0–4 months to target

Agreement signed
Deal details

Multi-year agreement to support Claude development and deployment, with capacity starting later in 2026. No exact dollar or megawatt figure is disclosed.

Company announcement ↗Assess this deal
Source ↗
Apr 9, 2026

Meta

CoreWeave

Cloud compute

$21B · Approx. · through Dec 2032

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Expanded agreement for approximately $21B through December 2032. Includes new capacity and exercise of an option under a previous order. Read with the earlier agreement rather than treating both as independent projects.

CoreWeave announcement ↗Related: Meta / CoreWeave · 2025-09-30Assess this deal
Source ↗
Apr 6, 2026

Anthropic

Google / Broadcom

Cloud compute

Undisclosed

5 GW

TPU compute · May 6 disclosure

Primarily United States

2027

3–16 months to target

Agreement signed
Deal details

The April 6 announcement is for multiple gigawatts of next-generation TPU capacity starting in 2027. Anthropic’s May 6 recap states a 5 GW agreement with Google and Broadcom. No public dollar figure appears on either Anthropic page. Builds on a prior October 2025 TPU-capacity increase.

Hardware: Google TPUs

Anthropic, Google and Broadcom compute partnership ↗Anthropic, May 6 capacity update ↗Assess this deal
Source ↗
Apr 2, 2026

Nscale

Fortum

Campus build

Undisclosed

Undisclosed

Harjavalta, Finland

No delivery date disclosed

Build announced
Deal details

Site securing and development agreement for the Sievari industrial area. Fortum supports grid design and permitting; preliminary land-sale work is underway. Power capacity remains subject to design and permitting. No first-capacity date or contract value is disclosed.

Nscale announcement ↗Assess this deal
Source ↗
Mar 27, 2026

Microsoft

Crusoe

Campus build

Undisclosed

900 MW

Planned campus capacity

Abilene, Texas, US

First building: mid-2027

3–16 months to target

Build announced
Deal details

New 900 MW campus serving Microsoft, next to the existing Abilene development. Includes two buildings and onsite generation. The combined 2.1 GW Abilene figure includes the existing campus.

Crusoe announcement ↗Assess this deal
Source ↗
Mar 16, 2026

Meta

Nebius

Cloud compute

Up to $27B · 5 years

Undisclosed

Multiple locations · not named

Early 2027

3–16 months to target

Agreement signed
Deal details

Includes $12B of dedicated capacity and up to $15B of additional capacity that remains after sales to other customers. The $27B ceiling is not all dedicated capacity.

Hardware: NVIDIA Vera Rubin

Nebius announcement ↗Assess this deal
Source ↗
Mar 16, 2026

Microsoft

Nscale

Cloud compute

Undisclosed

Up to 1.35 GW

Proposed compute capacity

Mason County, West Virginia, US

Late 2027

3–16 months to target

Letter of intent
Deal details

Letter of intent for up to 1.35 GW at Monarch. The campus’s potential power expansion above 8 GW is not the Microsoft allocation. A letter of intent is not a completed supply contract.

Hardware: NVIDIA Vera Rubin NVL72

Nscale announcement ↗Assess this deal
Source ↗
Feb 27, 2026

OpenAI

Amazon Web Services

Cloud compute

$100B · 8 years · expansion

2 GW

Approximately · Trainium compute

Location undisclosed

Trainium4 expected in 2027

Agreement signed
Deal details

An additional $100B over eight years expands the earlier $38B AWS agreement. Approximately 2 GW of Trainium capacity is included. Amazon’s equity investment is separate.

Hardware: Trainium3 / Trainium4

OpenAI announcement ↗Assess this deal
Source ↗
Feb 18, 2026

NVIDIA

Yotta

Cloud compute

$1B+ · Four years

Undisclosed

India

Host supercluster target: August 2026; NVIDIA service start unconfirmed

Agreement signed
Deal details

Four-year NVIDIA DGX Cloud engagement within Yotta's Blackwell Ultra supercluster. April says NVIDIA is expected to account for roughly half the tranche offtake. The full 20,736 GPUs, host facility MW and over $2B build budget are not NVIDIA allocations or additional contract value. The April deployment completion target is September 30, 2026. No customer service acceptance was verified.

Yotta February 18 NVIDIA DGX Cloud engagement ↗Yotta April 30 offtake and deployment update ↗Related: Yotta / Gorilla Technology · 2026-04-30Assess this deal
Source ↗
Feb 11, 2026

Mistral AI

EcoDataCenter

Campus build

€1.2B

Undisclosed

Borlänge, Sweden

2027

3–16 months to target

Build announced
Deal details

Long-term €1.2B infrastructure partnership at Borlänge. EcoDataCenter will build and operate the facility. The disclosed euro amount is retained without a dollar conversion.

Hardware: NVIDIA Vera Rubin

EcoDataCenter announcement ↗Assess this deal
Source ↗
Jan 14, 2026

OpenAI

Cerebras

Cloud compute

Undisclosed

750 MW

Inference compute

Location undisclosed

Phased through 2028

Agreement signed
Deal details

OpenAI announced 750 MW of inference compute to be introduced in phases through 2028. The announcement does not disclose a contract price or individual sites.

Hardware: Cerebras wafer-scale systems

OpenAI announcement ↗Assess this deal
Source ↗
Nov 20, 2025

Nscale

Verne

Campus build

Undisclosed

15 MW

Deployment power; IT versus facility basis not specified

Iceland

Deployment planned in 2026

0–4 months to target

Agreement signed
Deal details

15 MW deployment at Verne’s Icelandic campus. The power basis is not specified as critical IT load, so this figure remains outside the IT power subtotal.

Hardware: Approximately 4,600 NVIDIA Blackwell Ultra GPUs

Nscale announcement ↗Assess this deal
Source ↗
Nov 18, 2025

Anthropic

Microsoft Azure / NVIDIA

Cloud compute

$30B

Up to 1 GW

Additional compute capacity

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Anthropic committed to purchase $30B of Azure compute capacity and to contract additional capacity up to 1 GW, initially on NVIDIA Grace Blackwell and Vera Rubin systems. NVIDIA and Microsoft also committed to invest up to $10B and $5B in Anthropic; those equity figures are omitted from the dollar column. Amazon remains Anthropic’s stated primary cloud and training partner.

Hardware: Grace Blackwell / Vera Rubin

Anthropic, Microsoft and NVIDIA partnerships ↗Assess this deal
Source ↗
Nov 12, 2025

Anthropic

Fluidstack

Campus build

$50B

Undisclosed

Texas and New York, US

Sites coming online through 2026

Build announced
Deal details

Anthropic announced a $50B investment in U.S. computing infrastructure, building data centers with Fluidstack in Texas and New York. The announcement says Fluidstack can deliver gigawatts of power but does not state a megawatt figure. This is an infrastructure build, not a cloud offtake.

Anthropic, $50 billion American AI infrastructure ↗Assess this deal
Source ↗
Nov 10, 2025

NVIDIA

CoreWeave

Cloud compute

$6.3B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

The results recap a $6.3B NVIDIA arrangement; the September 9 order gives NVIDIA access to residual unsold capacity. This backstop can overlap capacity sold to other customers and is excluded from aggregate purchase values. The date identifies the cited results disclosure.

CoreWeave third-quarter results ↗CoreWeave registration filing: residual capacity terms ↗Assess this deal
Source ↗
Nov 3, 2025

Microsoft

IREN

Cloud compute

$9.7B · Approx. · 5 years

200 MW

Critical IT load · Horizon 1–4

Childress, Texas, US

Phased through 2026

Agreement signed
Deal details

Approximately $9.7B over five years, with 20% prepayment. Horizon 1–4 support 200 MW of critical IT load within the 750 MW Childress campus; the full campus is not assigned to this contract.

Hardware: NVIDIA GB300

IREN announcement ↗IREN August 27 FY26 results: Horizon 1 delivery ↗Assess this deal
Source ↗
Nov 3, 2025

Microsoft

Lambda

Cloud compute

Undisclosed

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Multibillion-dollar agreement for tens of thousands of NVIDIA GPUs. No exact contract price or megawatt allocation is disclosed in the announcement.

Hardware: NVIDIA GPUs, including GB300 NVL72

Lambda announcement ↗Assess this deal
Source ↗
Oct 28, 2025

OpenAI

Microsoft Azure

Cloud compute

$250B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Microsoft disclosed an incremental $250B Azure services purchase by OpenAI. The equity ownership and prior investment are separate from this services commitment.

Microsoft quarterly filing ↗Assess this deal
Source ↗
Sep 30, 2025

Meta

CoreWeave

Cloud compute

Up to $14.2B · Through Dec 2031

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Filed September 30 for a September 25 order. Up to approximately $14.2B through December 2031, subject to delivery and availability terms. An option to expand through 2032 is separate.

CoreWeave SEC filing ↗Related: Meta / CoreWeave · 2026-04-09Assess this deal
Source ↗
Sep 25, 2025

OpenAI

CoreWeave

Cloud compute

Up to $6.5B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

September expansion only. CoreWeave also disclosed a $4B May expansion and approximately $22.4B in cumulative OpenAI contracts. Do not add the cumulative figure again.

CoreWeave announcement ↗Related: OpenAI / CoreWeave · 2025-03-10Assess this deal
Source ↗
Sep 23, 2025

OpenAI

Oracle

Cloud compute

$300B+ · 5 years

Up to 4.5 GW

Planned compute capacity

United States · multiple sites

No delivery date disclosed

Agreement signed
Deal details

September disclosure of the July Oracle agreement: over $300B across five years and up to 4.5 GW of additional Stargate capacity. This is part of the Stargate program, not capacity additional to its headline total.

Oracle announcement ↗Related: OpenAI / Stargate (SoftBank, Oracle, MGX) · 2025-01-21Assess this deal
Source ↗
Sep 8, 2025

Microsoft

Nebius

Cloud compute

$17.4B · Approx. · through 2031

Undisclosed

Vineland, New Jersey, US

Late 2025 (announced target)

Delivery reported

Agreement signed
Deal details

Approximately $17.4B for dedicated GPU capacity, subject to deployment and availability. Additional services could increase the value to approximately $19.4B. Microsoft can terminate delayed tranches under the filing’s conditions.

Nebius announcement ↗Nebius September 8 SEC filing ↗Nebius August 12, 2026 shareholder letter, page 5 ↗Assess this deal
Source ↗
Aug 28, 2025

CoreWeave

Applied Digital

Campus build

Undisclosed

150 MW

Incremental critical IT load; Building 4

Ellendale, North Dakota, US

2027 (planned ready for service)

3–16 months to target

Agreement signed
Deal details

Third lease dated August 28 adds 150 MW to the initial 250 MW, bringing CoreWeave’s campus allocation to 400 MW. The record contains only the incremental allocation. Reported campus delivery remains attached to the original record to avoid counting it twice.

Applied Digital quarterly filing ↗Related: CoreWeave / Applied Digital · 2025-06-02Assess this deal
Source ↗
Aug 14, 2025

Fluidstack

TeraWulf

Campus build

Undisclosed

200+ MW

Critical IT load; approximately 250 MW gross facility capacity

Lake Mariner, New York, US

First approximately 40 MW targeted for first half of 2026

Delivery reported

Agreement signed
Deal details

Two ten-year hosting agreements. Approximately $3.7B initial-term revenue; $8.7B includes optional extensions. Google’s $1.8B backstop and warrants are financing support, not another compute purchase. The 160 MW expansion is separate. The August 2026 filing reports partial lease commencement by June 30, with later phases extending into early 2027. Its 102 MW energized figure covers Lake Mariner across customers, not a Fluidstack allocation.

TeraWulf August 14 announcement ↗TeraWulf August 5, 2026 filing, lease commencement ↗Assess this deal
Source ↗
Jun 2, 2025

CoreWeave

Applied Digital

Campus build

Undisclosed

250 MW

Critical IT load under initial leases

Ellendale, North Dakota, US

First 100 MW targeted for Q4 2025

Delivery reported

Agreement signed
Deal details

Initial leases cover 250 MW for approximately 15 years, with approximately $7B expected revenue. A separate 150 MW option was subsequently exercised, taking the campus to 400 MW under contract. The initial allocation is not the whole campus. Hosting revenue is excluded from compute purchase totals.

Applied Digital June 2 filing ↗Applied Digital fiscal Q4 2026 results ↗Assess this deal
Source ↗
Mar 10, 2025

OpenAI

CoreWeave

Cloud compute

Up to $11.9B

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Initial compute agreement. Later expansions are separate records; the September cumulative figure is not another contract.

CoreWeave announcement ↗Related: OpenAI / CoreWeave · 2025-09-25Assess this deal
Source ↗
Jan 21, 2025

OpenAI

Stargate (SoftBank, Oracle, MGX)

Campus build

$100B · $500B intended over four years

Undisclosed

United States · starts in Texas

Texas buildout underway at announcement

Build announced
Deal details

Stargate is a new company that intends to invest $500B over four years in U.S. AI infrastructure for OpenAI, beginning with $100B. Initial equity funders: SoftBank, OpenAI, Oracle, and MGX. Technology partners: Arm, Microsoft, NVIDIA, Oracle, and OpenAI. This is a project-company build, not a bilateral cloud offtake. The $100B figure is the initial deployment; the $500B figure is the stated intention.

OpenAI, Announcing The Stargate Project ↗Related: OpenAI / Oracle · 2025-09-23Assess this deal
Source ↗
Dec 23, 2024

xAI

NVIDIA

Campus build

Undisclosed

Undisclosed

Location undisclosed

In use by December 2024

In use at announcement
Deal details

xAI reported a 100,000-Hopper-GPU Colossus training system in use. The $6B funding round is not a compute contract price. This record describes a self-build milestone.

Hardware: 100,000 NVIDIA Hopper GPUs

xAI company update ↗Assess this deal
Source ↗
Dec 6, 2024

Cohere

Government of Canada

Campus build

Undisclosed

Undisclosed

Canada · site not named

No delivery date disclosed

Build announced
Deal details

Government announcement of support for a Canadian AI data center serving Cohere. The up-to-C$240M government contribution is not the total project cost or a compute purchase price. Builders are not named in this source.

Government of Canada announcement ↗Assess this deal
Source ↗
Oct 24, 2024

Sarvam AI

Yotta

Cloud compute

Undisclosed

Undisclosed

India

Sarvam 1 training completed on Shakti Cloud at announcement

In use at announcement
Deal details

Yotta reports Sarvam 1 was trained on Shakti Cloud in India. Uses the October 24, 2024 announcement date in the body; the page header says November 24. Price, reserved GPU count and MW are undisclosed. Sarvam released 30B and 105B models on March 6, 2026, trained in India using IndiaAI Mission compute. That later release does not identify Yotta as their provider and is not a new compute contract.

Yotta Sarvam 1 partnership (October 24 body date; November 24 page date) ↗Sarvam March 6, 2026 model release ↗Assess this deal
Source ↗

From a delivery target to a power assessment

Use Time to Power to assess site readiness with grid, permitting, and project evidence. Workspace access is required.

Coverage and sources

Selected public compute agreements, infrastructure investments, and self-build milestones. Each record links to a company announcement or regulatory source. Dates and agreement status describe the cited announcement; delivery targets are not confirmation that capacity is available today.

Contract values, project budgets, and campus capacity can overlap. We do not add them into a market total. Missing figures remain undisclosed, and original currencies are retained. Financing rounds and government grants are not compute purchase prices.

Coverage is strongest in North America and Europe. Chinese labs and providers, private agreements, and smaller regional operators are not yet comprehensively covered. An absent company does not mean it has no deals.

Suggest a deal or correction