Fluidstack / TeraWulf / Abernathy Joint Venture: Abernathy HPC Campus campus, October 2025

Announced Oct 28, 2025 · 168 MW · Undisclosed

TeraWulf's October 28, 2025 filing says the Abernathy Joint Venture would provide Fluidstack with 168 MW of critical IT load. The full campus was pre-leased under a 25-year sublease with Google credit enhancement. TeraWulf's November 6, 2026 Form 10-Q says the JV had not commenced operations as of September 30, 2026 and that TeraWulf sold its entire 50.1% interest to Fluidstack and other purchasers for approximately $530 million. That sale consideration is an ownership transaction, not customer contract value or data-center investment. The filing gives no first-capacity date; delivered and energized MW remain unknown.

First-capacity target: not disclosed