Undisclosed buyer / Undisclosed U.S. investment-grade hyperscaler: Polaris Forge 2 campus, October 2025
Announced Oct 22, 2025 · 200 MW · ~US$5B in announcement and 10-K; ~US$4B in proxy; unreconciled
Applied Digital disclosed a 15-year lease for 200 MW of critical IT load at Polaris Forge 2, with the customer identified only as an investment-grade U.S. hyperscaler. The October 2025 announcement and FY2026 Form 10-K state approximately US$5 billion of expected contract revenue; the September 2026 proxy states approximately US$4 billion for the same lease. The difference is unresolved, so no numeric contract value is included in financial totals. The campus is described as having 300 MW of total critical IT capacity at full build; that is a campus figure and is not added to the separate 200 MW lease allocation. The original announcement expected initial operations in 2026; the 10-K gives a 2H 2026–1H 2027 delivery schedule. The October 2026 results target 300 MW across all North Dakota campuses by year-end, but do not report a Polaris Forge 2 tranche or confirm energization. Harwood voters rejected a charter measure requiring added review of industrial and data-center development; that vote did not itself change the lease or establish a delivery milestone.
First-capacity target: Initial capacity expected in 2H 2026; full capacity in early 2027. The FY2026 lease schedule gives 2H 2026–1H 2027 for the 200 MW. October 2026 results target 300 MW across all North Dakota campuses by year-end, without assigning a specific Polaris Forge 2 tranche.
Assess the delivery assumptions
Check the site, power connection, permits, and delivery milestones behind this agreement with GreenCIO.