CoreWeave compute deals
Public agreements, delivery targets, and source evidence for CoreWeave.
Market overview
The commitments behind the buildout
Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.
| Layer | Stated amount | Up to | More than |
|---|---|---|---|
| Compute purchases | — | — | — |
| IT power leases | 782.5 MW | — | — |
| Campus projects | — | — | — |
Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.
USD compute agreements
—
Stated contract values over their full terms
Additional upper-limit values
—
Additional minimum values
—
0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.
Compare buyers · 1 companies
| Buyer / developer | Agreements | Compute: stated | Compute: up to | Compute: over | Dated targets |
|---|---|---|---|---|---|
| CoreWeave | 7 | — | — | — | 4 of 7 |
Time to Power
When is capacity expected?
4 dated targets · 3 without a first-capacity window
0 elapsed targets await delivery evidence
Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.
Actual time to power: not established
Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.
Reported delivery
atNorth / CoreWeave · MW undisclosed · majority of planned it capacity online
CoreWeave did not state the exact live MW quantity, initial online date, or metered energized power.
Applied Digital / CoreWeave · 250 MW ready for service
Polaris Forge 1 campus; 250 MW of critical IT load live as of October 1, 2026, out of 400 MW contracted. Ready for service is a company-reported operational milestone; it does not establish the date of utility energization.
2025
Delivery reported
Ellendale, North Dakota, US · First 100 MW targeted for Q4 2025
First compute capacity · A first phase may cover only part of the agreement.
2027
2–15 months away
Ellendale, North Dakota, US · 2027 (planned ready for service)
First compute capacity · A first phase may cover only part of the agreement.
2028
19–23 months away
Navi Mumbai, India · Mid-2028 (first phase expected to be available)
First compute capacity · A first phase may cover only part of the agreement.
2028
14–27 months away
Indonesia · three facilities · 2028
First compute capacity · A first phase may cover only part of the agreement.
How to read these dates and figures
Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 1 announcements disclose no MW allocation. 2 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.
7 announcements
| Announced | Buyer / partner | Value | Capacity | Location / timing | Details |
|---|---|---|---|---|---|
| Oct 27, 2026 | CoreWeave CoreWeave / atNorth Campus build | Undisclosed | 22.5 MW Planned IT capacity at DEN01; CoreWeave says the majority is online, but does not quantify the live portion or report utility-metered power | Copenhagen, Denmark The majority of planned IT capacity was online by October 27, 2026; the initial online date is not stated | In use at announcementDeal detailsCoreWeave says most of the planned 22.5 MW of IT capacity at atNorth DEN01 was online on October 27, 2026. The exact online quantity and initial service date are not disclosed. This is a named IT-capacity project, not a utility measurement of energized power. CoreWeave's 1.5 GW active-power and 4.2 GW contracted-power figures are company-wide snapshots from June and August, respectively, and are not added to this site record. Hardware: NVIDIA Blackwell systems CoreWeave Denmark deployment announcement ↗Assess this deal |
| Oct 6, 2026 | CoreWeave CoreWeave / AdaniConneX Campus build | Undisclosed | 240 MW Three 80 MW data-center buildings; IT-load versus facility-power basis is not stated | Navi Mumbai, India Mid-2028 (first phase expected to be available) 19–23 months to target | Build announcedDeal detailsCoreWeave plans 240 MW of data-center capacity across three 80 MW buildings at AdaniConneX's Taloja campus. CoreWeave is the sole tenant and plans to deploy Vera Rubin systems. The source does not define the MW basis. The first phase is expected to be available in mid-2028; this is a planned availability target, not delivery or energization evidence. A further 240 MW is an expansion opportunity and is not included. Hardware: NVIDIA Vera Rubin platform planned CoreWeave and AdaniConneX India campus announcement ↗Related: CoreWeave / CoreWeave / atNorth · 2026-10-27Assess this deal |
| Aug 4, 2026 | CoreWeave Local facility partners Campus build | Undisclosed | 360 MW Contracted IT power · three facilities | Indonesia · three facilities 2028 14–27 months to target | Build announcedDeal detailsThree Indonesian facilities with 360 MW of contracted IT power, expected online in 2028. This is the regional deployment allocation, not CoreWeave’s global contracted-power total. Company announcement ↗Assess this deal |
| Jun 24, 2026 | CoreWeave Conapto Campus build | Undisclosed | Undisclosed | Stockholm, Sweden Initial capacity online at announcement | Build announcedDeal detailsColocation agreement across two campuses. CoreWeave stated that initial capacity at Stockholm 4 South was already online. No deal-specific power allocation or contract value is disclosed. The company-wide active and contracted power figures are not assigned to these campuses. CoreWeave investor announcement ↗Assess this deal |
| Aug 28, 2025 | CoreWeave Applied Digital Campus build | Undisclosed | 150 MW Incremental critical IT load; Building 4 | Ellendale, North Dakota, US 2027 (planned ready for service) 2–15 months to target | Agreement signedDeal detailsThird lease dated August 28 adds 150 MW to the initial 250 MW, bringing CoreWeave’s campus allocation to 400 MW. The record contains only the incremental allocation. Reported campus delivery remains attached to the original record to avoid counting it twice. Applied Digital quarterly filing ↗Related: CoreWeave / Applied Digital · 2025-06-02Assess this deal |
| Jul 15, 2025 | CoreWeave Chirisa Technology Parks / Machine Investment Group Campus build | Up to $6B | 100 MW Initial data-center capacity; IT versus facility basis unspecified | Lancaster County, Pennsylvania, US No delivery date disclosed | Letter of intentDeal detailsCoreWeave described its intent to commit up to $6B to equip a new Lancaster data center. The source states an initial 100 MW facility with potential expansion to 300 MW, but does not define the MW basis or give a first-capacity date. The amount is an infrastructure commitment, not a signed compute purchase or annual capital expenditure. The 300 MW expansion is potential and is not added to the stated 100 MW initial capacity. CoreWeave, Pennsylvania data center announcement ↗CoreWeave, Pennsylvania data center announcement ↗Assess this deal |
| Jun 2, 2025 | CoreWeave Applied Digital Campus build | Undisclosed | 250 MW Critical IT load under initial leases | Ellendale, North Dakota, US First 100 MW targeted for Q4 2025 Delivery reported | Agreement signedDeal detailsInitial leases cover 250 MW for approximately 15 years, with approximately $7B expected revenue. A separate 150 MW option was subsequently exercised, taking the campus to 400 MW under contract. The initial allocation is not the whole campus. Hosting revenue is excluded from compute purchase totals. Applied Digital June 2 filing ↗Applied Digital fiscal Q4 2026 results ↗Applied Digital fiscal Q1 2027 results, filed October 7, 2026 ↗Assess this deal |