Crusoe compute deals
Public agreements, delivery targets, and source evidence for Crusoe.
Market overview
The commitments behind the buildout
Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.
| Layer | Stated amount | Up to | More than |
|---|---|---|---|
| Compute purchases | — | — | — |
| IT power leases | 158 MW | — | — |
| Campus projects | 1.008 GW | — | — |
Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.
USD compute agreements
—
Stated contract values over their full terms
Additional upper-limit values
—
Additional minimum values
—
0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.
Compare buyers · 1 companies
| Buyer / developer | Agreements | Compute: stated | Compute: up to | Compute: over | Dated targets |
|---|---|---|---|---|---|
| Crusoe | 7 | — | — | — | 4 of 7 |
Time to Power
When is capacity expected?
4 dated targets · 3 without a first-capacity window
0 elapsed targets await delivery evidence
Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.
Actual time to power: not established
Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.
Reported delivery
Polar Data Centers / Crusoe · 12 MW dra01 is live and powering crusoe cloud
Polar and Crusoe state that DRA01 provides 12 MW of IT capacity and is live. The announcement does not give a utility energization date.
2027
2–9 months away
Snyder, Texas, US · 1H 2027 (August target; July release said Q1 2027)
First power · A first phase may cover only part of the agreement.
2027
7–11 months away
Adjacent to the Itaipu substation, Paraguay · Initial deployment planned for mid-2027
First compute capacity · A first phase may cover only part of the agreement.
2027
11–15 months away
Tørdal, Norway · Expected live in late 2027
First compute capacity · A first phase may cover only part of the agreement.
2027
2–15 months away
Idaho National Laboratory, Idaho, US · Crusoe Spark proof of concept targeted for 2027
First power · A first phase may cover only part of the agreement.
How to read these dates and figures
Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 1 announcements disclose no MW allocation. 1 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.
7 announcements
| Announced | Buyer / partner | Value | Capacity | Location / timing | Details |
|---|---|---|---|---|---|
| Oct 22, 2026 | Crusoe Araico Strategic partnership | Undisclosed | 106 MW Path to scale to 106 MW of IT capacity; not the initial deployment capacity. Further expansion to approximately 280 MW total is an option and its measurement basis is unspecified. | Adjacent to the Itaipu substation, Paraguay Initial deployment planned for mid-2027 7–11 months to target | Agreement signedDeal detailsCrusoe and Araico announced a strategic partnership on October 22, 2026, for AI Cloud infrastructure adjacent to the Itaipu substation. The first deployment is planned for mid-2027. Crusoe describes a path to 106 MW of IT capacity and long-term options to expand to approximately 280 MW total, but it does not state when the 106 MW scale-up will be reached. The 106 MW is not initial capacity; the optional 280 MW is not additive and its basis is not specified. No investment amount or compute contract value is disclosed. This is not Araico's separately announced Iguazu AI Campus, and its campus estimates are not assigned here. Crusoe-Araico Paraguay AI Cloud partnership announcement ↗U.S. Department of State Paraguay fact sheet ↗Assess this deal |
| Oct 21, 2026 | Crusoe Polar Data Centers Campus build | Undisclosed | 12 MW IT capacity | Tørdal, Norway No delivery date disclosed | In use at announcementDeal detailsPolar and Crusoe report DRA01 as live, with 12 MW of IT capacity powering Crusoe Cloud. The stated capacity is IT load, not campus or utility power. The October 21 report date does not establish the energization date. Polar and Crusoe partnership expansion ↗Assess this deal |
| Oct 21, 2026 | Crusoe Polar Data Centers Campus build | Undisclosed | 40 MW Additional critical liquid-cooled IT capacity | Tørdal, Norway Expected live in late 2027 11–15 months to target | Build announcedDeal detailsCrusoe and Polar plan DRA02 as a separate phase with an additional 40 MW of critical liquid-cooled IT capacity, expected to go live in late 2027. This is a target, not delivery evidence. It is separate from the 12 MW live at DRA01. Polar and Crusoe partnership expansion ↗Assess this deal |
| Jul 30, 2026 | Crusoe Aalo Atomics Strategic partnership | Undisclosed | Undisclosed | Idaho National Laboratory, Idaho, US Crusoe Spark proof of concept targeted for 2027 2–15 months to target | Build announcedDeal detailsThe companies plan to run a Crusoe Spark modular data center on Aalo power in 2027 as a proof of concept. They also describe future Aalo Pods and 50 MWe reactor plants, but do not state a data-center power allocation. Aalo's 10 MWe reactor rating is not entered as delivered campus power. No MW, contract value or energization evidence is disclosed for the data center. Crusoe and Aalo Atomics announce nuclear-powered AI factory partnership ↗Assess this deal |
| Jul 27, 2026 | Crusoe Energy Vault Campus build | Undisclosed | 8 MW Contracted powered-shell capacity · Phase 1 | Snyder, Texas, US 1H 2027 (August target; July release said Q1 2027) 2–9 months to target | Build announcedDeal detailsEnergy Vault began construction on a powered-shell campus for Crusoe Cloud. Phase 1 is contracted for 8 MW and includes ten Crusoe Spark modular data centers. Energy Vault's August 11 filing reports a 1H 2027 commercial-operation target; the July 27 release gave Q1 2027. The release describes expansion potential to 25 MW in Phase 2 and planned site capacity up to 500 MW. Those are not contracted Phase 1 capacity and are excluded from totals. Construction is not energization; no delivered or energized MW is confirmed. Energy Vault, Snyder AI campus groundbreaking ↗Energy Vault Q2 2026 results, SEC Exhibit 99.1 ↗Assess this deal |
| Jul 15, 2026 | Crusoe Lancium Campus build | Undisclosed | 1 GW Planned campus capacity | Childress, Texas, US No delivery date disclosed | Build announcedDeal detailsCrusoe and Lancium announced a 1 GW campus for an unnamed hyperscale customer. Construction is expected to start in Q3 2026. This is a separate project from IREN’s Childress campus. Crusoe announcement ↗Assess this deal |
| Mar 24, 2026 | Crusoe Crusoe Cloud Strategic partnership | Undisclosed | 20 MW Power infrastructure partnership; the announcement does not reconcile the 20 MW figure with the existing 12 MW microgrid or state an incremental versus total basis | Sparks, Nevada No delivery date disclosed | Build announcedDeal detailsThe campus already operates four Crusoe Spark modular data centers on a 12 MW / 63 MWh microgrid. The announced expansion increases the deployment to 24 data centers and describes work with Redwood Energy at 20 MW, but does not state whether 20 MW is incremental or the final power-system total. Do not add this figure to power subtotals until the basis is reconciled. The source reports 99.2% operating availability for the existing system; that is not a new delivery milestone for the expansion. Crusoe and Redwood March 24 expansion announcement ↗Assess this deal |