NTT DATA compute deals

Public agreements, delivery targets, and source evidence for NTT DATA.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT load12 MW——
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. The layers can overlap and must not be added together. Announced capacity does not establish delivery or energization.

USD compute agreements

—

Stated contract values over their full terms

Additional upper-limit values

—

Additional minimum values

—

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
NTT DATA1———0 of 1

Time to Power

When is capacity expected?

0 dated targets · 1 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

Reported delivery

NTT DATA / NTT DATA · 12 MW jkt2a opened with stated 12 mw it capacity

NTT DATA announced the facility opening and 12 MW of critical IT load. This is reported IT capacity, not metered energized power or a customer compute allocation.

Source · 2026-11-03 ↗

No dated first-capacity targets in this selection.

How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 0 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

1 announcement

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Nov 3, 2026

NTT DATA

NTT Global Data Centers

Campus build

Undisclosed

12 MW

12 MW of critical IT load at an opened AI-ready data center; this is IT capacity, not facility power or measured energized draw

Central Jakarta, Indonesia

NTT DATA announced the facility opening on November 3, 2026; no customer-specific first-compute date or utility-metered power is stated

In use at announcement
Deal details

NTT DATA announced the opening of the Jakarta 2 Annex Data Center on November 3, 2026. The company states 12 MW of critical IT load and describes the facility as AI-ready. The release does not identify an AI customer, customer allocation, first workload date, facility power requirement, or metered energized draw. The 12 MW is IT capacity and must not be treated as campus power or actual electricity use.

NTT DATA JKT2A opening announcement ↗NTT DATA Jakarta 2 Annex facility specification ↗Assess this deal
Source ↗