QumulusAI compute deals
Public agreements, delivery targets, and source evidence for QumulusAI.
Market overview
The commitments behind the buildout
Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.
| Layer | Stated amount | Up to | More than |
|---|---|---|---|
| Compute purchases | — | — | — |
| IT power leases | — | — | — |
| Campus projects | — | — | — |
Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.
USD compute agreements
—
Stated contract values over their full terms
Additional upper-limit values
—
Additional minimum values
—
0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.
Compare buyers · 1 companies
| Buyer / developer | Agreements | Compute: stated | Compute: up to | Compute: over | Dated targets |
|---|---|---|---|---|---|
| QumulusAI | 1 | — | — | — | 1 of 1 |
Time to Power
When is capacity expected?
1 dated targets · 0 without a first-capacity window
0 elapsed targets await delivery evidence
Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.
Actual time to power: not established
Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.
2026
0–3 months away
Metropolitan Atlanta, Georgia, United States · Ready-for-service target Q4 2026, conditional on the current occupant transition; no completion evidence found
First compute capacity · A first phase may cover only part of the agreement.
How to read these dates and figures
Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 0 announcements disclose no MW allocation. 1 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.
1 announcement
| Announced | Buyer / partner | Value | Capacity | Location / timing | Details |
|---|---|---|---|---|---|
| Aug 20, 2026 | QumulusAI QumulusAI Campus build | Undisclosed | Up to 3.75 MW Up to 3.75 MW of data-center capacity under a seven-year colocation agreement; IT-load versus facility-power basis is not stated | Metropolitan Atlanta, Georgia, United States Ready-for-service target Q4 2026, conditional on the current occupant transition; no completion evidence found 0–3 months to target | Agreement signedDeal detailsQumulusAI signed a seven-year colocation agreement for up to 3.75 MW in metropolitan Atlanta, conditional on the current occupant leaving. QumulusAI states a Q4 2026 ready-for-service target and says the site could support up to 2,048 B300-class GPUs. A right of first offer for up to 7 MW is not contracted capacity and is not included. The source does not say whether 3.75 MW is critical IT load or facility power. The later US$211.9 million customer agreement uses this site, but the MW basis remains unclear and the planned site amount is not a delivered customer allocation. Hardware: Site expected to support up to 2,048 NVIDIA Blackwell B300-class GPUs QumulusAI Atlanta colocation agreement ↗Assess this deal |