Radiant compute deals
Public agreements, delivery targets, and source evidence for Radiant.
Market overview
The commitments behind the buildout
Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.
| Layer | Stated amount | Up to | More than |
|---|---|---|---|
| Compute purchases | — | — | — |
| IT power leases | — | — | — |
| Campus projects | — | 100 MW | — |
Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.
USD compute agreements
—
Stated contract values over their full terms
Additional upper-limit values
—
Additional minimum values
—
0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.
Compare buyers · 1 companies
| Buyer / developer | Agreements | Compute: stated | Compute: up to | Compute: over | Dated targets |
|---|---|---|---|---|---|
| Radiant | 1 | — | — | — | 1 of 1 |
Time to Power
When is capacity expected?
1 dated targets · 0 without a first-capacity window
0 elapsed targets await delivery evidence
Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.
Actual time to power: not established
Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.
2028
13–17 months away
North Yorkshire, England, UK · Phase 1 targets commercial operations from Q1 2028; planning, regulatory and network approvals, an anchor tenant, commercial agreements, and final investment decisions remain outstanding
First compute capacity · A first phase may cover only part of the agreement.
How to read these dates and figures
Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 0 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.
1 announcement
| Announced | Buyer / partner | Value | Capacity | Location / timing | Details |
|---|---|---|---|---|---|
| Nov 3, 2026 | Radiant Drax / Brookfield-Qai joint venture Campus build | Potential investment could exceed £20 billion across the full development, including £2.5 billion for Phase 1 | Up to 100 MW Up to 100 MW of Phase 1 data-centre compute capacity; source does not specify IT load versus total facility power and this is not energized power | North Yorkshire, England, UK Phase 1 targets commercial operations from Q1 2028; planning, regulatory and network approvals, an anchor tenant, commercial agreements, and final investment decisions remain outstanding 13–17 months to target | Agreement signedDeal detailsDrax, Brookfield and Radiant announced an agreement to develop the project, with capital support through Brookfield-Qai's AI infrastructure joint venture. Phase 1 targets up to 100 MW of data-centre compute capacity and commercial operations from Q1 2028. The first phase is planned to import power from the grid. The 4 GW of Drax grid access and 2.6 GW of dispatchable generation describe the power station, not this data-centre phase or delivered power. The wider project targets more than 1 GW across three phases; Phase 2's additional 500 MW is an ambition for 2028–2031 and Phase 3 has no quantity or date. Do not add these ambitions to Phase 1. Brookfield's potential investment estimate exceeds £20 billion, including chips, and includes £2.5 billion for Phase 1; neither amount is stated as spent or fully committed. No tenant has been secured. Keep the native GBP estimate out of USD capital totals. Q1 2028 is an operating target, not proof of construction, customer service, or energization. Drax RNS, strategic partnership for GW-scale data centre ↗Drax company announcement, November 3, 2026 ↗Assess this deal |