All compute deals

Tencent compute deals

Public agreements, delivery targets, and source evidence for Tencent.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT power leases———
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

USD compute agreements

—

Stated contract values over their full terms

Additional upper-limit values

—

Additional minimum values

—

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Tencent1———1 of 1

Time to Power

When is capacity expected?

1 dated targets · 0 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

2026

0–3 months away

Tencent / Tencent Greater Bay Area Computing Center

Shaoguan, Guangdong, China · Shaoguan municipal government targeted project production by year-end 2026; no dated commissioning evidence found

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 1 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

1 announcement

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
May 8, 2024

Tencent

Tencent Greater Bay Area Computing Center

Campus build

RMB 5 billion stated project investment

Undisclosed

Approximately 30,000 standard racks and phase-one operating capability for 200,000 servers; MW and power basis undisclosed

Shaoguan, Guangdong, China

Shaoguan municipal government targeted project production by year-end 2026; no dated commissioning evidence found

0–3 months to target

Build announced
Deal details

Shaoguan Daily reported that Tencent and Shaoguan signed an investment agreement on May 8, 2024 for a Greater Bay Area computing center. The municipal source states RMB 5 billion total project investment, about 30,000 standard racks, and phase-one operating capability for 200,000 servers. It gives no MW, rack power, GPU quantity, or energized-power measurement. A July 20, 2026 city update said it would push Tencent and GDS projects into production before year-end; this is a government target, not confirmation that the Tencent site is live. Later Shaoguan cluster totals and the October 25 six-cluster report are not attributed to this site because their project boundaries are unclear.

Hardware: AI, large-model, cloud-computing and IoT workloads; phase-one server capability is not a GPU count

Tencent Shaoguan project investment agreement signing ↗Shaoguan municipal government, 2026 compute-cluster update ↗Shaoguan municipal government, district data-center cluster update ↗Assess this deal
Source ↗