Together AI compute deals

Public agreements, delivery targets, and source evidence for Together AI.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT power leases———
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

$240M

Stated contract values, over their full terms

Additional upper-limit values

—

Additional minimum values

—

1 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Together AI1———1 of 1

Time to Power

When is capacity expected?

1 dated targets · 0 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

2027

3–7 months away

Together AI / IBM Cloud

Site not disclosed · Expected availability Q1 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 1 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

1 announcement

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Aug 11, 2026

Together AI

IBM Cloud

Cloud compute

$240M · Multi-year; exact term undisclosed

Undisclosed

Location undisclosed

Expected availability Q1 2027

3–7 months to target

Agreement signed
Deal details

Dedicated IBM Cloud cluster for Together AI open-source inference. Site, MW and GPU count are undisclosed. Expected availability is a target, not delivery evidence. Together AI’s separate financing is excluded.

Hardware: NVIDIA HGX B300 / Spectrum-X

IBM August 11 Together AI agreement ↗Assess this deal
Source ↗