Time to Power

When is AI compute capacity expected?

First-capacity targets that companies stated when they announced a deal. A target describes expected availability; it is not evidence that power or compute has been delivered.

Data as of Nov 23, 2026

Dated first-capacity targets
66
Passed without reported delivery
5
Records with reported delivery
24
Records without a dated target
105

A passed target is not a delay

Records whose target has passed still need delivery evidence. The date alone does not show a delay.

Actual time to power: not established

Measured time to power needs a dated start and site-level energization evidence. Announcements give neither.

Next 5 targets

Targets that have not passed and have no reported delivery, soonest deadline first. Only the target year is shown here.

  1. 2026First-capacity target

    QumulusAI / QumulusAI: Columbia colocation capacity

    Campus build · Agreement signed · Announced Nov 3, 2026

    Undisclosed

    0.5 MW

  2. 2026First-capacity target

    Nebius / Nebius

    Strategic partnership · Build announced · Announced May 20, 2026

    Undisclosed

    328 MW

  3. 2026First-capacity target

    Anthropic / CoreWeave

    Cloud compute · Agreement signed · Announced Apr 10, 2026

    Undisclosed

    Undisclosed

  4. 2026First-capacity target

    Gimlet Labs / Cerebras

    Strategic partnership · Build announced · Announced Sep 28, 2026

    Undisclosed

    100 MW

  5. 2026First-capacity target

    Tencent / Tencent Greater Bay Area Computing Center: Zhenjiang Industrial Park

    Campus build · Build announced · Announced May 8, 2024

    RMB 5 billion stated project investment

    Undisclosed

Signed-in workspaces

The full delivery schedule

  • All 66 dated targets in deadline order
  • The reviewed window and months remaining for each target
  • The 5 passed targets that still need delivery evidence
  • The 24 reported delivery milestones and their sources
  • Schedules filtered by buyer, provider, or deal type
  • CSV export with every target window

Access needs an approved GreenCIO workspace account.

How to read these dates

Dates are the windows companies announced. A vague year keeps the full year. Construction completion and chip release dates are not counted as first-capacity targets. A first phase may cover only part of an agreement. Method and coverage