Time to Power
When is AI compute capacity expected?
Data as of Nov 23, 2026
- Dated first-capacity targets
- 66
- Passed without reported delivery
- 5
- Records with reported delivery
- 24
- Records without a dated target
- 105
A passed target is not a delay
Records whose target has passed still need delivery evidence. The date alone does not show a delay.
Actual time to power: not established
Measured time to power needs a dated start and site-level energization evidence. Announcements give neither.
Next 5 targets
Targets that have not passed and have no reported delivery, soonest deadline first. Only the target year is shown here.
2026First-capacity target
QumulusAI / QumulusAI: Columbia colocation capacityCampus build · Agreement signed · Announced Nov 3, 2026
Undisclosed
0.5 MW
2026First-capacity target
Nebius / NebiusStrategic partnership · Build announced · Announced May 20, 2026
Undisclosed
328 MW
2026First-capacity target
Anthropic / CoreWeaveCloud compute · Agreement signed · Announced Apr 10, 2026
Undisclosed
Undisclosed
2026First-capacity target
Gimlet Labs / CerebrasStrategic partnership · Build announced · Announced Sep 28, 2026
Undisclosed
100 MW
2026First-capacity target
Tencent / Tencent Greater Bay Area Computing Center: Zhenjiang Industrial ParkCampus build · Build announced · Announced May 8, 2024
RMB 5 billion stated project investment
Undisclosed
The full delivery schedule
- All 66 dated targets in deadline order
- The reviewed window and months remaining for each target
- The 5 passed targets that still need delivery evidence
- The 24 reported delivery milestones and their sources
- Schedules filtered by buyer, provider, or deal type
- CSV export with every target window
Access needs an approved GreenCIO workspace account.
How to read these dates
Dates are the windows companies announced. A vague year keeps the full year. Construction completion and chip release dates are not counted as first-capacity targets. A first phase may cover only part of an agreement. Method and coverage