All compute deals

Gimlet Labs compute deals

Public agreements, delivery targets, and source evidence for Gimlet Labs.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT power leases———
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

—

Stated contract values, over their full terms

Additional upper-limit values

—

Additional minimum values

—

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Gimlet Labs1———1 of 1

Time to Power

When is capacity expected?

1 dated targets · 0 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

2026

0–3 months away

Gimlet Labs / Cerebras

Site not disclosed · First Cerebras-powered Gimlet Cloud datacenter expected later in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 0 announcements disclose no MW allocation. 1 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

1 announcement

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Sep 28, 2026

Gimlet Labs

Cerebras

Strategic partnership

Undisclosed

100 MW

Planned inference deployment; facility versus critical IT basis unspecified

Location undisclosed

First Cerebras-powered Gimlet Cloud datacenter expected later in 2026

0–3 months to target

Build announced
Deal details

Planned 100 MW deployment across the partnership, not a disclosed customer purchase or energized power measurement. Site, contract value and first-phase MW are undisclosed. Existing private inference traffic does not establish delivery of the planned cloud datacenter. The initial 2026 datacenter target is distinct from 2027 CS-4 access.

Hardware: Cerebras wafer-scale systems with GPUs; CS-4 access expected in 2027

Gimlet September 28 Cerebras deployment announcement ↗Cerebras September 28 partnership release ↗Assess this deal
Source ↗