All compute deals

Google compute deals

Public agreements, delivery targets, and source evidence for Google.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT power leases———
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

USD compute agreements

—

Stated contract values over their full terms

Additional upper-limit values

—

Additional minimum values

—

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Google4———1 of 4

Time to Power

When is capacity expected?

1 dated targets · 3 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

2027

1–14 months away

Google / Google / Blackstone

United States · site allocations undisclosed · Crux AI plans to bring its first 500 MW of TPU capacity online in 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 2 announcements disclose no MW allocation. 2 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

4 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Oct 6, 2026

Google

Constellation Energy

Strategic partnership

Undisclosed

890 MW

New nuclear generation capacity delivered to the PJM grid; not a data-center allocation

PJM Interconnection, United States

No delivery date disclosed

Agreement signed
Deal details

The 20-year agreement covers 890 MW of new nuclear capacity from uprates at 11 Constellation units, with the first uprate expected in 2028. A separate 15-year agreement supports 2,700 MW from existing generation on the PJM grid. Neither amount is a Google data-center allocation or evidence of energized data-center power. Constellation's stated $4.3B investment is not Google's contract value and is excluded.

Google and Constellation, PJM power agreement ↗Assess this deal
Source ↗
Sep 28, 2026

Google

Crusoe

Campus build

Undisclosed

Undisclosed

Armstrong County, Texas, United States

No delivery date disclosed

Build announced
Deal details

Google campus under construction since June 2025. Connected to Goodnight 1 wind farm (265.5 MW, operational) and Goodnight 2 (265.5 MW, under construction). Wind generation ratings are not campus load or energized IT capacity. Campus MW, agreement value and first-capacity date are undisclosed. Separate from Crusoe’s Abilene campuses.

Crusoe September 28 Google campus announcement ↗Assess this deal
Source ↗
Sep 9, 2026

Google

Google / Blackstone

Strategic partnership

$5 billion equity commitment; not a customer contract or construction spend

500 MW

Crux AI's planned first-phase TPU capacity; critical IT-load versus facility-power basis and site allocations are undisclosed

United States · site allocations undisclosed

Crux AI plans to bring its first 500 MW of TPU capacity online in 2027

1–14 months to target

Build announced
Deal details

Crux AI launched as the U.S.-based compute-as-a-service company formed through the Blackstone and Google TPU cloud venture. Crux says Blackstone funds committed $5 billion in equity and Google will provide TPUs, software, and services. Crux plans to bring its first 500 MW of TPU capacity online in 2027 as the initial phase of a multi-gigawatt roadmap. The 500 MW is provider-level planned compute capacity, not a customer allocation; the source does not define critical IT load versus facility power or disclose site allocations. Bloomberg reported delays at proposed sites, including Google's scrapped plan for Crusoe to build in Cheyenne, but did not quantify the affected share or report a revised Crux-wide target. Keep the 2027 target as announced; no dated operating or energization evidence is established. The $5 billion is an equity commitment to the platform, not customer contract value or disclosed construction spend, and is excluded from financial totals.

Hardware: Google Tensor Processing Units (TPUs)

Crux AI launch announcement, September 9, 2026 ↗Blackstone and Google TPU cloud joint venture announcement, May 18, 2026 ↗Google Cloud announcement, May 19, 2026 ↗Bloomberg report on Crux AI site delays, September 9, 2026 ↗Assess this deal
Source ↗
Sep 9, 2026

Google

Google Finland digital infrastructure program

Campus build

€13 billion Finland digital infrastructure, clean energy, and partnership investment program over two years

Undisclosed

Program covers multiple data centers, clean energy, and partnerships; no site-level capacity disclosed

Hamina, Kajaani, Muhos, and Vaala, Finland

No delivery date disclosed

Build announced
Deal details

Google announced a €13B two-year Finland program covering digital infrastructure, clean energy, and partnerships. This is not a site cost or contract value. Google named activity in Hamina, Kajaani, Muhos, and Vaala, but disclosed no site-level MW or first-capacity dates. On October 6, 2026, the Finnish Licensing and Supervision Agency asked Tuike Finland Oy to suspend work that significantly changes the environment at the planned Muhos and Kajaani sites by October 23, until the environmental impact assessments are complete. The notice does not cover planning, measurements, soil studies, or other low-impact and readily reversible work. It is a permitting and delivery risk, not evidence of energization or a revised delivery date.

Google Finland infrastructure announcement ↗Google Finland clean energy and infrastructure plan ↗Finnish Licensing and Supervision Agency notice, October 6, 2026 ↗Google Muhos location page, checked October 7, 2026 ↗Assess this deal
Source ↗