Google compute deals

Public agreements, delivery targets, and source evidence for Google.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT power leases———
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

—

Stated contract values, over their full terms

Additional upper-limit values

—

Additional minimum values

—

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Google1———0 of 1

Time to Power

When is capacity expected?

0 dated targets · 1 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

No dated first-capacity targets in this selection.

How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 1 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

1 announcement

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Sep 28, 2026

Google

Crusoe

Campus build

Undisclosed

Undisclosed

Armstrong County, Texas, United States

No delivery date disclosed

Build announced
Deal details

Google campus under construction since June 2025. Connected to Goodnight 1 wind farm (265.5 MW, operational) and Goodnight 2 (265.5 MW, under construction). Wind generation ratings are not campus load or energized IT capacity. Campus MW, agreement value and first-capacity date are undisclosed. Separate from Crusoe’s Abilene campuses.

Crusoe September 28 Google campus announcement ↗Assess this deal
Source ↗