All compute deals

Nebius compute deals

Public agreements, delivery targets, and source evidence for Nebius.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT power leases———
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

—

Stated contract values, over their full terms

Additional upper-limit values

—

Additional minimum values

—

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Nebius2———1 of 2

Time to Power

When is capacity expected?

1 dated targets · 1 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

2026

0–3 months away

Nebius / Nebius

Site not disclosed · First 328 MW fuel-cell project expected to be operational in 2026

First power · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 0 announcements disclose no MW allocation. 2 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

2 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Jun 8, 2026

Nebius

Nebius UK infrastructure deployments

Campus build

Approximately £1.7 billion investment across four UK capacity sites

65 MW

Combined capacity of three new NVIDIA infrastructure deployments at full ramp; source does not specify IT load versus facility power

United Kingdom

Three new deployments reach full ramp in 2027; first-capacity date not stated

Build announced
Deal details

Nebius states approximately £1.7B of investment for UK capacity buildout and three new deployments with 65 MW combined capacity at full ramp in 2027. The source does not define the MW basis or identify individual site allocations. The investment is in pounds and is not a compute contract value. A separate first UK deployment was already operating from November 2025 and is not included as a fourth deployment in the 65 MW figure.

Hardware: NVIDIA infrastructure; model and quantity not stated

Nebius UK expansion announcement ↗Assess this deal
Source ↗
May 20, 2026

Nebius

Nebius

Strategic partnership

Undisclosed

328 MW

Installed behind-the-meter fuel-cell generation capacity for an unnamed first US project; not compute, IT load, or confirmed energized power

Location undisclosed

First 328 MW fuel-cell project expected to be operational in 2026

0–3 months to target

Build announced
Deal details

The partners describe 328 MW of installed fuel-cell generation capacity for the first US project, expected to be operational in 2026. The release does not name the site or report commissioning, energization, or delivered compute. Keep the generation rating separate from data-center load and actual energized power.

Nebius and Bloom May 20 project announcement ↗Assess this deal
Source ↗