Nscale compute deals

Public agreements, delivery targets, and source evidence for Nscale.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT power leases———
Campus projects2.583 GW——

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

USD compute agreements

—

Stated contract values over their full terms

Additional upper-limit values

—

Additional minimum values

—

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Nscale8———4 of 8

Time to Power

When is capacity expected?

4 dated targets · 4 without a first-capacity window

Assess a site →

1 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

Reported delivery

Verne / Nscale · 7.5 MW first phase complete; 7.5 mw of gpu capacity deployed

Verne says 7.5 MW was deployed in the first phase, with 128 racks including 64 liquid-cooled NVIDIA GB300 racks. This is a first phase of the 15 MW agreement, not full delivery of the contracted amount.

Company update · 2026-04-23 ↗

Ionic Digital / Nscale · 234 MW ionic reports operating leased capacity; monthly rent began

Ionic states the Ward County campus is energized and operating and reports rent commencement for the 234 MW Nscale lease in August 2026. This verifies facility capacity under lease, not Microsoft GPU service delivery.

Company update · 2026-08-19 ↗

2025

Original target passed

Nscale / InfraPartners

Glomfjord, Norway · Expanded facility targeted to go live in Q2 2025

First power · A first phase may cover only part of the agreement.

Assess delivery →

2026

Delivery reported

Nscale / Verne

Iceland · Deployment planned in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

8–15 months away

Nscale / Ionic Digital

Ward County, Texas, US · Ionic expects the additional power to be energized in the second half of 2027, subject to approval

First power · A first phase may cover only part of the agreement.

Assess delivery →

2028

14–21 months away

Nscale / Nscale

Mason County, West Virginia, US · 1H 2028

First power · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 2 announcements disclose no MW allocation. 1 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

8 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Jul 28, 2026

Nscale

Ionic Digital

Campus build

Undisclosed

89 MW

Incremental site power under lease amendment; conditional on availability and regulatory approval, not IT load

Ward County, Texas, US

Ionic expects the additional power to be energized in the second half of 2027, subject to approval

8–15 months to target

Agreement signed
Deal details

The filing reports that a February 2026 lease amendment obligates Nscale to lease an additional 89 MW when available. Ionic expects to energize the increment in the second half of 2027, but the capacity is subject to regulatory approval and is not yet operating. This is incremental to the original 234 MW lease.

Ionic Digital SEC registration statement ↗Related: Nscale / Ionic Digital · 2025-10-14Assess this deal
Source ↗
Jul 6, 2026

Nscale

Nordkraft

Strategic partnership

Undisclosed

Undisclosed

Narvik, Norway

No delivery date disclosed

Agreement signed
Deal details

Joint operations company for the existing Narvik development. Its planned 2026 start refers to the operations company, not energized customer capacity. No incremental power allocation or contract value is disclosed.

Nscale July 6 announcement ↗Assess this deal
Source ↗
May 5, 2026

Nscale

Start Campus

Cloud compute

€465 million for the second building; €230 million for shared infrastructure

200 MW

Second campus building; facility capacity, not a customer compute allocation

Sines, Portugal

No delivery date disclosed

Build announced
Deal details

Nscale states a second 200 MW building and €465M investment in that building, plus €230M for shared infrastructure. The figures describe campus build and investment, not Microsoft's compute allocation or contract value. The campus is permitted for 1.2 GW; the full-campus figure is not added to this building. No energization date is stated for the building.

Nscale, SINES deployment announcement ↗Assess this deal
Source ↗
Apr 2, 2026

Nscale

Fortum

Campus build

Undisclosed

Undisclosed

Harjavalta, Finland

No delivery date disclosed

Build announced
Deal details

Site securing and development agreement for the Sievari industrial area. Fortum supports grid design and permitting; preliminary land-sale work is underway. Power capacity remains subject to design and permitting. No first-capacity date or contract value is disclosed.

Nscale announcement ↗Assess this deal
Source ↗
Mar 16, 2026

Nscale

Nscale

Campus build

Undisclosed

2 GW

Initial onsite powered-microgrid capacity

Mason County, West Virginia, US

1H 2028

14–21 months to target

Build announced
Deal details

Nscale announced its agreement to acquire AIPCorp and Monarch Compute Campus. Nscale states initial onsite microgrid power capacity of 2 GW is expected online by 1H 2028, with expansion to approximately 8 GW planned for 2031. The 2 GW is site power capacity, not a customer compute allocation or energized power. Microsoft's separate up-to-1.35 GW letter of intent at Monarch is linked and must not be added to the campus figure.

Nscale, AIPCorp and Monarch campus announcement ↗Assess this deal
Source ↗
Nov 20, 2025

Nscale

Verne

Campus build

Undisclosed

15 MW

Deployment power; IT versus facility basis not specified

Iceland

Deployment planned in 2026

Delivery reported

Agreement signed
Deal details

15 MW deployment at Verne’s Icelandic campus. The power basis is not specified as critical IT load, so this figure remains outside the IT power subtotal. Verne reported that the first 7.5 MW phase was deployed on April 23, 2026; this does not confirm the remaining 7.5 MW.

Hardware: Approximately 4,600 NVIDIA Blackwell Ultra GPUs

Nscale announcement ↗Data Center Dynamics reports the first-phase deployment ↗Assess this deal
Source ↗
Oct 14, 2025

Nscale

Ionic Digital

Campus build

Undisclosed

234 MW

Operating facility power capacity leased to Nscale; not critical IT load or a Microsoft compute allocation

Ward County, Texas, US

No delivery date disclosed

Agreement signed
Deal details

Ionic leased its full 234 MW Ward County capacity to Nscale for an AI/HPC campus. Its filing says the powered campus has operated since 2023 and monthly lease payments began in August 2026. Nscale's October 1 update says the Ward site is live and delivering thousands of GPUs, but it does not identify those GPUs as Microsoft capacity. The 234 MW is site power, not customer IT load. The campus announcement's approximately 240 MW figure is not added as a second record.

Ionic Digital lease announcement ↗Ionic Digital Q2 2026 results, filed August 19, 2026 ↗Nscale reports Ward County live and delivering GPUs ↗Related: Nscale / Ionic Digital · 2026-07-28Assess this deal
Source ↗
Mar 25, 2025

Nscale

InfraPartners

Campus build

Undisclosed

60 MW

Announced site capacity after expansion; source says the existing 30 MW facility would expand to 60 MW

Glomfjord, Norway

Expanded facility targeted to go live in Q2 2025

Target elapsed · confirm delivery

Build announced
Deal details

The 60 MW announcement is the planned total site capacity, not an incremental 60 MW above the existing 30 MW. The Q2 2025 go-live target has elapsed. Nscale's current site page, checked October 25, 2026, states 30 MW operational capacity, expandable to 60 MW; it gives no dated confirmation that the expansion reached 60 MW. Bloomberg reported on October 15, 2026 that construction was six months behind schedule and that 6.4 MW of the planned 30 MW was operating in early October. This reported operating amount conflicts with Nscale's 30 MW operational-capacity statement and has no published utility or company measurement cited here. Keep the source claims separate; do not replace the announced 60 MW site capacity or count either claim as an independently verified energized-power total. Bloomberg also reported delay penalties owed to customers, citing people familiar with the matter, without a public amount or filing that confirms the liability.

Nscale and InfraPartners Glomfjord expansion ↗Nscale Glomfjord site status, checked October 26, 2026 ↗Bloomberg report on Glomfjord construction delays, October 15, 2026 ↗Assess this deal