Nscale compute deals
Public agreements, delivery targets, and source evidence for Nscale.
Market overview
The commitments behind the buildout
Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.
| Layer | Stated amount | Up to | More than |
|---|---|---|---|
| Compute purchases | — | — | — |
| IT power leases | — | — | — |
| Campus projects | 2.583 GW | — | — |
Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.
USD compute agreements
—
Stated contract values over their full terms
Additional upper-limit values
—
Additional minimum values
—
0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.
Compare buyers · 1 companies
| Buyer / developer | Agreements | Compute: stated | Compute: up to | Compute: over | Dated targets |
|---|---|---|---|---|---|
| Nscale | 8 | — | — | — | 4 of 8 |
Time to Power
When is capacity expected?
4 dated targets · 4 without a first-capacity window
1 elapsed targets await delivery evidence
Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.
Actual time to power: not established
Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.
Reported delivery
Verne / Nscale · 7.5 MW first phase complete; 7.5 mw of gpu capacity deployed
Verne says 7.5 MW was deployed in the first phase, with 128 racks including 64 liquid-cooled NVIDIA GB300 racks. This is a first phase of the 15 MW agreement, not full delivery of the contracted amount.
Ionic Digital / Nscale · 234 MW ionic reports operating leased capacity; monthly rent began
Ionic states the Ward County campus is energized and operating and reports rent commencement for the 234 MW Nscale lease in August 2026. This verifies facility capacity under lease, not Microsoft GPU service delivery.
2025
Original target passed
Glomfjord, Norway · Expanded facility targeted to go live in Q2 2025
First power · A first phase may cover only part of the agreement.
2026
Delivery reported
Iceland · Deployment planned in 2026
First compute capacity · A first phase may cover only part of the agreement.
2027
8–15 months away
Ward County, Texas, US · Ionic expects the additional power to be energized in the second half of 2027, subject to approval
First power · A first phase may cover only part of the agreement.
2028
14–21 months away
Mason County, West Virginia, US · 1H 2028
First power · A first phase may cover only part of the agreement.
How to read these dates and figures
Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 2 announcements disclose no MW allocation. 1 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.
8 announcements
| Announced | Buyer / partner | Value | Capacity | Location / timing | Details |
|---|---|---|---|---|---|
| Jul 28, 2026 | Nscale Ionic Digital Campus build | Undisclosed | 89 MW Incremental site power under lease amendment; conditional on availability and regulatory approval, not IT load | Ward County, Texas, US Ionic expects the additional power to be energized in the second half of 2027, subject to approval 8–15 months to target | Agreement signedDeal detailsThe filing reports that a February 2026 lease amendment obligates Nscale to lease an additional 89 MW when available. Ionic expects to energize the increment in the second half of 2027, but the capacity is subject to regulatory approval and is not yet operating. This is incremental to the original 234 MW lease. Ionic Digital SEC registration statement ↗Related: Nscale / Ionic Digital · 2025-10-14Assess this deal |
| Jul 6, 2026 | Nscale Nordkraft Strategic partnership | Undisclosed | Undisclosed | Narvik, Norway No delivery date disclosed | Agreement signedDeal detailsJoint operations company for the existing Narvik development. Its planned 2026 start refers to the operations company, not energized customer capacity. No incremental power allocation or contract value is disclosed. Nscale July 6 announcement ↗Assess this deal |
| May 5, 2026 | Nscale Start Campus Cloud compute | €465 million for the second building; €230 million for shared infrastructure | 200 MW Second campus building; facility capacity, not a customer compute allocation | Sines, Portugal No delivery date disclosed | Build announcedDeal detailsNscale states a second 200 MW building and €465M investment in that building, plus €230M for shared infrastructure. The figures describe campus build and investment, not Microsoft's compute allocation or contract value. The campus is permitted for 1.2 GW; the full-campus figure is not added to this building. No energization date is stated for the building. Nscale, SINES deployment announcement ↗Assess this deal |
| Apr 2, 2026 | Nscale Fortum Campus build | Undisclosed | Undisclosed | Harjavalta, Finland No delivery date disclosed | Build announcedDeal detailsSite securing and development agreement for the Sievari industrial area. Fortum supports grid design and permitting; preliminary land-sale work is underway. Power capacity remains subject to design and permitting. No first-capacity date or contract value is disclosed. Nscale announcement ↗Assess this deal |
| Mar 16, 2026 | Nscale Nscale Campus build | Undisclosed | 2 GW Initial onsite powered-microgrid capacity | Mason County, West Virginia, US 1H 2028 14–21 months to target | Build announcedDeal detailsNscale announced its agreement to acquire AIPCorp and Monarch Compute Campus. Nscale states initial onsite microgrid power capacity of 2 GW is expected online by 1H 2028, with expansion to approximately 8 GW planned for 2031. The 2 GW is site power capacity, not a customer compute allocation or energized power. Microsoft's separate up-to-1.35 GW letter of intent at Monarch is linked and must not be added to the campus figure. Nscale, AIPCorp and Monarch campus announcement ↗Assess this deal |
| Nov 20, 2025 | Nscale Verne Campus build | Undisclosed | 15 MW Deployment power; IT versus facility basis not specified | Iceland Deployment planned in 2026 Delivery reported | Agreement signedDeal details15 MW deployment at Verne’s Icelandic campus. The power basis is not specified as critical IT load, so this figure remains outside the IT power subtotal. Verne reported that the first 7.5 MW phase was deployed on April 23, 2026; this does not confirm the remaining 7.5 MW. Hardware: Approximately 4,600 NVIDIA Blackwell Ultra GPUs Nscale announcement ↗Data Center Dynamics reports the first-phase deployment ↗Assess this deal |
| Oct 14, 2025 | Nscale Ionic Digital Campus build | Undisclosed | 234 MW Operating facility power capacity leased to Nscale; not critical IT load or a Microsoft compute allocation | Ward County, Texas, US No delivery date disclosed | Agreement signedDeal detailsIonic leased its full 234 MW Ward County capacity to Nscale for an AI/HPC campus. Its filing says the powered campus has operated since 2023 and monthly lease payments began in August 2026. Nscale's October 1 update says the Ward site is live and delivering thousands of GPUs, but it does not identify those GPUs as Microsoft capacity. The 234 MW is site power, not customer IT load. The campus announcement's approximately 240 MW figure is not added as a second record. Ionic Digital lease announcement ↗Ionic Digital Q2 2026 results, filed August 19, 2026 ↗Nscale reports Ward County live and delivering GPUs ↗Related: Nscale / Ionic Digital · 2026-07-28Assess this deal |
| Mar 25, 2025 | Nscale InfraPartners Campus build | Undisclosed | 60 MW Announced site capacity after expansion; source says the existing 30 MW facility would expand to 60 MW | Glomfjord, Norway Expanded facility targeted to go live in Q2 2025 Target elapsed · confirm delivery | Build announcedDeal detailsThe 60 MW announcement is the planned total site capacity, not an incremental 60 MW above the existing 30 MW. The Q2 2025 go-live target has elapsed. Nscale's current site page, checked October 25, 2026, states 30 MW operational capacity, expandable to 60 MW; it gives no dated confirmation that the expansion reached 60 MW. Bloomberg reported on October 15, 2026 that construction was six months behind schedule and that 6.4 MW of the planned 30 MW was operating in early October. This reported operating amount conflicts with Nscale's 30 MW operational-capacity statement and has no published utility or company measurement cited here. Keep the source claims separate; do not replace the announced 60 MW site capacity or count either claim as an independently verified energized-power total. Bloomberg also reported delay penalties owed to customers, citing people familiar with the matter, without a public amount or filing that confirms the liability. Nscale and InfraPartners Glomfjord expansion ↗Nscale Glomfjord site status, checked October 26, 2026 ↗Bloomberg report on Glomfjord construction delays, October 15, 2026 ↗Assess this deal |