Nscale / Ionic Digital: Ward County / Cedarvale campus expansion campus, July 2026

Announced Jul 28, 2026 · 89 MW · Undisclosed

The filing reports that a February 2026 lease amendment obligates Nscale to lease an additional 89 MW when available. Ionic expects to energize the increment in the second half of 2027, but the capacity is subject to regulatory approval and is not yet operating. This is incremental to the original 234 MW lease.

First-capacity target: Ionic expects the additional power to be energized in the second half of 2027, subject to approval

Assess the delivery assumptions

Check the site, power connection, permits, and delivery milestones behind this agreement with GreenCIO.