Yotta compute deals

Public agreements, delivery targets, and source evidence for Yotta.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT power leases———
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

USD compute agreements

—

Stated contract values over their full terms

Additional upper-limit values

—

Additional minimum values

—

0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Yotta2———0 of 2

Time to Power

When is capacity expected?

0 dated targets · 2 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

Reported delivery

Gorilla Technology / Yotta · MW undisclosed · first yotta 1 delivery phase reported delivered: 640 servers and 5,110 b200 gpus

Gorilla CEO said the first of four Yotta 1 phases had been delivered. This confirms reported equipment delivery only; it does not confirm installation, customer acceptance, first compute service, or energized MW.

Company update · 2026-09-22 ↗

No dated first-capacity targets in this selection.

How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 2 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

2 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Apr 30, 2026

Yotta

Gorilla Technology

Strategic partnership

Approx. $2.5B project value (July update)

Undisclosed

New Delhi, India (July 21 update)

Original September 30 completion target elapsed. Gorilla's August 24 earnings call set Yotta 1 and Yotta 2 Phase 1 completion by end-November; delivery and customer service remain unconfirmed.

Agreement signed
Deal details

Expansion separate from the earlier 5,120-GPU programme. April disclosure valued this project at approximately $2.8B; July 21 described Yotta 2 at approximately $2.5B without reconciling the difference. Gorilla's August 24 earnings call said Phase 2 equipment was being manufactured, with Yotta 1 and Yotta 2 Phase 1 targeted for completion by end-November. Its September 22 CEO interview scheduled B300 delivery to start in the first week of October in blocks of about 5,000 GPUs and said all Yotta deliveries were expected by year-end. The October start target has elapsed; no dated B300 delivery, installation, customer acceptance, service, or energization confirmation was found by November 3. The transcript says equipment requires setup and customer testing before billing. Gorilla's October 30 SEC filing reports an initial $25M financing close for previously announced data center projects; it does not assign proceeds to this Yotta tranche. Project value remains outside compute-purchase totals. No MW conversion is inferred from GPU count.

Hardware: 20,736 NVIDIA B300 GPUs

Yotta April 30 expansion announcement ↗Gorilla July 21 project value and location update ↗Gorilla September 8 equipment delivery update ↗Gorilla CEO September 22 Water Tower Research conference interview ↗Gorilla Q2 2026 earnings call, August 24 ↗Assess this deal
Source ↗
Mar 16, 2026

Yotta

Gorilla Technology

Strategic partnership

More than US$500M expected Gorilla revenue over five years; not project value or contract price

Undisclosed

Approximately 640 NVIDIA HGX B200 servers and more than 5,000 GPUs; no MW, IT-load or facility-power allocation disclosed

Navi Mumbai, India

Gorilla reported the first of four delivery phases, 640 servers and 5,110 B200 GPUs, delivered on September 22, 2026. Remaining phases were then scheduled through early October. Service acceptance and first compute date are undisclosed.

Agreement signed
Deal details

Gorilla signed binding agreements with Yotta for approximately 640 HGX B200 servers with more than 5,000 GPUs at Yotta's NM1 facility. Gorilla expected more than US$500M in revenue over five years; this is expected supplier revenue, not project value, capex or compute-purchase price. On September 22, Gorilla's CEO said the first of four delivery phases, 640 servers and 5,110 B200 GPUs, had been delivered. The remaining phases were scheduled through early October at that time. No site MW, IT-load allocation, customer acceptance, service start or utility energization is disclosed. Do not convert GPUs or use Yotta campus-wide power roadmaps as this tranche's capacity.

Hardware: Approximately 640 NVIDIA HGX B200 servers; Gorilla CEO identified 5,110 B200 GPUs

Gorilla and Yotta March 16 agreement announcement ↗Gorilla July 21, 2026 deployment and revenue update ↗Gorilla September 8, 2026 equipment-delivery update ↗Gorilla CEO September 22 Water Tower Research conference interview ↗Related: Yotta / Gorilla Technology · 2026-04-30Assess this deal
Source ↗