Anthropic compute deals

Public agreements, delivery targets, and source evidence for Anthropic.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases5 GW6 GW300 MW
IT power leases———
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

Compute purchase agreements

$41.6B

Stated contract values, over their full terms

Additional upper-limit values

—

Additional minimum values

Over $100B

3 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Anthropic85 GW6 GW300 MW3 of 8

Time to Power

When is capacity expected?

3 dated targets · 5 without a first-capacity window

Assess a site →

1 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

2026

Original target passed

Anthropic / SpaceX

Site not disclosed · May 2026 (original target; later May–June ramp disclosed)

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–4 months away

Anthropic / CoreWeave

Site not disclosed · Later in 2026

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

3–16 months away

Anthropic / Google / Broadcom

Primarily United States · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 4 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

8 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Sep 24, 2026

Anthropic

Akamai

Cloud compute

$11.6B · Seven years from each project plan’s service start

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Project Plans 2 and 3 signed September 18 under the May 5 master agreement. Approximately $11.6B is subject to delivery, availability and termination provisions. Potential additional $9B, equity warrants and supplier capital spending are excluded. Site, MW and dated first service are undisclosed.

Hardware: CPU cloud infrastructure

Akamai September 24 Anthropic expansion ↗Akamai September 24 Form 8-K ↗Assess this deal
Source ↗
Sep 16, 2026

Anthropic

Zerra DC / Australian Data Centres / Macquarie Capital

Campus build

Undisclosed

Undisclosed

Western Downs, Queensland, Australia

No delivery date disclosed

Agreement signed
Deal details

The consortium signed lease documentation with an Australian Anthropic subsidiary for the first stage of Western Downs Digital Park, subject to customary approvals. The disclosure does not specify leased MW, contract value or delivery date. Consortium funding obligations also remain subject to approvals. Campus estimates are not an Anthropic allocation.

Dexus September 16 regulatory disclosure via EQS ↗Assess this deal
Source ↗
May 6, 2026

Anthropic

SpaceX

Cloud compute

$1.25B/month

300+ MW

Colossus 1 compute

Location undisclosed

May 2026 (original target; later May–June ramp disclosed)

Target elapsed · confirm delivery

Agreement signed
Deal details

The May 6 announcement covers more than 300 MW at Colossus 1. SpaceX’s June 5 prospectus describes later agreements across Colossus 1 and 2: approximately 325,000 GPUs and $1.25B per month through May 2029, with reduced fees during the May–June ramp. Either party can terminate on 90 days’ notice after the initial three months. No guaranteed total or incremental MW is inferred. Orbital compute remains an expression of interest.

Hardware: 220,000+ NVIDIA GPUs

Anthropic, SpaceX compute deal ↗SpaceX June 5, 2026 prospectus, section 4.3.4.5 ↗Assess this deal
Source ↗
Apr 20, 2026

Anthropic

Amazon Web Services

Cloud compute

$100B+ · 10 years

Up to 5 GW

Trainium and related compute

Location undisclosed

Nearly 1 GW by end of 2026

Agreement signed
Deal details

Anthropic committed more than $100B over ten years to AWS technologies for up to 5 GW of new Trainium and related capacity. Nearly 1 GW is expected before the end of 2026. Amazon also announced a $5B equity investment, with up to $20B more later; those equity figures are omitted from the dollar column.

Hardware: Trainium2–4

Anthropic, Amazon compute collaboration ↗Assess this deal
Source ↗
Apr 10, 2026

Anthropic

CoreWeave

Cloud compute

Undisclosed

Undisclosed

Location undisclosed

Later in 2026

0–4 months to target

Agreement signed
Deal details

Multi-year agreement to support Claude development and deployment, with capacity starting later in 2026. No exact dollar or megawatt figure is disclosed.

Company announcement ↗Assess this deal
Source ↗
Apr 6, 2026

Anthropic

Google / Broadcom

Cloud compute

Undisclosed

5 GW

TPU compute · May 6 disclosure

Primarily United States

2027

3–16 months to target

Agreement signed
Deal details

The April 6 announcement is for multiple gigawatts of next-generation TPU capacity starting in 2027. Anthropic’s May 6 recap states a 5 GW agreement with Google and Broadcom. No public dollar figure appears on either Anthropic page. Builds on a prior October 2025 TPU-capacity increase.

Hardware: Google TPUs

Anthropic, Google and Broadcom compute partnership ↗Anthropic, May 6 capacity update ↗Assess this deal
Source ↗
Nov 18, 2025

Anthropic

Microsoft Azure / NVIDIA

Cloud compute

$30B

Up to 1 GW

Additional compute capacity

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Anthropic committed to purchase $30B of Azure compute capacity and to contract additional capacity up to 1 GW, initially on NVIDIA Grace Blackwell and Vera Rubin systems. NVIDIA and Microsoft also committed to invest up to $10B and $5B in Anthropic; those equity figures are omitted from the dollar column. Amazon remains Anthropic’s stated primary cloud and training partner.

Hardware: Grace Blackwell / Vera Rubin

Anthropic, Microsoft and NVIDIA partnerships ↗Assess this deal
Source ↗
Nov 12, 2025

Anthropic

Fluidstack

Campus build

$50B

Undisclosed

Texas and New York, US

Sites coming online through 2026

Build announced
Deal details

Anthropic announced a $50B investment in U.S. computing infrastructure, building data centers with Fluidstack in Texas and New York. The announcement says Fluidstack can deliver gigawatts of power but does not state a megawatt figure. This is an infrastructure build, not a cloud offtake.

Anthropic, $50 billion American AI infrastructure ↗Assess this deal
Source ↗