Axe Compute compute deals
Public agreements, delivery targets, and source evidence for Axe Compute.
Market overview
The commitments behind the buildout
Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.
| Layer | Stated amount | Up to | More than |
|---|---|---|---|
| Compute purchases | — | — | — |
| IT power leases | — | — | — |
| Campus projects | — | 55 MW | — |
Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.
Compute purchase agreements
—
Stated contract values, over their full terms
Additional upper-limit values
—
Additional minimum values
—
0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.
Compare buyers · 1 companies
| Buyer / developer | Agreements | Compute: stated | Compute: up to | Compute: over | Dated targets |
|---|---|---|---|---|---|
| Axe Compute | 1 | — | — | — | 0 of 1 |
Time to Power
When is capacity expected?
0 dated targets · 1 without a first-capacity window
0 elapsed targets await delivery evidence
Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.
Actual time to power: not established
Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.
No dated first-capacity targets in this selection.
How to read these dates and figures
Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 0 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.
1 announcement
| Announced | Buyer / partner | Value | Capacity | Location / timing | Details |
|---|---|---|---|---|---|
| Aug 17, 2026 | Axe Compute Duos Technologies Cloud compute | Over $500 million in aggregate contractual base payments over five years; excludes electricity and usage-based charges | Up to 55 MW Aggregate total AI facility capacity reserved across multiple sites; not disclosed as critical IT load or energized power | Multiple U.S. sites Initial project readiness targeted from late 2026 through early 2027; testing and written acceptance are required | Agreement signedDeal detailsDuos signed service orders reserving up to 55 MW of total facility capacity for Axe Compute across multiple U.S. sites. Duos supplies the facilities, power, and colocation services; Axe brings and operates the compute equipment. Initial project readiness was targeted to begin in late 2026 and continue into early 2027, subject to construction, commissioning, testing, and Axe's written acceptance. The agreements are separate from the earlier 10 MW Georgia deployment. The reported hosting payments are retained as source text and excluded from compute-purchase and infrastructure-investment totals. Axe Compute announcement of 55 MW Duos agreements ↗Duos Technologies agreement terms and capacity basis ↗Duos update on the Axe Compute relationship, October 5, 2026 ↗Assess this deal |