Microsoft / Microsoft Azure compute deal, September 2025
Announced Sep 16, 2025 · 50 MW · Undisclosed
Nscale's January 2025 UK investment announcement said the Loughton site was scheduled to be live in Q4 2026. Its later, more specific September 2025 Microsoft deployment announcement stated 50 MW of AI capacity, scalable to 90 MW, with 23,040 GB300 GPUs targeted from Q1 2027. These are separate site-readiness and customer-service targets. The Guardian reported on September 24, 2026 that UK Power Networks had reportedly told Nscale the grid would not provide sufficient power until the early to mid-2030s. Nscale said it remained committed and was investigating on-site generation and ways to accelerate the connection. The grid timing is a reported risk, not a confirmed compute delivery date or revised company target. Do not infer the facility is energized. The separate UK-wide investment plan and Stargate UK framework are not added to this site record.
First-capacity target: 23,040 NVIDIA GB300 GPUs targeted for Q1 2027; Guardian reports a material risk that grid power will not be sufficient until the early to mid-2030s
Assess the delivery assumptions
Check the site, power connection, permits, and delivery milestones behind this agreement with GreenCIO.