Microsoft / Nscale: Ward County / Cedarvale campus compute deal, October 2025

Announced Oct 15, 2025 · Undisclosed · Undisclosed

This is a site-level deployment under Nscale's approximately 200,000-GPU Microsoft agreement across four countries. The GPUs are not added to a global GPU total. Nscale's October 1, 2026 update says Ward County was live and delivering thousands of GPUs, but it does not identify them as Microsoft capacity. No dated evidence that Microsoft compute service began was verified by November 3, 2026. Ionic Digital's separate 234 MW lease is facility power, not Microsoft's compute allocation.

First-capacity target: Phased delivery of AI infrastructure services targeted from Q3 2026