RHAELM compute deals
Public agreements, delivery targets, and source evidence for RHAELM.
Market overview
The commitments behind the buildout
Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.
| Layer | Stated amount | Up to | More than |
|---|---|---|---|
| Compute purchases | — | — | — |
| IT power leases | — | — | — |
| Campus projects | — | 400 MW | — |
Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.
Compute purchase agreements
—
Stated contract values, over their full terms
Additional upper-limit values
—
Additional minimum values
—
0 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. These are purchase commitments, not annual capital expenditure.
Compare buyers · 1 companies
| Buyer / developer | Agreements | Compute: stated | Compute: up to | Compute: over | Dated targets |
|---|---|---|---|---|---|
| RHAELM | 1 | — | — | — | 1 of 1 |
Time to Power
When is capacity expected?
1 dated targets · 0 without a first-capacity window
0 elapsed targets await delivery evidence
Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.
Actual time to power: not established
Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.
2028
14–27 months away
Chiba Thermal Power Station, Chiba, Japan · Operations targeted around 2028
First compute capacity · A first phase may cover only part of the agreement.
How to read these dates and figures
Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 0 announcements disclose no MW allocation. 0 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.
1 announcement
| Announced | Buyer / partner | Value | Capacity | Location / timing | Details |
|---|---|---|---|---|---|
| Oct 1, 2026 | RHAELM JERA / Dell Technologies Campus build | >US$15B total project capital deployment across all phases; not a customer contract | Up to 400 MW Supported site power capacity; not stated critical IT load or energized compute | Chiba Thermal Power Station, Chiba, Japan Operations targeted around 2028 14–27 months to target | Build announcedDeal detailsRHAELM and JERA are developing the Chiba project; Dell contributes a standardized AI infrastructure model. The 400 MW figure is power capacity supporting the project, with no critical IT allocation or energized quantity disclosed. More than US$15B covers land, power infrastructure, facility construction and AI compute across all phases; it is project capital, not contract value. Apollo is a planned financing partner. The separate national framework and possible 2030s sites are not additional projects. RHAELM, JERA and Dell October 1 project announcement ↗RHAELM Japanese-language project announcement, October 1, 2026 ↗JERA October 1 announcement ↗Assess this deal |