All compute deals

Undisclosed buyer compute deals

Public agreements, delivery targets, and source evidence for Undisclosed buyer.

Clear filters

Market overview

The commitments behind the buildout

Selected public agreements. Amounts follow the selected filters. Compute purchases and the facilities hosting them can describe the same capacity.

Capacity by contract layer
LayerStated amountUp toMore than
Compute purchases———
IT power leases830 MW——
Campus projects———

Upper limits are not firm commitments. Minimums are not exact totals. Each column stands alone; the three layers must not be added together.

USD compute agreements

$16.7B

Stated contract values over their full terms

Additional upper-limit values

—

Additional minimum values

Over $174M

11 agreements with comparable USD values. Excludes financing, construction budgets, monthly fees, and overlapping contract updates. Full-term contract values are not annual revenue or infrastructure capital expenditure.

Compare buyers · 1 companies
Buyer / developerAgreementsCompute: statedCompute: up toCompute: overDated targets
Undisclosed buyer20———7 of 20

Time to Power

When is capacity expected?

7 dated targets · 13 without a first-capacity window

Assess a site →

0 elapsed targets await delivery evidence

Delivery confirmation is still needed for these records. An elapsed target alone does not establish a delay.

Actual time to power: not established

Company targets describe expected availability. Measured time to power requires a dated start and site-level energization evidence.

Reported delivery

QumulusAI / Undisclosed buyer · MW undisclosed · final b300 handoff completed october 1; all gpus under the agreement in production and billing

QumulusAI says B200 handoff occurred September 8 and final B300 handoff at its Kansas City site occurred October 1. It does not state agreement-specific MW. The release separately reports portfolio totals of 7 MW active, 1 MW energized but awaiting customer handoff, and 3.75 MW at Atlanta targeted for early 2027; these values are not allocated to this customer.

Company update · 2026-10-15 ↗

QumulusAI / Undisclosed buyer · MW undisclosed · full customer handoff in philadelphia; agreement live and in production

QumulusAI reports full handoff on September 1 at its Philadelphia colocation site. The GPU count, site MW, IT load, and utility energization date are undisclosed.

Company update · 2026-09-10 ↗

Sharon AI / Undisclosed buyer · MW undisclosed · initial ai cloud deployment delivered and accepted by customer

Sharon AI says the customer accepted an initial deployment under the five-year agreement. The release does not identify the specific site, GPU count, customer MW, or utility energization date.

Company update · 2026-08-20 ↗

MEEZA / Undisclosed buyer · 4 MW ready-for-service certificate signed; facility handed over on june 21, 2026

MEEZA confirms delivery of the 4 MW expansion to the unnamed hyperscaler. This is project capacity; IT-load versus facility-power basis remains undisclosed.

Company update · 2026-07-01 ↗

2026

Delivery reported

Undisclosed buyer / Undisclosed AI inference platform

Site not disclosed · Q3 2026 target; B200 handoff September 8 and final B300 handoff October 1

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

0–2 months away

Undisclosed buyer / Undisclosed California neocloud provider

Michigan, United States · November 2026 target in September 17 update; not yet confirmed operational

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2026

1–3 months away

Undisclosed buyer / Undisclosed generative-AI inference platform

Site not disclosed · Capacity turnover expected in December 2026; no dated delivery or energization evidence

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Undisclosed buyer / Undisclosed AI inference platform

Metro Atlanta, Georgia, United States · Capacity turnover targeted for early 2027; no dated delivery or energization evidence

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Undisclosed buyer / Applied Digital

Boyce, Louisiana, US · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2027

2–15 months away

Undisclosed buyer / Applied Digital

United States; state not identified in cited release · 2027

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →

2028

14–21 months away

Undisclosed buyer / Applied Digital

Southern United States; state undisclosed · First half of 2028

First compute capacity · A first phase may cover only part of the agreement.

Assess delivery →
How to read these dates and figures

Dates are the original announced windows. A vague year keeps a full-year range; construction completion and equipment release dates are excluded. 12 announcements disclose no MW allocation. 4 quantified records are excluded from capacity comparisons because their scope is not comparable or overlaps. Export the CSV for the source, quantity terms, and inclusion basis of each agreement.

20 announcements

Download CSV
AI compute deals, newest announcements first
AnnouncedBuyer / partnerValueCapacityLocation / timingDetails
Sep 29, 2026

Undisclosed buyer

Undisclosed AI inference platform

Cloud compute

$211.9M · Three-year take-or-pay agreement; two one-year extensions are optional and excluded from the stated value

Undisclosed

More than 2,000 B300 GPUs across both September 29 agreements; per-customer GPU quantity and IT-load allocation are undisclosed. The 3.75 MW Atlanta site capacity is not assigned as customer IT load.

Metro Atlanta, Georgia, United States

Capacity turnover targeted for early 2027; no dated delivery or energization evidence

2–15 months to target

Agreement signed
Deal details

QumulusAI reports a three-year take-or-pay agreement worth US$211.9 million with a returning AI inference platform customer. It says the deal follows that customer's separate US$71.9 million agreement and targets capacity turnover in early 2027. The source combines GPU counts across this and another contract and does not disclose this customer's count. Two optional one-year extensions worth US$70.6 million each are excluded. The associated Atlanta site's up-to 3.75 MW is data-center capacity, not a disclosed customer IT allocation, and its MW basis is unknown.

Hardware: NVIDIA Blackwell B300 GPUs; exact customer allocation undisclosed

QumulusAI, US$240.9 million in two new customer contracts ↗Related: Undisclosed buyer / Undisclosed AI inference platform · 2026-07-28Assess this deal
Source ↗
Sep 29, 2026

Undisclosed buyer

Undisclosed generative-AI inference platform

Cloud compute

$29.1M · Three-year agreement; a two-year extension option worth US$19.4 million is excluded from the stated value

Undisclosed

More than 2,000 B300 GPUs across both September 29 agreements; per-customer GPU quantity and MW allocation undisclosed

Location undisclosed

Capacity turnover expected in December 2026; no dated delivery or energization evidence

1–3 months to target

Agreement signed
Deal details

QumulusAI reports a three-year agreement worth US$29.1 million with a returning generative-AI inference platform customer. It says the deal follows a separate two-year agreement worth more than US$32 million. Customer GPU quantity and MW are undisclosed; the September announcement gives more than 2,000 B300 GPUs combined across this and another new agreement. A two-year extension option worth US$19.4 million is excluded. December 2026 turnover is a target, not delivery evidence.

Hardware: NVIDIA Blackwell B300 GPUs; exact customer allocation undisclosed

QumulusAI, US$240.9 million in two new customer contracts ↗Related: Undisclosed buyer / Undisclosed generative-AI inference platform · 2026-07-23Assess this deal
Source ↗
Sep 7, 2026

Undisclosed buyer

MEEZA

Cloud compute

More than QAR 1 billion; contract term not disclosed

8 MW

Operational data centre services capacity at a planned campus; source does not define IT-load versus facility-power basis

Qatar; campus name not disclosed

No delivery date disclosed

Agreement signed
Deal details

MEEZA announced a long-term lease with an unnamed global hyperscaler for 8 MW of data centre services at an upcoming campus. MEEZA valued the agreement at more than QAR 1 billion. The customer, contract term, site name, delivery date, and IT-load versus facility-power basis are not disclosed. Keep its capacity and native-currency value out of aggregates. This is a separate announced contract, but the unnamed customer prevents overlap checks against the other MEEZA hyperscaler records.

MEEZA hyperscaler agreement for 8 MW ↗Data Center Dynamics reports MEEZA's 8 MW lease ↗MEEZA announcement reproduced by Mubasher ↗Assess this deal
Source ↗
Sep 1, 2026

Undisclosed buyer

Green Mountain

Campus build

Undisclosed

14 MW

Data centre capacity; IT versus facility power not specified

LON-East, Romford, London, UK

Capacity described as recently delivered; customer occupancy date undisclosed

Agreement signed
Deal details

An unnamed neocloud operator contracted 14 MW within the 37 MW LON-East campus. Company-reported facility delivery does not establish customer occupancy or a utility energization date. Price and term are undisclosed. The campus total is not the customer allocation.

Green Mountain September 1 company announcement ↗Assess this deal
Source ↗
Aug 31, 2026

Undisclosed buyer

E2E Networks

Cloud compute

Approx. INR 1,000 crore (excluding taxes)

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Binding term sheet with an unnamed sovereign AI company based in India for Blackwell cloud GPUs and allied services. Customer identity is undisclosed; do not attribute the order to Sarvam. Site, MW, GPU count and first-service date are undisclosed. Original INR value is retained without currency conversion.

Hardware: NVIDIA Blackwell cloud GPUs; count undisclosed

E2E Networks August 31 binding term sheet filing ↗Assess this deal
Source ↗
Aug 24, 2026

Undisclosed buyer

Undisclosed U.S. cloud customer

Cloud compute

$13.7B · Six-year commercial agreement; approximately US$13.7 billion for three initial GPU-service tranches; later expansion agreements are unpriced

Undisclosed

Customer GPU-services allocation and site MW undisclosed

Maysville, Georgia, United States

Maysville site is under development; no first-delivery date stated. The customer must approve the proposed delivery date for the third tranche.

Agreement signed
Deal details

RUM Group's August 24 SEC filing confirms a six-year GPU-services agreement with an unnamed US cloud customer at its Maysville site, then under development. The three initial tranches have an approximately US$13.7 billion total order value, spread evenly across the tranches. The customer must review and accept RUM's proposed delivery date for the third tranche before obligations for that tranche apply. The filing does not name the customer; The Information reports Anthropic, but that attribution is not confirmed by the filing or a company announcement. It states no MW, GPU count, first-delivery date, or utility energization date. RUM said it did not yet have financing for the required development and equipment when it filed; no financing condition applies to its agreement. Expansion agreements are possible but unpriced and are not included.

Hardware: GPU access and GPU services; model and quantity undisclosed

RUM Group Form 8-K, August 23 GPU-services agreement ↗The Information reports that Anthropic is the customer; the SEC filing does not identify it ↗Assess this deal
Source ↗
Aug 4, 2026

Undisclosed buyer

Undisclosed global AI platform

Cloud compute

$373M · Cloud computing services over five years

Undisclosed

Initial 2,048 B300 GPUs; customer MW allocation undisclosed. Sharon AI's 132 MW company-wide capacity and 120 MW contracted across customers are not allocated to this agreement.

Australia

Revenue expected to commence in Q1 2027; source does not give a distinct first-compute or energization date

Agreement signed
Deal details

Sharon AI reports a five-year cloud service agreement with an unnamed global AI platform. The initial deployment is expected to use 2,048 NVIDIA B300 GPUs, with revenue expected from Q1 2027. Sharon AI's 132 MW AI Factory capacity and 120 MW contracted across end customers are not allocated to this agreement. Revenue timing does not establish a first-compute or energization date.

Hardware: Initial deployment of 2,048 NVIDIA Blackwell Ultra B300 GPUs

Sharon AI Form 8-K exhibit, US$373 million customer agreement ↗Assess this deal
Source ↗
Jul 28, 2026

Undisclosed buyer

Undisclosed AI inference platform

Cloud compute

$71.9M · Three-year agreement with renewal options

Undisclosed

B200 and B300 capacity; GPU quantity and customer MW allocation undisclosed

Location undisclosed

Q3 2026 target; B200 handoff September 8 and final B300 handoff October 1

Delivery reported

In use at announcement
Deal details

QumulusAI first expected capacity for customer use in Q3 2026. It later reported B200 handoff on September 8 and B300 handoff at its Kansas City site on October 1; on October 15 it said all GPUs under the agreement were in production and billing. The agreement reached service after its Q3 target. Customer MW and utility energization are undisclosed. QumulusAI's separate portfolio MW figures are not assigned to this customer.

Hardware: NVIDIA Blackwell B200 and B300 GPUs

QumulusAI three-year AI inference agreement ↗QumulusAI reports full B200 handoff ↗QumulusAI reports final B300 handoff and production billing ↗Related: Undisclosed buyer / Undisclosed AI inference platform · 2026-09-29Assess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

300 MW

Critical IT load

Boyce, Louisiana, US

2027

2–15 months to target

Agreement signed
Deal details

Delta Forge 1: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 results ↗Assess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

210 MW

Critical IT load

Southern United States; state undisclosed

First half of 2028

14–21 months to target

Agreement signed
Deal details

Delta Forge 2: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 results ↗Assess this deal
Source ↗
Jul 27, 2026

Undisclosed buyer

Applied Digital

Campus build

Undisclosed

300 MW

Critical IT load

United States; state not identified in cited release

2027

2–15 months to target

Agreement signed
Deal details

Polaris Forge 3: 15-year take-or-pay lease with an unnamed US hyperscaler. Date is the results disclosure, not the undisclosed signing date. Each campus is a separate lease; customer identity is not inferred. Hosting revenue is not included in compute purchase values.

Applied Digital July 27 results ↗Assess this deal
Source ↗
Jul 23, 2026

Undisclosed buyer

Undisclosed generative-AI inference platform

Cloud compute

$32M+ · Two-year agreement with renewal options

Undisclosed

Dedicated B300 GPU clusters; GPU quantity and customer MW allocation undisclosed

Location undisclosed

Capacity expected in fall 2026; no dated delivery evidence found

Agreement signed
Deal details

QumulusAI reports a two-year agreement worth more than US$32 million for dedicated Blackwell B300 clusters serving a generative-AI inference platform. The September 29 US$29.1 million agreement is a separate second commitment by the same customer. The original fall 2026 target remains unverified; the later agreement's December target does not prove delivery of this tranche.

Hardware: NVIDIA Blackwell B300 GPU clusters

QumulusAI generative-AI inference agreement ↗Related: Undisclosed buyer / Undisclosed generative-AI inference platform · 2026-09-29Assess this deal
Source ↗
Jul 22, 2026

Undisclosed buyer

Undisclosed GPU cloud marketplace

Cloud compute

$18M+ · Two-year take-or-pay agreement

Undisclosed

NVIDIA B300 GPU capacity; quantity and customer MW allocation undisclosed

Philadelphia, Pennsylvania, United States

Customer handoff completed September 1, 2026

In use at announcement
Deal details

QumulusAI reports a two-year take-or-pay agreement worth more than US$18 million with an unnamed GPU marketplace. Its September 10 release says the full Blackwell B300 deployment was handed to the customer on September 1 at the Philadelphia colocation site. GPU count and MW are not disclosed; operational handoff does not give a utility energization measurement.

Hardware: NVIDIA Blackwell B300 nodes

QumulusAI marketplace agreement announcement ↗QumulusAI confirms full handoff in Philadelphia ↗Assess this deal
Source ↗
Jul 16, 2026

Undisclosed buyer

Undisclosed global AI lab

Cloud compute

$1.3B · Cloud computing services over five years

Undisclosed

Customer-specific MW and GPU allocation undisclosed; reported 116 MW of company-wide contracted capacity is not allocated to this agreement

New Zealand

Cloud deployments planned in New Zealand; revenue expected across Q1 and Q2 2027, with no distinct first-compute date stated

Agreement signed
Deal details

Sharon AI reports a five-year cloud computing agreement with an unnamed global AI lab. It plans deployments across data center infrastructure in New Zealand and expects revenue to begin in Q1–Q2 2027. That revenue window is not reported as a first compute or power date. Sharon AI's 132 MW AI Factory capacity and 116 MW contracted to customers are company-wide amounts, not this customer's allocation.

Sharon AI Form 8-K exhibit, US$1.32 billion customer agreement ↗Assess this deal
Source ↗
Jun 24, 2026

Undisclosed buyer

Undisclosed California neocloud provider

Cloud compute

More than $1.2 billion in expected revenue over the maximum 20-year term; more than $3.0 billion only if the customer exercises expansion to 52 MW and both extension options

20 MW

Initial critical AI compute capacity under the MSA; not campus power or confirmed energized capacity

Michigan, United States

November 2026 target in September 17 update; not yet confirmed operational

0–2 months to target

Agreement signed
Deal details

The June 24 MSA covers an initial 20 MW of critical AI compute capacity and gives the customer an option to expand to 52 MW. The September 17 update says operations are targeted to begin in November 2026 and that more than $70 million had been invested as of September 15; neither statement confirms delivery. The approximately 340 MW figure is total potential campus capacity, subject to power, infrastructure, financing, and regulatory approvals, and is not included here. Contract revenue is conditional on the maximum term and is not recorded as compute-purchase value or capital expenditure.

Hyperscale Data MSA for Michigan AI compute capacity ↗Hyperscale Data September 17 delivery and investment update ↗Assess this deal
Source ↗
Jun 11, 2026

Undisclosed buyer

Hyperbolic and one unnamed AI inference platform

Cloud compute

$124M+ · Two customer agreements with three-year terms; the announcement reports their combined value

Undisclosed

1,280 NVIDIA Blackwell GPUs across two customer agreements; per-customer GPU counts and MW are undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

QumulusAI reports more than US$124 million in two three-year customer agreements, one with Hyperbolic and one unnamed AI inference platform. The source states that the agreements support 1,280 Blackwell GPUs and include nearly US$21.9 million in combined upfront commitments. It does not allocate contract value or GPUs by customer, so this combined announcement is one record. The figure is counted once; later customer-specific agreements are separate commitments.

Hardware: 1,280 NVIDIA Blackwell GPUs across both agreements

QumulusAI, two AI inference infrastructure agreements ↗Assess this deal
Source ↗
May 14, 2026

Undisclosed buyer

Undisclosed global technology company

Cloud compute

$950M · Initial contract value over five years; take-or-pay

Undisclosed

Customer-specific MW and GPU allocation undisclosed; Sharon AI's company-wide secured and contracted capacity is not allocated to this agreement

Multiple data centers in Australia

Initial deployment accepted August 20, 2026; additional clusters expected over the following months

Agreement signed
Deal details

Sharon AI reports an approximately US$950 million five-year take-or-pay cloud infrastructure agreement with an unnamed global technology company. Its August 20 release confirms that the customer accepted an initial deployment, with more NVIDIA GPU clusters expected in the following months. Sharon AI's reported company-wide secured and contracted MW are not allocated to this customer. Customer MW, GPU count, exact site, and utility energization date are unknown.

Hardware: NVIDIA GPU clusters; model and quantity undisclosed

Sharon AI Form 8-K exhibit, five-year customer agreement ↗Sharon AI reports initial deployment accepted ↗Assess this deal
Source ↗
Apr 29, 2026

Undisclosed buyer

E2E Networks

Cloud compute

$7.7M · Six months

Undisclosed

Location undisclosed

No delivery date disclosed

Agreement signed
Deal details

Executed agreement with an unnamed US AI service provider specialising in large-scale model training. Committed value covers GPU cloud computing and allied services for six months. Customer identity, site, GPU count, MW and service commencement are undisclosed.

E2E Networks April 29 exchange filing ↗Assess this deal
Source ↗
Oct 28, 2025

Undisclosed buyer

MEEZA

Cloud compute

More than QAR 750 million; contract term not disclosed

6 MW

Phase-one data centre services capacity; source does not define IT-load versus facility-power basis

Qatar; site name not disclosed

No delivery date disclosed

Agreement signed
Deal details

MEEZA announced a lease with an unnamed global hyperscaler for 6 MW of data centre services as phase one, with capacity intended for cloud and AI workloads. The company stated a value above QAR 750 million. Customer, site, contract term, delivery date, and IT-load versus facility-power basis are not stated. Do not add this capacity or native-currency value to USD totals. The unnamed customer prevents overlap checks against MEEZA's other hyperscaler contracts.

MEEZA global hyperscaler agreement for 6 MW, Qatar Exchange filing ↗Qatar Exchange filing ↗Assess this deal
Source ↗
Jul 1, 2025

Undisclosed buyer

MEEZA

Cloud compute

More than QAR 350 million over a term exceeding 10 years

4 MW

Data centre expansion capacity; source does not identify whether 4 MW is IT load or total facility power

Qatar

No delivery date disclosed

Agreement signed
Deal details

MEEZA announced a long-term agreement with an unnamed global hyperscaler to use a 4 MW data centre expansion. MEEZA valued the contract at more than QAR 350 million over more than ten years. On July 1, 2026, MEEZA said the expansion was handed over on June 21 after signing a ready-for-service certificate. The source does not name the customer or define the MW basis; retain the native currency and exclude 4 MW from power aggregates until the basis is known.

MEEZA global hyperscaler agreement ↗MEEZA confirms handover and ready-for-service milestone ↗Assess this deal
Source ↗